All Pennsylvania projects
Contested

TekPark Data Center Expansion (TierPoint)

Upper Macungie Township, Lehigh County

TierPoint bought the TekPark campus in 2025 and is expanding it toward 100 megawatts, and state regulators have approved PPL's new lines to a new substation on the site.

ContestedLargeGrid StandardBrownfieldLV
At a glance

The project by the numbers

StatusProposed
Capacity100 MW
Site137 acres
First announced2025-10-23
Target online2026 to 2027

TierPoint plans to more than triple the power at Breinigsville's old Bell Labs campus

The number that mattersPPL told the PUC that the customer at the old Bell Labs site uses about 30 megawatts today and has asked for service for a final load of about 100 megawatts.
Developer
TierPoint, LLC of St. Louis, led by Chairman and CEO Jerry Kent, which owns the TekPark campus and runs the existing data center there.
Tenant
TierPoint hasn't named its tenants, though it says its TekPark clients include large technology service providers using advanced cooling for AI and GPU-heavy work. PPL's filings describe the power customer only as an existing customer at the former Bell Labs site.
Current stage
DEP's tracker lists the expansion as proposed with no permit applications received as of October 22, 2026, though it expects stormwater, stream crossing, water, air quality and storage tank permits. The utility work is further along. The PUC approved PPL's two short transmission lines on August 6, 2026, PPL planned to start the first line in August 2026, and DEP proposed on August 29, 2026 to issue PPL's stormwater permit for the line from the Breinigsville Substation. No Upper Macungie Township land development filing for the expansion has been reported.
Decision body
Upper Macungie Township Board of Supervisors and Planning Commission for any land development; DEP for stormwater, stream crossing, water, air quality and storage tank permits; the Pennsylvania Public Utility Commission, which approved PPL's lines.
Top issues
Power use rising from about 30 to about 100 megawatts; who pays for PPL's new lines; new transmission structures up to 125 feet tall; stormwater from line construction draining to high-quality cold water streams; air quality and storage tank permits DEP expects but hasn't received; tenants who haven't been named
Key opponents
No organized opposition group or public official has opposed the expansion in the records reviewed, and no one filed a protest against PPL's line application at the PUC.
Key supporters
TierPoint, which says the expansion responds to client demand; PPL Electric, which told the PUC the lines are needed to serve the customer's load and will also let about 2,700 nearby customers be switched to another source during maintenance and outages.

How we got here

PPL presented the customer's power request to PJM on July 18, 2024 and its proposed fix on September 19, 2024, and added it to its local plan on March 18, 2025. On October 23, 2025, TierPoint announced it had bought the TekPark campus and started a 100 megawatt power expansion. PPL asked the PUC to approve its new TEK Park lines on May 1, 2026, and DEP published PPL's stormwater permit application for the first line on May 23, 2026. In July 2026 PPL told the PUC the customer now uses about 30 megawatts. The PUC approved the lines on August 6, 2026, and on August 29, 2026 DEP announced it intends to issue the stormwater permit for the second line.

Update, October 26, 2026. In a tour report presented to the Lower Mount Bethel Township supervisors on October 19, 2026, Supervisor John Mauser wrote that TierPoint's Breinigsville data center runs at 28 megawatts with plans to increase to 100 megawatts. The report says the site has 15 generators of 2.5 megawatts and 8 redundant generators of 2.0 megawatts that are tested every two weeks, that the older section built in 1987 uses an evaporative cooling system that may use up to 3 million gallons of water a month from a public water source, and that the newer section uses a closed-loop system.

What is at stake

Impacts raised and open questions

Energy costs and the grid

Medium

PPL puts the new lines at about $4.6 million: the customer pays for the $2.7 million first phase and PPL pays for the $1.9 million second phase, and the PUC's order says its approval doesn't address how those costs are recovered. PPL also told the PUC that about 40 more megawatts of load in the area would overload a Breinigsville Substation transformer if the other one were lost.

Pennsylvania Public Utility Commission

Visual and light

Low

PPL will remove one transmission structure and put up 19 new ones ranging from about 56 to 125 feet tall, in a right-of-way about 100 feet wide on PPL and customer land.

Pennsylvania Public Utility Commission

Water

Low

DEP's notices show PPL's two line projects disturbing about 6.7 and 11.78 acres, with stormwater draining to Breinig Run, Little Lehigh Creek and its tributaries, which DEP lists as high-quality cold water fisheries.

Pennsylvania Bulletin
Timeline

How it has unfolded

  • 2024-07-18PPL presents the customer's request for more power at the TEK Park site to PJM's regional planning meeting. Pennsylvania Public Utility Commission
  • 2024-09-19PPL presents its proposed transmission fix for the TEK Park customer to PJM. Pennsylvania Public Utility Commission
  • 2025-10-23TierPoint announces it bought the 137-acre TekPark campus and started a 100 megawatt power expansion it expects to finish in the second half of 2026. TierPoint, LLC
  • 2026-05-01PPL files a Letter of Notification asking the PUC to approve new 138/69 kV lines to a new customer-owned TEK Park substation. Pennsylvania Public Utility Commission
  • 2026-05-23DEP publishes PPL's stormwater permit application and draft permit for the Tek Park 138-69kV New Tap Project, covering 6.7 acres of earth disturbance. Pennsylvania Bulletin
  • 2026-07-13PPL tells PUC staff the existing customer at the former Bell Labs site uses about 30 megawatts and is expanding. Pennsylvania Public Utility Commission
  • 2026-08-06The PUC approves PPL's TEK Park lines with no protests filed and no hearings held. Pennsylvania Public Utility Commission
  • 2026-08-29DEP announces a tentative decision to issue PPL's stormwater permit for the roughly one-mile Breinigsville-Tek Park line, covering 11.78 acres. Pennsylvania Bulletin
  • 2026-10-19A tour report from visits to TierPoint's Breinigsville site on August 25 and September 1, 2026 says the site runs at 28 megawatts with plans to reach 100, has 15 generators of 2.5 megawatts and 8 redundant generators of 2.0 megawatts, and that the older section built in 1987 uses evaporative cooling that may use up to 3 million gallons of public water a month. Lower Mount Bethel Township
Legal record

Filings and legal actions

  • 2026-05-01
    Letter of Notification (transmission line siting) Pennsylvania Public Utility Commission · A-2026-3062204

    PPL sought approval for about 0.5 miles of new double-circuit lines to the new customer-owned TEK Park 138/69-13 kV substation and about 0.75 miles of new lines from the Breinigsville Substation. The PUC found the filing in the public interest, noted that no protests were filed, and said its approval doesn't address cost recovery.

    PPL Electric Utilities Corporation · Approved August 6, 2026
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →