South Hanover Township Data Center (HCI DP Land Acquisition, former Pennsy Supply quarry)

South Hanover Township, Dauphin County

HCI DP Land Acquisition LLC wants two data centers and a substation on the 249-acre former Pennsy Supply quarry near Hummelstown, but its zoning hearings have been put on hold at its own request.

Withdrawn / DeniedLargeTBD/UndisclosedBrownfieldS Central
At a glance

The project by the numbers

StatusStopped / Paused
Building area596,800 sq ft
Site249 acres
First announced2026-06-23

Texas developer seeks data centers on a former quarry in South Hanover Township

The number that mattersPennLive reported that HCI is the equitable owner of 12 parcels totaling 496 acres in the township, about twice the 249-acre quarry tract in its special exception request.
Developer
HCI DP Land Acquisition LLC, a Texas-based company (PennLive) that the local opposition group identifies as The Hanover Company, a Houston real estate developer.
Tenant
No tenant named
Current stage
HCI's special exception application and its challenge to the township's zoning were set for a Zoning Hearing Board hearing on August 17, 2026. The applicant's attorney asked for a continuance, and the township's public notices page lists a notice of hearing pause and a letter to the Zoning Hearing Board about an indefinite extension. The supervisors voted 5-0 on July 1 to advertise a data center overlay ordinance and announced an August 11 hearing, but the minutes through September 22 record no hearing or adoption vote. The supervisors continue to meet in executive session about litigation involving the data center ordinance.
Decision body
South Hanover Township Zoning Hearing Board (special exception and validity challenge); South Hanover Township Board of Supervisors (data center overlay ordinance)
Top issues
Private wells and groundwater, Swatara Creek and the quarry water, noise and backup generators, building height, residential parcels included in the draft overlay, setbacks, light, decommissioning bonds, property values, and nearness to Three Mile Island raised in public comment
Key opponents
Protect South Hanover PA; Supervisor Kevin Busher said on June 23 that the supervisors plan to oppose the project at the Zoning Hearing Board
Key supporters
None identified in the record we read

How we got here

January 27, 2026: draft data center ordinance in the supervisors' packet for advertisement. June 8: The Hanover Company emails the township a noise study for its Hummelstown project. June 23: township receives HCI's special exception application and zoning challenge; a crowd fills the meeting. July 1: supervisors vote 5-0 to advertise a data center overlay ordinance. July 14: manager announces an August 11 ordinance hearing and a Zoning Hearing Board hearing on HCI's cases for August 17. July 28: solicitor reports HCI's attorney asked for a continuance. The township posts a notice of hearing pause and a letter to the Zoning Hearing Board about an indefinite extension. September 21: Protect South Hanover PA starts a petition.

Community response

Who is organizing against it

Protect South Hanover PA (Protect SHT, Hershey and Hummelstown), website https://www.protectsouthhanoverpa.org, Facebook groups https://www.facebook.com/share/g/1FE6GBVu3J/ and https://www.facebook.com/share/g/1CuRr57zRA/, petition https://www.change.org/p/protect-south-hanover-township-hummelstown-derry-township-from-hyperscale-data-centers (source_key s17, s18)

Timeline

How it has unfolded

  • 2026-01-27The supervisors' January 27 meeting packet included a draft data center ordinance marked for advertisement. South Hanover Township
  • 2026-06-08The Hanover Company emailed the township a noise study for its Hummelstown project. South Hanover Township
  • 2026-06-23The township received HCI's special exception application for a data center on the 249.5-acre former quarry and a challenge to the township's zoning covering a larger area. Local21 News (WHP)
  • 2026-06-23At a packed meeting, Supervisor Kevin Busher said the project will likely go to the Zoning Hearing Board and the supervisors plan to oppose it. South Hanover Township
  • 2026-07-01At a special meeting with 23 public speakers, the supervisors voted 5-0 to advertise a data center overlay ordinance, pending revisions. South Hanover Township
  • 2026-07-14The manager announced an August 11 hearing on the data center ordinance and said the Zoning Hearing Board would hear HCI's two submissions on August 17. South Hanover Township
  • 2026-07-28The township solicitor reported that the data center applicant's attorney asked for a continuance and the request was before the Zoning Hearing Board's solicitor. South Hanover Township
  • 2026-08-11The supervisors' agenda and minutes for the announced hearing date show no ordinance hearing or vote, and residents asked again that residential parcels be removed from the overlay. South Hanover Township
  • 2026-08-25The solicitor said a colleague, Jim Diamond, has handled the data center case and there was nothing substantive to report, as residents referred to the developer's pause. South Hanover Township
  • 2026-09-08Supervisor Kevin Busher said the board shouldn't support any data center ordinance until a public town hall forum is held. South Hanover Township
  • 2026-09-21Protect South Hanover PA started a petition asking the township to remove residential properties from the overlay and asking the state for a moratorium. Change.org
  • 2026-09-22The supervisors met in executive session on potential litigation over the data center ordinance, and residents spoke about the paused data center proposal and a pending warehouse application. South Hanover Township
Legal record

Filings and legal actions

  • 2026-06-23
    Special exception application South Hanover Township Zoning Hearing Board · n/a

    Asks for a special exception to allow a data center on the 249-acre former Pennsy Supply quarry in the Industrial Park District.

    HCI DP Land Acquisition LLC; South Hanover Township · Hearing set for August 17, 2026, then continued at the applicant's request; the township's public notices page lists a notice of hearing pause
  • 2026-06-23
    Validity challenge to the zoning ordinance (PennLive called it a variance request) South Hanover Township Zoning Hearing Board · n/a

    Argues the township's zoning violates Pennsylvania law by leaving out data centers and asks to allow a data center on a larger property, including the 249-acre Wagner Avenue tract and a 0.01-acre Grandview Road parcel.

    HCI DP Land Acquisition LLC; South Hanover Township · Hearing set for August 17, 2026, then continued at the applicant's request; the township's public notices page lists a notice of hearing pause
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.