Energy costs and the grid
MediumThe site is about a mile from the Tenaska Westmoreland Generating Station, a natural gas power plant. Neither the landowner nor Tenaska would say whether the data center would draw on it.
TribLiveSouth Huntingdon Township, Westmoreland County
A Sewickley energy firm applied in May for a land use permit to build a data center warehouse on 178 acres near the I-70 interchange, about a mile from a gas-fired power plant. The landowner says it's in the early stages.
Stanton Farm LLC acquired 178 acres along Route 31 in September 2021. In January 2025 the Westmoreland Conservation District approved a wastewater discharge permit for a warehouse on the site, a permit that runs to December 2029. In February 2025 DEP received an application filed by Douglas Sippel of Zelienople to fill about 2,163 feet of unnamed tributaries to Lick Run for a 1 million-square-foot warehouse with semi-trailer parking. TriEnergy and Stanton Farm signed a three-year agreement for the project in October 2025, and TriEnergy applied for a township land use permit in May 2026. DEP published notice of the stream application on June 13, 2026. On Sept. 17, 2026, supervisors unanimously adopted a 12-section data center ordinance while residents shouted for them to table it. The Pittsburgh Business Journal reported the proposal on Oct. 12, 2026, TribLive followed with details from the application on Oct. 13, and Marcellus Drilling News reported on Oct. 14 that the plans filed with the township don't say where the electricity will come from. On Oct. 19 TribLive reported the township still hadn't reviewed the plan because DEP hadn't approved the sewage permit.
The site is about a mile from the Tenaska Westmoreland Generating Station, a natural gas power plant. Neither the landowner nor Tenaska would say whether the data center would draw on it.
TribLiveThe township ordinance requires a 500-foot setback from property lines with evergreen woodland or an opaque barrier to block views. Residents said 500 feet isn't enough, and the township's special counsel said larger setbacks probably aren't enforceable without zoning.
TribLiveA wastewater discharge permit for a warehouse was approved in January 2025, and DEP has not yet approved a sewage permit for the data center project.
TribLiveThe ordinance caps daytime and nighttime sound levels and light from the facility. A cattle farmer at the Sept. 17 meeting asked that developers pay for a study of effects on farm animals.
TribLiveThe developer's DEP application would permanently fill about 2,163 linear feet of five small unnamed tributaries to Lick Run and 0.09 acre of floodway for the building and parking. It proposes buying stream mitigation credits from the Laurel Hill Creek Mitigation Bank to make up for the loss.
Pennsylvania Bulletin, Vol. 56, No. 24The DEP application describes semi-trailer parking, employee parking and a driveway for the one-million-square-foot building along Mt. Pleasant Road (Route 31).
Pennsylvania Bulletin, Vol. 56, No. 24The township's Sept. 17, 2026 data center ordinance requires a secondary facility for storing bulk ammonia used in data center operations, along with an environmental impact assessment, according to TribLive.
TribLiveWould permanently fill about 2,163 linear feet of unnamed tributaries to Lick Run and 0.09 acre of floodway and add a 40-foot culvert to build a one-million-square-foot warehouse, semi-trailer and employee parking, a driveway, utilities and stormwater facilities, with mitigation credits from the Laurel Hill Creek Mitigation Bank.
Douglas Sippel, 174 Tomlinson Drive, Zelienople · Pending; no DEP decision published through October 17, 2026In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.