Follow the Money

Backer profile · Investor or lender

IFM Investors

An infrastructure investment manager that took Switch private with DigitalBridge in December 2022.

Scoreboard

1

Pennsylvania project on our map

  • 1 proposed, under review or on appeal

Owner: 1

Switch Data Center Campus (former Pittsburgh International Race Complex)
Approved or built0
In process1
Stopped0
Building area named647,250 sq ftpublished for 1 of 1
Land involved384 acrespublished for 1 of 1
Investment announced$1.4 billionpublished for 1 of 1
Permanent jobs claimed80claimed for 1 of 1
Water, maximum0.009 million gal/daypublished for 1 of 1
Counties1Beaver
Earliest project2026first public announcement
Local groups opposing2across its projects
Legal filings2appeals, challenges and suits on file
Community impacts7documented on its projects
News stories20in our coverage log

Projects

ProjectStatusRoleSize named
Switch Data Center Campus (former Pittsburgh International Race Complex)Big Beaver Borough, Beaver CountySuggest a correction Under Review Owner 647,250 sq ft

Sources

Project details, statuses and figures come from each project’s own profile, which lists its sources.

Help stop the 900 Conshohocken Road data center.

Corrections and additions

Are you with one of these organizations?

If something here is wrong, out of date or missing, tell us. We read every submission, check it against the public record or the documents you send, and update the page when it’s supported. You can also send context you’d like considered, such as a change in ownership, a project you’ve left, or your organization’s response.

Submissions go privately to our volunteer team. If we change a page because of one, we note it on that page. Questions can also go to noconshydatacenters@proton.me.

OrganizationIFM Investors

What are you sending?