Follow the Money

Backer profile · Developer

J.G. Petrucci Co.

J.G. Petrucci Co. is a privately held developer and design-build company in Asbury, New Jersey, founded in 1987, that says it has built more than six million square feet and owns and manages about 3.5 million square feet in three states. With Peron Development, it confirmed in February 2026 that it's working on a data center campus in Lower Mount Bethel Township, Northampton County, near Talen Energy's power plants. After strong local opposition, a petition to rezone about 239 acres there from agricultural to industrial use is before the township, and no conditional use or land development application has been filed. In August 2026 it filed plans for a data center at 1024 N. Bradford Street in Allentown, beside Coca-Cola Park, on a site that DatacenterDynamics says was approved in 2022 for its Allentown Flex Center industrial building.

Baxtel reported in August 2026 that J.G. Petrucci submitted plans for a 100 megawatt, 146,000 square foot data center and substation at 1024 N. Bradford Street in Allentown.

Scoreboard

2

Pennsylvania projects on our map

  • 2 proposed, under review or on appeal

Developer: 2

Lower Mount Bethel Tech CenterAllentown Flex Center Data Center (J.G. Petrucci, 1024 N. Bradford Street, beside Coca-Cola Park)
Approved or built0
In process2
Stopped0
Megawatts named1,300 MWpublished for 2 of 2
Building area named146,000 sq ftpublished for 1 of 2
Land involved239 acrespublished for 1 of 2
Investment announced$5.0 billionpublished for 1 of 2
Permanent jobs claimed500claimed for 1 of 2
Counties2Lehigh, Northampton
Earliest project2026first public announcement
Local groups opposing2across its projects
Legal filings1appeals, challenges and suits on file
Community impacts11documented on its projects
News stories12in our coverage log

Projects

ProjectStatusRoleSize named
Allentown Flex Center Data Center (J.G. Petrucci, 1024 N. Bradford Street, beside Coca-Cola Park)City of Allentown, Lehigh CountySuggest a correction Application Filed Developer 100 MW
146,000 sq ft
Lower Mount Bethel Tech CenterLower Mount Bethel Township, Northampton CountySuggest a correction Application Filed Developer 1,200 MW

Sources

Project details, statuses and figures come from each project’s own profile, which lists its sources.

Help stop the 900 Conshohocken Road data center.

Corrections and additions

Are you with one of these organizations?

If something here is wrong, out of date or missing, tell us. We read every submission, check it against the public record or the documents you send, and update the page when it’s supported. You can also send context you’d like considered, such as a change in ownership, a project you’ve left, or your organization’s response.

Submissions go privately to our volunteer team. If we change a page because of one, we note it on that page. Questions can also go to noconshydatacenters@proton.me.

OrganizationJ.G. Petrucci Co.

What are you sending?