- Developer
- Elysian Partners, LLC (Kevin Brown), which the York Daily Record describes as a privately held real estate company from Boca Raton, Florida, presented the idea on May 19, 2025, represented by Attorney Craig Sharnetzka of CGA Law Firm. The tract belongs to private landowners on White Oak Road. Elysian hasn't filed an application.
- Tenant
- No end user has been named. Elysian described a generic facility and said data centers are in high demand because of AI.
- Current stage
- The idea remains exploratory: Windsor adopted its data center ordinance on July 20, 2026, and the White Oak Road tract Elysian described is in the Agricultural zone, where the ordinance doesn't allow data centers, so the township solicitor has said a separate rezoning would be needed. No application or plan has been submitted, according to township minutes, and the supervisors' September 21, 2026 meeting had no data center business.
- Decision body
- Windsor Township Board of Supervisors (Chairperson Katherine A. Kerchner, Stan Saylor and Kim Moyer), which decides conditional uses and rezonings, with review by the Windsor Township Planning Commission and the York County Planning Commission.
- Top issues
- Which zones should allow data centers, water use and effects on private wells and the Red Lion Municipal Authority's reservoir, noise from cooling equipment and diesel generators, fire department capacity, farmland preservation, and whether developers can be required to pay for emergency equipment.
- Key opponents
- No organized group has been named in township records. Residents spoke at planning commission and supervisors meetings from August 2025 on about water, wells, noise, fire protection, farmland and the Red Lion Municipal Authority's reservoir, and most of the 24 residents at the July 20, 2026 hearing opposed allowing data centers in the commercial zone. Supervisor Stan Saylor mentioned a resident petition about data centers in July 2025.
- Key supporters
- Supervisor Stan Saylor said in May 2025 that a data center would add tax base and jobs with little traffic, and he and Supervisor Kim Moyer pushed to allow data centers in commercial zones after visiting data centers in Loudoun County, Virginia. Some residents thanked the board for being proactive.
How we got here
May 19, 2025: Elysian Partners pitched an AI data center for White Oak Road to the supervisors. July 17, 2025: the planning commission reviewed a lot line adjustment for the White Oak Road properties, and the township engineer noted talk of a data center there. August 18, 2025: supervisors sent a text amendment proposed by an interested party to the planning commission. August 21 to November 20, 2025: the planning commission held public discussions and voted 5-0 to move a revised draft forward. February 16, 2026: supervisors agreed on conditional use in the Industrial and General Commercial zones. March 16, 2026: the draft went to the York County Planning Commission, which later declined to recommend it. July 20, 2026: after a public hearing, supervisors adopted Ordinance No. 2026-07-01 and dropped the General Commercial zone. August 17, 2026: Supervisor Saylor said he didn't favor changes for now.