Local, regional, and trade coverage of the 900 Conshohocken Road data-center proposal, newest first. The latest: Plymouth Township Council says the developer rejected all forty-three of its proposed safeguards and has filed a challenge to the township zoning ordinance itself. Testimony begins Thursday, August 6.

He rejected all 43 safeguards. Now he’s trying to remove residents from the decision entirely.

Give Council its due first, because it earned some today.

Five members went on the record, together, opposing this application. They put forty-three specific conditions in front of the developer, and they published all forty-three so residents can read them. Some of that work is genuinely good. A 500-foot separation for mechanical equipment. A 100-foot planted buffer. Noise limits written down to 16 hertz, which is the frequency range that actually keeps people awake. A decommissioning bond. A public monitoring portal. Somebody did real homework on that list, and residents who spent the last year raising these exact issues should recognize their own fingerprints on it.

Council President Lynne Viscio said, “Although the applicant rejected these conditions and safeguards, we are not backing down.” Ward 1’s William Winchester Jr., whose ward this is, said, “It is unfortunate that Mr. O’Neill has refused these measures and assurances.”

That is a Township Council in opposition, and that is worth something on August 6.

Now the part that should worry everyone.

What he filed

Council writes that the applicant has now filed a second application challenging the validity of the Township’s zoning ordinance, and describes it this way:

“This is a blatant attempt by the Applicant to demand approval by tantrum. The Township will not entertain such theatrics.”

Residents should understand this differently, because it is not theatrics and it is not a bluff.

A substantive validity challenge under Section 916.1 of the Pennsylvania Municipalities Planning Code is the mechanism for attacking a zoning ordinance itself rather than arguing about one application under it. If it succeeds, Section 1006-A allows a court to order the described development approved. A court reviewing that challenge owes no deference to the Zoning Hearing Board or to Council. The Commonwealth Court has said the paramount concern the legislature expressed in that section is to provide a successful challenger with some measure of relief, and that a court declining the relief requested has to consider what alternative relief it can grant instead. The burden shifts to the Township to prove the project is incompatible with its existing, generally applicable rules.

Read plainly, that is an attempt to move this decision out of a room where residents have party status, where neighbors can cross-examine, and where a five-member local board answers to the community, and into a courtroom where none of that applies.

That is the story today. Everything else is context.

The question that is still unanswered

Nine days ago, MoreThanTheCurve asked all five Council members a direct question. Between November 17, 2025, when the first application was withdrawn, and April 19, 2026, when the second one was dated, there was roughly a five-month stretch with no application pending against this property. Section 609.2 of the Planning Code lets a township declare its own zoning ordinance substantively invalid, take a 180-day pause, and write proper rules while shielded from landowner challenges. Montgomery Township used it in March. Doylestown Township, West Whiteland and Lancaster Township all did the same. Montgomery and Chester Counties jointly published a Data Center Ordinance Guide in April with model language ready to adopt. Whitemarsh is drafting from it right now. Tredyffrin authorized amendments with no application pending anywhere in the township.

Council did not respond to that question. It also did not respond when asked whether anyone from the Governor’s administration had been in contact about data centers.

Today’s statement contains what appears to be the answer to the first one:

“As the Township already had a mechanism to review and process the data center use, there was no necessity for the Township to develop a stand-alone data center ordinance for the nascent and emerging use.”

Residents disagreed with that judgment at the time, and this week is the argument for why. An ordinance is law. It binds regardless of whether the developer agrees to it. The forty-three demands were presented instead as a memorandum of understanding, which is a two-signature document, and the developer declined to sign. Council was left holding a list with no legal force behind it.

There is a reason to believe an ordinance would have worked. In Upper Merion, where this same developer has five data center applications in land development, he agreed to abide by some of the stricter provisions of an ordinance that township adopted after his applications were already filed. He complied with a law. He walked away from a request. The difference between those two instruments is the difference we are living with now.

Council does not owe anyone an apology for that. It does owe residents a straight answer, in writing, about what it will do differently, because Plymouth Township has other industrial parcels and this will not be the last application.

What belongs in the record on August 6

The forty-three demands are strong on noise and thin in one place that matters. Demand 26 requires that “All generators shall meet or exceed Tier 4 emissions standards.” Tier 4 is a federal standard for compression-ignition engines. The EPA’s own definition of a stationary internal combustion engine excludes combustion turbines, which fall under a different rule entirely. So that condition reaches the backup diesels that run occasionally and does not reach the gas turbines that would run around the clock. Across all forty-three items there is no megawatt cap, no limit on the number of turbines, no ceiling on annual operating hours, and no numeric nitrogen oxide or fine particulate limit at the property line. Demand 22 goes further and requires that the project “shall be power self-sufficient through on-site power generation,” which locks the power plant in.

Those are fixable gaps, and the hearing is where they get fixed. Parties with standing should put the megawatt figure, the turbine count, the operating hours, and property-line air limits into the record, under oath, with the applicant’s own witnesses on the stand.

What to ask for

Publish the validity challenge. The filing date, where it was filed, and the grounds asserted. Residents cannot evaluate any of this until they can read it.

Answer the five-month question plainly, including whether legal advice shaped the decision.

Adopt a data center ordinance regardless of what happens here, because the rest of the township is still unprotected.

And be at Colonial Middle School on August 6.

Be there August 6 Fund the fight

All Coverage

Press, opinion, local reporting.

Newest first. Some sources are paywalled, links go to the publisher.

Patch Jul 27, 2026
Township

'Demanding Approval By Tantrum': Plymouth Twp. Council Calls Out Data Center Developer

Council discloses that the developer rejected all forty-three proposed health and safety conditions and filed a challenge to the validity of the township's zoning ordinance. The full condition list is published with the story.

NBC10 Philadelphia Jul 27, 2026
News

Plymouth Township rejects data center after several proposals and 'temper tantrum'

Broadcast coverage of the July 27 council statement, including Council President Lynne Viscio on the applicant's ordinance challenge.

MoreThanTheCurve Jul 22, 2026
Analysis

No response from Plymouth Township's council when asked about the 180-day moratorium option

The five-month stretch between November 17, 2025 and April 19, 2026 when no application was pending and Section 609.2 was available to the township.

MoreThanTheCurve Jul 16, 2026
Borough

Borough of Conshohocken will seek party status for zoning hearing involving proposed data center

Council agrees to seek party status, with the formal vote set for August 5; borough solicitor Michael Peters of Eastburn & Gray will represent Conshohocken before the board.

MoreThanTheCurve Jul 14, 2026
Hearing

Zoning hearing in Plymouth Township for data center to be continued from July 28th to August 6th

The township announces the continuance: the board convenes July 28 only to vote it, and testimony begins Thursday, August 6 at 7 p.m. at Colonial Middle School.

MoreThanTheCurve Jul 13, 2026
Borough

Petition encourages Conshohocken's borough council to seek party status in data center zoning hearing

A resident-launched petition ahead of the July 15 council meeting asks the borough to intervene and oppose the project.

Metro Philadelphia Jun 2026
News

Battle begins over proposed data center in Plymouth Township

Metro's feature on the opening of the zoning fight: the demonstration outside Colonial Middle School, the party-status battle, and the developer's wider multi-site data center push in the region.

MoreThanTheCurve Jun 26, 2026
Hearing

Zoning hearing for proposed data center in Conshohocken kicks off in Plymouth Township

The June 25 recap: no testimony taken, and party status granted to the township, the Borough of Conshohocken Authority, and twelve residents.

PHL17 Jun 24, 2026
News

Neighbors oppose data center proposed in Plymouth Township ahead of zoning meeting

On the eve of the hearing, WPHL talks with neighbors who rallied against the project, citing the cumulative effect of noise and pollution on the river and a community plan that called for green space and amenities, not a data center.

Plymouth Township Jun 22, 2026
Township

Livestream available for the June 25, 2026 Zoning Hearing Board meeting

The township confirms the special meeting begins at 7 p.m. at Colonial Middle School and that residents may attend in person or observe the hearing remotely by livestream.

Patch Jun 17, 2026
Hearing

First hearing on Plymouth Twp. data center coming up

A preview of the June 25 hearing, noting that a broad, bipartisan opposition is urging residents to turn out and make their voices heard as the application returns to the Zoning Hearing Board.

MoreThanTheCurve Jun 11, 2026
Analysis

Plymouth Township's council released a statement on the data center. See what questions they chose not to answer

Covers the council's opposition statement, then presses three questions the township left unanswered: why it has not begun a data center ordinance, whether it will act on the county's 42-acre quarry listing on Conshohocken Road, and whether it wanted that sale delayed.

Patch Jun 10, 2026
Township

Plymouth Twp. Council Opposes Data Center, Cites Threat To Health And Safety

Council formally opposes the application as submitted and authorizes the Township Solicitor to argue against it before the Zoning Hearing Board, calling for enforceable safeguards for residents, infrastructure, and emergency responders.

Patch Jun 2026
Hearing

First hearing date set for Plymouth Twp. data center proposal

The township confirms the first Zoning Hearing Board session for June 25 at 7 p.m. at Colonial Middle School, a larger venue chosen to accommodate the crowds the project has been drawing.

MoreThanTheCurve Jun 2026
Local

Zoning hearing for the proposed data center to be held June 25th

The township confirms the first hearing for June 25 at Colonial Middle School, expected to span several dates, with party-status requests and initial testimony at the opening session.

MoreThanTheCurve May 2026
Local

No official role for Plymouth Township's Environmental Advisory Board in the hearing

The township's EAB advises Council, not the Zoning Hearing Board, and has no formal role in the special-exception process, leaving the evidentiary record to the parties.

MoreThanTheCurve May 8, 2026
Opinion

The proposed data center in Conshohocken. What (we think) you should know

A local explainer of the special-exception standard, the burden of proof, the closed-loop water claim, and the on-site gas turbines, with the author's own ambivalence about AI throughout.

Philadelphia Inquirer May 6, 2026
News

Controversial AI data center proposal has been resurrected outside Conshohocken

O'Neill resubmits the 2-million-square-foot plan six months after the first was withdrawn. More than 1,300 people have now signed a petition opposing it over light, noise, air, water, and electricity costs.

Montco Today May 5, 2026
Local

Conshohocken data center fight reignites with new application

A second attempt at the former Cleveland-Cliffs site, again requiring a special exception in the Heavy Industrial district, revives the debate over infrastructure, noise, and local impact.

Chestnut Hill Local May 2026
Local

Developer proposes another hyperscale data center in Montco

MLP Ventures founder Brian O'Neill resubmits to the zoning hearing board. The piece situates the proposal within the AI-driven national data-center boom and the local pushback against it.

MoreThanTheCurve May 1, 2026
Local

Zoning application for data center at former steel plant submitted to Plymouth Township

First report of the May 1 re-filing. State law requires a hearing within 60 days; the township says it will use the full window to prepare for anticipated public interest.

Plymouth Township May 1, 2026
Township

Plymouth Township receives zoning hearing board application for proposed data center

The township's official statement on the second application, explaining the special-exception standard and the Zoning Hearing Board's role as a quasi-judicial body weighing evidence and testimony.

Chestnut Hill Local Feb 11, 2026
Local

Residents call for data center moratorium in Plymouth Township

Patti Smith launches a petition urging newly elected officials to pass a data-center moratorium, giving the township time to write regulations before more proposals arrive.

Data Center Dynamics Oct 2025
Industry

Plymouth Township planning agency votes not to recommend data center proposal

The agency votes 4-0 against recommending a special exception for the 66-acre site, noting that the Heavy Industrial designation does not currently cover data-center uses.

6abc / WPVI Nov 18, 2025
News

Developer withdraws Plymouth Township data center plan after legal issue halts meeting

Less than an hour into the hearing, a party raised that the applicant lacked legal standing because the agreement of sale with Cleveland-Cliffs was not finalized. The application was withdrawn.

Patch Nov 2025
Local

Vote on controversial Montco data center suddenly halted Monday night

A massive crowd of opponents turned out for the expected vote, which never happened after the developer withdrew over the standing question. Opponents called it the smallest of wins.

Philadelphia Inquirer Oct 3, 2025
News

Main Line developer is planning AI data center in Plymouth Township

First detailed public report on the proposal: 2 million square feet, 10 buildings, 66 acres, on-site gas turbines, and an undisclosed tenant.

WHYY Oct 2025
News

Conshohocken-area residents push back on data center proposal

Reporting from the early hearings, with Connaughtown residents roughly 200 feet from the property line voicing concerns about noise, air, and water.

BISNOW Oct 2025
Industry

Conshohocken data center proposal fields pushback

Industry coverage of the project, the Cleveland-Cliffs steel-mill site history, and the developer's pivot from earlier mixed-use concepts for the parcel.

Help us keep the record.

The hearing will be decided on what is documented, not what is posted. Sign up to volunteer, or to underwrite expert testimony.

Fund the fight.

Community-funded legal counsel, expert witnesses, and transcripts. Every dollar goes on the record.

Donate on GoFundMe →