- Developer
- Switch, Ltd. of Las Vegas (founder and CEO Rob Roy), which DigitalBridge and IFM Investors took private in December 2022. Natalie Stewart Mitchell, senior vice president of government affairs and campus development, and Steven Roberts, vice president of construction development, present the project; General Counsel Scott Hettema signed the county application. Attorney Alan T. Shuckrow of Strassburger McKenna Gutnick & Gefsky represents Switch, and Atwell, LLC is the civil engineer. The land is held by Wampum I, LLC, which Provident Data Centers president Julian Hawes signed for at the March 2026 purchase and which Switch's filings now show as its wholly owned subsidiary.
- Tenant
- No tenant has been named. Switch says it designs, builds and operates campuses for AI, cloud and enterprise customers, and its April 2026 announcement pitched the site's fiber connections to finance, healthcare, higher education and government organizations.
- Current stage
- Preliminary land development review as of October 26, 2026. Switch filed July 7, 2026 and revised its plans September 4, and the borough engineer's October 11 review letter lists open zoning and land development items. Switch's plans were on the October 22 agenda of the borough Planning Commission, which wasn't scheduled to act on them, and the presentation Switch posted for that meeting describes three buildings of about 215,000 square feet each, air-cooled closed-loop chillers, one Tier 4 backup generator per building and a will-serve letter from the Beaver Falls Municipal Authority for up to 7,200 gallons of water a day. The Beaver County Planning Commission commented on the first plans August 18 and is reviewing the revision. DEP's tracker shows the Chapter 102 construction stormwater permit (PAC040210) pending since July 9, 2026, with the air quality plan approval for the generators, a storage tank permit and Act 537 sewage planning not yet submitted, and the Beaver County Conservation District gave Switch until November 4, 2026 to resubmit the stormwater application.
- Decision body
- Big Beaver Borough Council grants preliminary and then final land development approval after review by the borough engineer and zoning officer, the borough Planning Commission and the Beaver County Planning Commission, whose review is advisory. Data centers are a permitted use with special regulations in the Industrial district, so no zoning hearing is needed. DEP and the Beaver County Conservation District handle the construction stormwater permit, DEP's air program handles the generator plan approval, and PennDOT reviews traffic at Pendale Road and Route 18 and a highway occupancy permit for a new driveway onto Fairlane Boulevard.
- Top issues
- private wells and groundwater; 2.25 million gallons of diesel for backup generators; noise from 216 chillers and generator testing; old underground mines; construction and Route 18 traffic; transparency and the timing of the 2025 zoning change; loss of the race track; electric rates and FirstEnergy upgrades; LERTA tax abatement
- Key opponents
- Three Rivers Motorsport Preservation Society (Dan Dennehy-Rodriguez), formed by supporters of the former track, and the Big Beaver Association, called the Big Beaver Alliance in borough minutes. The two groups co-hosted a June 29, 2026 town hall that drew nearly 100 people. No elected official has publicly opposed the project in the coverage and records reviewed.
- Key supporters
- Switch is the project's main backer, and at its June 2, 2026 town hall one Big Beaver Borough council member said they supported the data center, Beaver County Radio reported. Beaver County's solicitor has said approval is a borough matter, and the county commissioners haven't taken a public position in the coverage reviewed.
How we got here
On September 16, 2025, Big Beaver Borough Council voted 6-0 to adopt zoning amendments under Ordinance 245 and a LERTA tax abatement ordinance covering the Industrial and commercial districts. The track's sale and closure were announced in October 2025, residents asked council for a moratorium on October 21, and the track closed November 9, 2025. In December 2025, a petition to repeal or replace Ordinance 245 was reported to council with more than 600 signatures. Wampum I, LLC completed its $50 million purchase in March 2026, and Switch and borough staff held an administrative meeting April 13. Switch announced the campus April 30 and held a town hall June 2, where police turned away reporters, and opponents held their own town hall June 29. Switch filed preliminary land development plans July 7 and its DEP stormwater application July 9. Council approved a curative amendment resolution August 4, which its special counsel said won't apply to Switch. The Beaver County Planning Commission issued comments August 18, Switch's notice of intent came before the borough Planning Committee August 27 in a meeting the crowd forced outdoors, and revised plans arrived in September. On October 2, Switch agreed to give council until December 18, 2026 to decide, and the borough engineer issued his review October 11.
Update, October 26, 2026. On October 20, 2026 borough council's agenda listed a presentation on the curative amendment ordinance, motions to send that ordinance to the borough and county planning commissions and advertise a December 1, 2026 public hearing, a $49,700 contract with EPD for community input on grants and any community benefits agreement, and adoption of Ordinance No. 250 amending the zoning ordinance. On October 22, 2026 Switch's preliminary plans were on the agenda of the newly appointed borough Planning Commission, which wasn't scheduled to act on them, and the presentation Switch posted for that meeting describes three buildings of about 215,000 square feet each, air-cooled closed-loop chillers, one Tier 4 backup generator per building, estimated daily water use of 2,000 to 2,500 gallons and a will-serve letter from the Beaver Falls Municipal Authority for up to 7,200 gallons a day.