- Developer
- TierPoint, LLC of St. Louis, led by Chairman and CEO Jerry Kent, which owns the TekPark campus and runs the existing data center there.
- Tenant
- TierPoint hasn't named its tenants, though it says its TekPark clients include large technology service providers using advanced cooling for AI and GPU-heavy work. PPL's filings describe the power customer only as an existing customer at the former Bell Labs site.
- Current stage
- DEP's tracker lists the expansion as proposed with no permit applications received as of October 22, 2026, though it expects stormwater, stream crossing, water, air quality and storage tank permits. The utility work is further along. The PUC approved PPL's two short transmission lines on August 6, 2026, PPL planned to start the first line in August 2026, and DEP proposed on August 29, 2026 to issue PPL's stormwater permit for the line from the Breinigsville Substation. No Upper Macungie Township land development filing for the expansion has been reported.
- Decision body
- Upper Macungie Township Board of Supervisors and Planning Commission for any land development; DEP for stormwater, stream crossing, water, air quality and storage tank permits; the Pennsylvania Public Utility Commission, which approved PPL's lines.
- Top issues
- Power use rising from about 30 to about 100 megawatts; who pays for PPL's new lines; new transmission structures up to 125 feet tall; stormwater from line construction draining to high-quality cold water streams; air quality and storage tank permits DEP expects but hasn't received; tenants who haven't been named
- Key opponents
- No organized opposition group or public official has opposed the expansion in the records reviewed, and no one filed a protest against PPL's line application at the PUC.
- Key supporters
- TierPoint, which says the expansion responds to client demand; PPL Electric, which told the PUC the lines are needed to serve the customer's load and will also let about 2,700 nearby customers be switched to another source during maintenance and outages.
How we got here
PPL presented the customer's power request to PJM on July 18, 2024 and its proposed fix on September 19, 2024, and added it to its local plan on March 18, 2025. On October 23, 2025, TierPoint announced it had bought the TekPark campus and started a 100 megawatt power expansion. PPL asked the PUC to approve its new TEK Park lines on May 1, 2026, and DEP published PPL's stormwater permit application for the first line on May 23, 2026. In July 2026 PPL told the PUC the customer now uses about 30 megawatts. The PUC approved the lines on August 6, 2026, and on August 29, 2026 DEP announced it intends to issue the stormwater permit for the second line.
Update, October 26, 2026. In a tour report presented to the Lower Mount Bethel Township supervisors on October 19, 2026, Supervisor John Mauser wrote that TierPoint's Breinigsville data center runs at 28 megawatts with plans to increase to 100 megawatts. The report says the site has 15 generators of 2.5 megawatts and 8 redundant generators of 2.0 megawatts that are tested every two weeks, that the older section built in 1987 uses an evaporative cooling system that may use up to 3 million gallons of water a month from a public water source, and that the newer section uses a closed-loop system.