Follow the Money

Backer profile · Developer

4-3 Glen Brook Group (with 4-3 Consulting)

4-3 Consulting LLC, founded by Jack Sordoni, puts together large groups of landowners to sell to data center buyers, and 4-3 Glen Brook Group LLC is the affiliated group behind its second deal in Salem Township, Luzerne County. 4-3 Consulting organized the sale of about 1,700 acres from 96 landowners to Blackstone-owned QTS, which the Times Leader reported in March 2026 paid the owners more than $500 million, and Sordoni said the township would get a $9 million community benefit agreement. In June 2026 the Glen Brook group announced a deal covering more than 4,000 acres and 194 landowners and asked the township to expand its data center overlay district for a campus with its own power plant, saying it has a buyer it can't name until zoning is approved and the sale closes.

Scoreboard

2

Pennsylvania projects on our map

  • 1 approved or built
  • 1 proposed, under review or on appeal

Partner: 2 · Developer: 1

QTS Salem Township Data Center CampusSalem 3 Data Center Campus (4-3 Glen Brook Group)
Approved or built1
In process1
Stopped0
Megawatts named4,000 MWpublished for 1 of 2
Land involved5,700 acrespublished for 2 of 2
Investment announced$10.0 billionpublished for 1 of 2
Counties1Luzerne
Earliest project2026first public announcement
Local groups opposing1across its projects
Legal filings2appeals, challenges and suits on file
Community impacts13documented on its projects
News stories23in our coverage log

Projects

ProjectStatusRoleSize named
QTS Salem Township Data Center CampusSalem Township, Luzerne CountySuggest a correction Approved Partner ·
Salem 3 Data Center Campus (4-3 Glen Brook Group)Salem Township, Luzerne CountySuggest a correction Under Review Developer, Partner 4,000 MW

Sources

Project details, statuses and figures come from each project’s own profile, which lists its sources.

Help stop the 900 Conshohocken Road data center.

Corrections and additions

Are you with one of these organizations?

If something here is wrong, out of date or missing, tell us. We read every submission, check it against the public record or the documents you send, and update the page when it’s supported. You can also send context you’d like considered, such as a change in ownership, a project you’ve left, or your organization’s response.