All Pennsylvania projects
Contested

Switch Data Center Campus (former Pittsburgh International Race Complex)

Big Beaver Borough, Beaver County

Switch, Ltd. has filed preliminary plans for three data center buildings, with room shown for two more, on the 384-acre former Pittsburgh International Race Complex in Big Beaver Borough. The borough is reviewing the plan, and council has until December 18, 2026 to decide.

ContestedLargeTBD/UndisclosedBrownfieldSW
At a glance

The project by the numbers

StatusUnder Review
Building area647,250 sq ft
Site384 acres
Water (max)0.009 MGD
Capex$ 1.4 B
Permanent jobs, as claimed80
First announced2026-04-30
Target online2028-01

Switch plans data center campus on former Pitt Race track in Big Beaver

The number that mattersThe borough engineer's October 11, 2026 review counts 75 emergency generators per building, each holding 10,000 gallons of diesel, for "a cumulative total of 2.250 million gallons of stored diesel fuel" across the first three buildings, and asks Switch to plan for spills and for protecting drinking water wells in the area.
Developer
Switch, Ltd. of Las Vegas (founder and CEO Rob Roy), which DigitalBridge and IFM Investors took private in December 2022. Natalie Stewart Mitchell, senior vice president of government affairs and campus development, and Steven Roberts, vice president of construction development, present the project; General Counsel Scott Hettema signed the county application. Attorney Alan T. Shuckrow of Strassburger McKenna Gutnick & Gefsky represents Switch, and Atwell, LLC is the civil engineer. The land is held by Wampum I, LLC, which Provident Data Centers president Julian Hawes signed for at the March 2026 purchase and which Switch's filings now show as its wholly owned subsidiary.
Tenant
No tenant has been named. Switch says it designs, builds and operates campuses for AI, cloud and enterprise customers, and its April 2026 announcement pitched the site's fiber connections to finance, healthcare, higher education and government organizations.
Current stage
Preliminary land development review as of October 26, 2026. Switch filed July 7, 2026 and revised its plans September 4, and the borough engineer's October 11 review letter lists open zoning and land development items. Switch's plans were on the October 22 agenda of the borough Planning Commission, which wasn't scheduled to act on them, and the presentation Switch posted for that meeting describes three buildings of about 215,000 square feet each, air-cooled closed-loop chillers, one Tier 4 backup generator per building and a will-serve letter from the Beaver Falls Municipal Authority for up to 7,200 gallons of water a day. The Beaver County Planning Commission commented on the first plans August 18 and is reviewing the revision. DEP's tracker shows the Chapter 102 construction stormwater permit (PAC040210) pending since July 9, 2026, with the air quality plan approval for the generators, a storage tank permit and Act 537 sewage planning not yet submitted, and the Beaver County Conservation District gave Switch until November 4, 2026 to resubmit the stormwater application.
Decision body
Big Beaver Borough Council grants preliminary and then final land development approval after review by the borough engineer and zoning officer, the borough Planning Commission and the Beaver County Planning Commission, whose review is advisory. Data centers are a permitted use with special regulations in the Industrial district, so no zoning hearing is needed. DEP and the Beaver County Conservation District handle the construction stormwater permit, DEP's air program handles the generator plan approval, and PennDOT reviews traffic at Pendale Road and Route 18 and a highway occupancy permit for a new driveway onto Fairlane Boulevard.
Top issues
private wells and groundwater; 2.25 million gallons of diesel for backup generators; noise from 216 chillers and generator testing; old underground mines; construction and Route 18 traffic; transparency and the timing of the 2025 zoning change; loss of the race track; electric rates and FirstEnergy upgrades; LERTA tax abatement
Key opponents
Three Rivers Motorsport Preservation Society (Dan Dennehy-Rodriguez), formed by supporters of the former track, and the Big Beaver Association, called the Big Beaver Alliance in borough minutes. The two groups co-hosted a June 29, 2026 town hall that drew nearly 100 people. No elected official has publicly opposed the project in the coverage and records reviewed.
Key supporters
Switch is the project's main backer, and at its June 2, 2026 town hall one Big Beaver Borough council member said they supported the data center, Beaver County Radio reported. Beaver County's solicitor has said approval is a borough matter, and the county commissioners haven't taken a public position in the coverage reviewed.

How we got here

On September 16, 2025, Big Beaver Borough Council voted 6-0 to adopt zoning amendments under Ordinance 245 and a LERTA tax abatement ordinance covering the Industrial and commercial districts. The track's sale and closure were announced in October 2025, residents asked council for a moratorium on October 21, and the track closed November 9, 2025. In December 2025, a petition to repeal or replace Ordinance 245 was reported to council with more than 600 signatures. Wampum I, LLC completed its $50 million purchase in March 2026, and Switch and borough staff held an administrative meeting April 13. Switch announced the campus April 30 and held a town hall June 2, where police turned away reporters, and opponents held their own town hall June 29. Switch filed preliminary land development plans July 7 and its DEP stormwater application July 9. Council approved a curative amendment resolution August 4, which its special counsel said won't apply to Switch. The Beaver County Planning Commission issued comments August 18, Switch's notice of intent came before the borough Planning Committee August 27 in a meeting the crowd forced outdoors, and revised plans arrived in September. On October 2, Switch agreed to give council until December 18, 2026 to decide, and the borough engineer issued his review October 11.

Update, October 26, 2026. On October 20, 2026 borough council's agenda listed a presentation on the curative amendment ordinance, motions to send that ordinance to the borough and county planning commissions and advertise a December 1, 2026 public hearing, a $49,700 contract with EPD for community input on grants and any community benefits agreement, and adoption of Ordinance No. 250 amending the zoning ordinance. On October 22, 2026 Switch's preliminary plans were on the agenda of the newly appointed borough Planning Commission, which wasn't scheduled to act on them, and the presentation Switch posted for that meeting describes three buildings of about 215,000 square feet each, air-cooled closed-loop chillers, one Tier 4 backup generator per building, estimated daily water use of 2,000 to 2,500 gallons and a will-serve letter from the Beaver Falls Municipal Authority for up to 7,200 gallons a day.

What is at stake

Impacts raised and open questions

Public safety

High

The borough engineer counts 75 diesel emergency generators per building, each with 10,000 gallons of fuel, or about 2.25 million gallons for the first three buildings. He asks Switch to plan for spills and for protecting drinking water wells nearby, and suggests sharing its spill plan, still marked draft, with New Beaver Township, Lawrence County and county emergency management.

Big Beaver Borough (Daniel J. Martone, Borough Engineer and Zoning Officer)

Noise and vibration

Medium

Switch's consultant, Acentech, measured average background sound near the property line of about 41 dBA by day and 39 dBA at night, and modeled the 216 chillers at up to 55.6 dBA at receiver points near the property line. That's well under the borough's 75 dBA limit but slightly above Switch's own 55 dBA goal at one point, and generator noise during outages and testing is exempt from the limit.

Big Beaver Borough

Air quality

Medium

Data Center Dynamics reports the filings show 270 MW of backup generator capacity. DEP's tracker shows the air quality plan approval needed to build the generators hasn't been applied for yet, and Switch told residents it would use Tier 4 generators.

Data Center Dynamics

Jobs and tax claims

Medium

Switch told residents the project would create 1,500 to 2,000 construction jobs and 80 to 100 full-time jobs once running, and that benefits would lag until full build-out.

Beaver County Radio

Water

Low

Switch's lawyer says the campus would draw about 9,000 gallons a day from the Beaver Falls Municipal Authority's 12-inch main fed by the on-site water tower, plus an initial fill of the closed-loop cooling system, and that existing on-site wells would be capped. Neighbors on private wells remain worried about groundwater.

Big Beaver Borough
Community response

Who is organizing against it

Three Rivers Motorsport Preservation Society

Supporters of the former Pitt Race and the regional motorsport community, Big Beaver area · 600 signatures

Leaders: Dan Dennehy-Rodriguez

Tactics: Speaking at council meetings, a petition to repeal or replace Ordinance 245, and a June 29, 2026 town hall with environmental, legal and legislative speakers

WPXI says the group was formed by supporters of the former track. Dennehy-Rodriguez asked council for a permanent moratorium in October 2025 and reported the petition's 600-plus signatures in December 2025. We couldn't find a website, social page or petition link.

Big Beaver Association

Big Beaver Borough residents

Tactics: Co-hosted the June 29, 2026 town hall and speaks at council meetings

WPXI calls it the Big Beaver Association, and July 7, 2026 borough minutes refer to the Big Beaver Alliance, which a member described as focused on opposing the proposed data center. We couldn't find a website or social page.

Timeline

How it has unfolded

  • 2025-09-16Council votes 6-0 to adopt zoning amendments under Ordinance 245 and a LERTA tax abatement ordinance covering the Industrial and commercial districts. Big Beaver Borough
  • 2025-10-20The track's planned closure after the 2025 season, following a sale, is reported along with talk that the site could become a data center. Performance Racing Industry
  • 2025-10-21Residents ask council for a permanent moratorium, and the solicitor says no applications have been filed and council has no say over the sale. Big Beaver Borough
  • 2025-11-09The race track closes after more than 20 years. Beaver County Radio
  • 2025-12-16A petition to repeal or replace Ordinance 245 with more than 600 signatures is reported to council. Big Beaver Borough
  • 2026-04-13Switch and borough staff hold an administrative meeting, similar to a pre-application conference, on the coming submission. Big Beaver Borough (Daniel J. Martone, Borough Engineer and Zoning Officer)
  • 2026-04-15Land records show Wampum I, LLC, linked to Provident Data Centers, paid $50 million for the track in a sale finalized in March. Beaver County Radio
  • 2026-04-30Switch announces a 382-acre data center campus in Big Beaver Borough. Switch
  • 2026-06-02Switch holds a town hall at the Big Beaver fire hall, describing three 200,000-square-foot buildings and a $1.4 billion investment, while police turn away the press. Beaver County Radio
  • 2026-06-29Opponents hold their own town hall, drawing nearly 100 people. WPXI
  • 2026-07-07Switch files preliminary land development plans with the borough and the Beaver County Planning Commission. Big Beaver Borough
  • 2026-07-09A Chapter 102 construction stormwater permit application (PAC040210) is submitted to DEP. Pennsylvania DEP
  • 2026-07-21Special counsel Don Graham tells council Switch's lawyer said the application was filed over concern about a possible state moratorium. Big Beaver Borough
  • 2026-08-04Council approves Resolution 07-2026, starting a curative amendment to its zoning ordinance. Big Beaver Borough
  • 2026-08-18The county planning commission issues review comments on Switch's first plans. Big Beaver Borough (Daniel J. Martone, Borough Engineer and Zoning Officer)
  • 2026-08-27Switch's notice of intent to apply is presented at a meeting moved outdoors because of the crowd. WPXI
  • 2026-09-04Switch revises its plans, enlarging each building to 215,750 square feet and outlining two future buildings. Big Beaver Borough
  • 2026-10-02Switch agrees council has until December 18, 2026 to decide on the preliminary plan. Big Beaver Borough
  • 2026-10-11The borough engineer issues his review of the preliminary plans and asks Switch for written responses and revised plans. Big Beaver Borough (Daniel J. Martone, Borough Engineer and Zoning Officer)
  • 2026-10-20Council's agenda listed a presentation on the curative amendment ordinance, motions to send it to the borough and county planning commissions and advertise a December 1, 2026 hearing, a $49,700 contract with EPD for community input on grants and any community benefits agreement, and adoption of Ordinance No. 250 amending the zoning ordinance. Big Beaver Borough
  • 2026-10-22The new Planning Commission meets with Switch's plans on the agenda and no action planned. Big Beaver Borough
  • 2026-10-22Switch's presentation to the borough Planning Commission, posted on the borough's Switch page, describes three buildings of about 215,000 square feet each, air-cooled closed-loop chillers and a Beaver Falls Municipal Authority will-serve letter for up to 7,200 gallons of water a day. Switch, posted by Big Beaver Borough
Legal record

Filings and legal actions

  • 2026-08-04
    Municipal curative amendment (Resolution 07-2026) Big Beaver Borough Council · n/a

    Council approved a resolution starting a curative amendment, which allows 180 days to adopt zoning changes. Special counsel Don Graham told council it was started after Switch's application arrived and won't apply to it, and that he saw no defect in how the ordinance treats data centers.

    Big Beaver Borough · Pending. Council's October 20, 2026 agenda listed motions to send the curative amendment ordinance to the borough and county planning commissions and to advertise a December 1, 2026 public hearing.
  • 2026-07-07
    Request for confidential treatment of plans under the Right-to-Know Law Big Beaver Borough · n/a

    Switch asked the borough to treat its plans as confidential under Right-to-Know Law exemptions and trade secret law, citing security risks, and asked for notice before any release so it could seek legal remedies.

    Switch, Ltd.; Big Beaver Borough · The borough has posted the application package, including plan sets and reports, on its website.
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →