- Developer
- QTS Data Centers, owned by Blackstone. Its DEP stormwater permit applications were filed by SNA North, LLC of Overland Park, Kansas, under the project names 'QTS-Salem-Yellow' and 'Project Zion-Blue.' 4-3 Consulting LLC (founder Jack Sordoni and principal Dave Scoblick) assembled the land, and JLL brokered the sale with Park Place Realty of Drums. Attorney David Tshudy represents QTS, and David Farhat is its director of development.
- Tenant
- No tenant named. QTS's project page says the permanent jobs would include positions 'employed by our tenants.'
- Current stage
- Township approvals are in hand: on July 15, 2026 the Salem Township Board of Supervisors approved the final master plan, the consolidation of 180 lots totaling 1,700 acres, and the vacation of parts of North Market Street and Moskaluk Road and all of Kiliti Road. DEP lists the project as under review as of October 22, 2026, with two stormwater permits (PAD400114 and PAD400116), a waterway encroachment permit (E4002226-011), an air quality plan approval (40-00162A, submitted July 29, 2026) and a federal general conservation plan pending, and storage tank, sewage planning and more stormwater permits not yet submitted. Plans for the replacement road still have to go through township land development review, which the zoning officer estimated could take about nine months.
- Decision body
- Salem Township Board of Supervisors (master plan, road vacations and land development), on recommendation of the Salem Township Planning Commission; Pennsylvania DEP (stormwater, waterway, air quality and storage tank permits); U.S. Fish and Wildlife Service (general conservation plan listed on DEP's tracker)
- Top issues
- Closing parts of three township roads and truck routes on Stone Church Road; boarded-up homes and neighbors left just outside the purchase line; property values; well water and the water supply for the cooling system's first fill; diesel backup generators and the pending air permit; stormwater to Walker Run; nondisclosure agreements signed by the township; limits on public comment; feral cats left on the bought-out properties
- Key opponents
- State Rep. Jamie Walsh, R-Ross Township, objected at the May 28, 2026 planning commission meeting when public comment was limited, and told The Center Square that 'things that have happened in Salem Township don't seem to have been all fully transparent.' Food & Water Watch has been organizing against data center development in the region. No organized local group focused on the QTS campus has been reported.
- Key supporters
- The Salem Township supervisors and Solicitor Anthony J. McDonald, a former judge, who said the supervisors 'saw the possibility of a data center as a positive'; 4-3 Consulting; and many of the 96 landowners who sold.
How we got here
By March 2026, Salem Township supervisors had already approved an initial QTS master plan with 18 buildings, according to QTS's attorney. QTS's first stormwater permit application (PAD400114) reached DEP on Dec. 8, 2025, and a second (PAD400116) on Feb. 17, 2026. On March 18, 2026, 4-3 Consulting announced that 96 landowners had been paid more than $500 million for about 1,700 acres, QTS said it was 'advancing plans' for a campus, and 4-3 founder Jack Sordoni said the township would receive a $9 million community benefit agreement. On March 26 the planning commission tabled an updated master plan with 12 buildings and about 100 more acres while it waited for county comments. The Pennsylvania Bulletin published notice of the two stormwater applications on April 18 and May 2. QTS filed a waterway encroachment application on May 22, and on May 28 the planning commission recommended conditional approval of the master plan, the lot consolidation and the road vacations. In June a volunteer cat rescue working on the bought-out properties was told to leave, and QTS said it was not pursuing extermination. The Center Square reported on June 23 that the township had signed nondisclosure agreements with two data center companies. On July 15 the supervisors approved the road vacations, the 180-lot consolidation and the final master plan. QTS applied for an air quality plan approval on July 29. On Aug. 18 Gov. Shapiro signed an executive order removing data centers, including both Salem Township campuses, from the state's permit fast-track program.