- Developer
- No data center developer has been named. CNX Resources Corporation of Canonsburg (President and CEO Alan Shepard since January 1, 2026) owns the land and is represented by attorneys Blaine Lucas and Robert Max Junker of Babst Calland. JLL is marketing the site through Executive Managing Director Dan Adamski, Managing Director Rick O'Brien and Senior Vice President Greg Hopkins.
- Tenant
- No tenant has been linked to the site. JLL has pitched it as able to support hyperscale providers such as Google, Meta and Amazon, and CNX's attorney said in June 2026 there were no current applications to buy the property.
- Current stage
- Marketed for sale or lease with no application filed as of October 26, 2026. DEP's tracker listed the project on October 22, 2026 as proposed with no applications received and five permits not yet submitted. South Strabane adopted its data center zoning and noise ordinances June 9, 2026. Its fossil fuel power generation ordinance, the last of the three, was tabled in late July and again August 25, 2026, and at the September 22, 2026 meeting the board declined to act on it, according to the Observer-Reporter.
- Decision body
- South Strabane Township Board of Supervisors (Chairman George Rowand, Vice Chairman Jeff Bull) under the data center ordinance adopted June 9, 2026; the March 2026 draft sent data centers through a conditional use process. The township Planning Commission reviews and recommends. DEP would handle the stormwater, encroachment, sewage planning, blasting and air permits.
- Top issues
- on-site gas power and air pollution; setbacks from homes; noise and light; water use and groundwater; property values; temporary versus permanent jobs; community benefit payments; CNX's claim that the township's rules are exclusionary
- Key opponents
- Center for Coalfield Justice (Executive Director Sarah Martik), which held a December 4, 2025 community meeting on what it called the CNX Resources-backed Zediker Megasite Proposal. Residents have filled township meetings and posted "no data centers in South Strabane" signs, but no separate organized group has been reported. Township officials haven't opposed a data center outright, and Solicitor Dennis Makel has said a ban would likely be unlawful.
- Key supporters
- Washington County Commissioners Chair Nick Sherman, who said the county is "proud to support this transformative project"; JLL; the Allegheny Conference on Community Development (CEO Stefani Pashman), which published an economic impact estimate; and Tom Platt of the Pittsburgh Regional Building Trades Council and IBEW Local 5, who spoke for the jobs at the March 31, 2026 hearing.
How we got here
JLL announced on October 20, 2025 that it was marketing CNX's Zediker Station property as a data center site, and Supervisor Jeff Bull called it speculation because the township had heard nothing. The Center for Coalfield Justice held a community meeting on the proposal December 4, 2025, and residents filled the supervisors' December 16 meeting, where the solicitor said a public hearing on a data center ordinance would follow. The Allegheny Conference released its economic impact estimate March 3, 2026. After tabling the ordinance more than once, the planning commission recommended it March 19, the same day CNX attorney Blaine Lucas sent a letter calling parts of it illegal, and supervisors held a three-hour public hearing March 31. Supervisors unanimously adopted the data center and noise ordinances June 9, 2026 with a 1,500-foot setback. The companion fossil fuel power generation ordinance was tabled in late July and again August 25, 2026.
Update, October 26, 2026. On September 22, 2026 the South Strabane supervisors declined to act on the proposed fossil fuel power generation ordinance, the last of three ordinances aimed at data center development, after tabling it at their July and August meetings. The Observer-Reporter didn't report a reason or a new vote date.