- Developer
- Tenaska, the Omaha, Neb., energy company, which owns the plant through Tenaska Pennsylvania Partners LLC.
- Tenant
- The plant has no tenant, and Tenaska sells its power into the PJM Interconnection regional grid. Plans filed for a data center proposed about a mile away don't say where its electricity would come from, according to Marcellus Drilling News.
- Current stage
- The plant is operating under initial Title V operating permit TV-65-00990, which DEP issued on June 30, 2026, effective July 15, 2026 and expiring June 30, 2031. In June 2026 DEP also reported reissuing the plant's water discharge permit (NPDES PA0254771).
- Decision body
- Pennsylvania Department of Environmental Protection, Southwest Regional Office, which issues the plant's air quality and water discharge permits. South Huntingdon Township is the host municipality.
- Top issues
- Air emissions and the plant's compliance record, emissions monitoring that advocacy groups called too thin, cooling tower plume, odors and noise reported by neighbors, the use of Youghiogheny River water, and whether a proposed data center nearby could draw on the plant's power.
- Key opponents
- No local group organized just against the plant has been reported. During DEP's Title V review, Clean Air Council, PennFuture, the Environmental Health Project and the Environmental Integrity Project pressed for stronger monitoring, and written comments were co-signed by groups including Mountain Watershed Association, Yough Communities CARE and Protect PT. West Newton Borough and the Unitarian Universalist Congregation of Smithton asked DEP to hold a public hearing, and South Huntingdon supervisors, through their solicitor, asked DEP to set up a stakeholder group.
- Key supporters
- Tenaska points to $2 million in local property taxes paid since 2018 and $18.9 million in salaries and local vendor payments in 2025. Marcellus Drilling News, an industry news site, has defended the plant's record. We found no statements of support from public officials in the records we reviewed.
How we got here
DEP issued plan approval PA-65-00990C for construction and temporary operation on April 1, 2015, and the plant began commercial operation in December 2018, according to Tenaska. DEP settled short-term carbon monoxide and nitrogen oxides exceedances with Tenaska through consent assessments of $14,997 in September 2022 and $5,028 in October 2025. Tenaska applied for its initial Title V operating permit on July 11, 2024. DEP first proposed the permit on October 4, 2025, held a public hearing in West Newton on February 4, 2026, and took comments through February 14, 2026. In May 2026 DEP extended the plant's temporary operating period to November 28, 2026, and on June 30, 2026 it issued Title V permit TV-65-00990, effective July 15. In October 2026 a data center was proposed on farmland along Route 31 about a mile away.