All Pennsylvania projects
Contested

Renaissance Park & Innovation Data Center Campus (King of Prussia)

Upper Merion Township, Montgomery County

J. Brian O'Neill's second Montgomery County front: five data center applications totaling more than 4.6 million square feet across King of Prussia, filed just before Upper Merion's stricter data center ordinance took effect and therefore reviewed under the older rules.

ContestedTBD/UndisclosedMixedSE
At a glance

The project by the numbers

StatusOn Appeal
Building area4,600,000 sq ft
Site266.89 acres
Permanent jobs, as claimed717
First announced2026-05-27
Target onlineTBD

Five applications, 4.6 million square feet, denied unanimously and now in court

The number that mattersMore than 20,000 residents signed the petition against the campus. When the Board of Supervisors denied all five applications on August 13, 2026, the crowd applauded, danced and high-fived in the auditorium.
Developer
MLP Ventures (J. Brian O'Neill), the same developer behind 900 Conshohocken Road across the Schuylkill River
Tenant
Undisclosed. O'Neill offered to name the prospective tenants only if township officials signed a nondisclosure agreement, and they declined.
Current stage
The project is on appeal in court: the supervisors' August 13, 2026 denials of all five preliminary land development plans stand, and the developer's September 16 land-use appeals in the Montgomery County Court of Common Pleas were still pending as of an October 23 Inquirer report, in which the developer's attorney said "the appeals of the rejection are ongoing." On October 19 the MLP Ventures entities withdrew the last of their seven Zoning Hearing Board applications, so the township cancelled the October 21 hearings. They'd already dropped their appeals of the zoning officer's July 20 letter on October 7, and on October 19 they dropped the remaining requests for variances by estoppel, each time after the township moved to quash.
Decision body
Upper Merion Township Board of Supervisors, which denied all five plans on August 13, 2026; the Montgomery County Court of Common Pleas, where the developer's land-use appeals are pending. The Zoning Hearing Board has no MLP applications left after the October 19 withdrawals.
Top issues
Scale: about 4.6 million square feet on roughly 267 acres, larger than Philadelphia International Airport; ordinance timing and grandfathering under the older rules; tenant secrecy and the refused nondisclosure agreement; on-site power generation, including generators, substations and backup power the developer wanted declared accessory uses; noise, vibration and heat; fire safety; Renaissance Boulevard parcels on and next to the Crater Resources Superfund site; a 411 Swedeland Road plan sited partly over a former county landfill with methane monitoring wells; a site replacing an operating daycare on Horizon Drive; the township's legal costs to defend its decisions.
Key opponents
Upper Merion Data Centers, organized by Courtney Smith and Zachary Davis, with a Change.org petition that has topped 17,000 signatures; Upper Merion Against Data Centers; the Hughes Park KOP Civic Association; State Sen. Katie Muth; Montgomery County Commissioner Neil Makhija, who told supervisors on August 13 that more than 20,000 people had signed a petition against the plan; neighbors organizing across the river with No Conshy Data Centers.
Key supporters
Steamfitters Local 420 and building trades members citing construction work; the developer’s tax-revenue projections

How we got here

Sketch plans went to the township May 9, 2025, and the zoning officer issued a preliminary opinion on August 6, 2025 that the developer later cited to argue data centers count as a specialized warehouse. The five land development applications were filed in early March 2026, with 600 River Road submitted March 12, the same day Upper Merion adopted stricter data center rules, so they are reviewed under the older rules. The first Planning Commission review on May 27, 2026 drew a packed and at times unruly crowd and produced no recommendation, and township officials declined the tenant nondisclosure agreement in late May. On July 22 the Planning Commission voted unanimously to recommend disapproval of three applications. On August 12 the developer sued and won a temporary injunction, which was vacated August 13; that evening the supervisors voted 5-0 to deny the extension requests and all five preliminary plans. After a July 20 letter from the zoning officer asking about on-site energy generation, the MLP entities filed seven Zoning Hearing Board applications appealing that letter or seeking variances by estoppel. On September 10 the supervisors authorized Solicitor John Walko to oppose them, and on September 16 the developer filed land-use appeals in the Montgomery County Court of Common Pleas through attorney Marc Kaplin, alleging bad faith and asking for a court-appointed referee. The state Department of Environmental Protection's permit tracker lists five of the sites as proposed, with no applications received. The developer withdrew the appeal claims on October 7 and the variance claims on October 19, and the October 21 Zoning Hearing Board hearings were cancelled. The court appeals remain pending.

Update, October 26, 2026. On October 23, 2026 the developer's attorney, Marc Kaplin, told the Philadelphia Inquirer that withdrawing the zoning applications doesn't affect the land-use appeals of the August 13 denials, which he said are ongoing in the Montgomery County Court of Common Pleas.

What is at stake

Impacts raised and open questions

Noise and vibration

High

Residents describe the hyperscale campus as 'power plants with hard drives' that would make the community unlivable; the applications predate the township's stricter noise limits and are reviewed under the older rules.

NBC10 Philadelphia

Air quality

High

Residents raised emissions, vibration and heat concerns across five sites totaling more than 4.6 million square feet in a developed suburban area.

Philadelphia Inquirer

Energy costs and the grid

High

Five-site campus adds substantial load in the same PJM zone as the 900 Conshohocken Road proposal, compounding capacity costs already passed to ratepayers.

Montco.Today

Energy costs and the grid

High

Right to Know records show the same developer told the Governor’s office he was building an 800 megawatt power plant in connection with his Montgomery County data center work and sought state help securing a term sheet with Digital Realty, one of the largest data center companies in the world.

Commonwealth of Pennsylvania (RTK release)

Public safety

High

Part of the 411 Swedeland Road plan sits on the former Montgomery County landfill, where methane monitoring wells under some proposed improvements have exceeded the lower explosive limit in the owner's quarterly reports, the township planner told supervisors on August 13.

Upper Merion Township

Air quality

High

The developer asked the Zoning Hearing Board to declare generators, substations and backup power systems shown on its sketch plans to be accessory uses permitted by right, and has said the campus would generate its own electricity on site.

Upper Merion Township

Energy costs and the grid

Medium

Second large O'Neill proposal in Montgomery County (about 4.6M sq ft); neighbor pushback over scale and local impacts.

Philadelphia Inquirer

Water

Medium

O'Neill states the facilities would use closed-loop water systems; residents and commissioners have pressed for verification of consumption and discharge.

Philadelphia Inquirer

Environmental justice and site legacy

Medium

2100 Renaissance Boulevard is next to the Crater Resources Superfund site, with groundwater monitoring wells tied to the Operable Unit Six plume, and the 2201 to 2901 Renaissance Boulevard campus is on the Superfund site; another plan would replace an operating daycare on Horizon Drive.

Montco.Today

Public safety

Medium

Residents raised fire safety and emergency preparedness for hyperscale facilities at the July 22 review.

NBC10 Philadelphia

Property values

Medium

Neighbors argue the scale of the campus, larger than Philadelphia International Airport, would permanently alter surrounding residential areas.

NBC10 Philadelphia

Water

Medium

The 2201 to 2901 Renaissance Boulevard campus is on the Crater Resources Superfund site, and 2100 Renaissance Boulevard is next to it, with groundwater monitoring wells tied to the site's Operable Unit Six plume, according to the August 13 minutes.

Upper Merion Township

Jobs and tax claims

Low

O'Neill claims property tax increases of 54 percent for the township and 28 percent for the school district, or $7,817 per child annually; permanent staffing for hyperscale data centers is typically small relative to footprint.

Montco.Today

Jobs and tax claims

Low

The developer's August economic impact study claims 15,000 jobs a year during construction, 717 permanent jobs and $55.4 million in local tax revenue. These are the developer's figures and haven't been independently checked.

PhillyVoice
Community response

Who is organizing against it

Upper Merion Data Centers

Township · Founded 2026 · 18,000 signatures

Leaders: Resident organizers including Courtney Smith and Zachary Davis; supported by State Sen. Katie Muth

Tactics: Packed Planning Commission hearings at Upper Merion Area Middle School with overflow crowds, orange "HUGE DATA CENTERS IN UPPER MERION, ABSOLUTELY NOT" signs, a Change.org petition rejecting the campus and all future AI data centers in King of Prussia, coordinated public comment on fire safety, noise, power and zoning

The group estimated 1,000 to 1,200 people at the May hearing, inside and out. At the July 22 review nearly the entire auditorium stood when asked who opposed the project, and the Planning Commission then voted unanimously to recommend disapproval of the three applications before it. Shares a developer and a river with the 900 Conshohocken Road fight in Plymouth Township.

Petition

Hughes Park KOP Civic Association

Neighborhood · Founded 2026

Leaders: Rob Erickson and Patti Erickson

Tactics: Neighborhood organizing in Hughes Park, turnout at Planning Commission and Board of Supervisors meetings, public comment on buffers and vesting, coordination with the wider Upper Merion opposition

The association has focused on the vesting problem: the township adopted far stricter data center rules days after these applications were filed, so the campus is reviewed under the old ordinance. Patti Erickson called that the real kicker for residents.

Upper Merion Against Data Centers

Upper Merion Township and King of Prussia

Tactics: Tracks the zoning and court fight and posts updates for residents

After the October 19 withdrawals it told followers, 'We need to stay informed and stay vigilant,' and said O'Neill is still suing the township. May overlap with Upper Merion Data Centers.

Timeline

How it has unfolded

  • 2025-05-09The developer submits sketch plans for the data center sites to the township. Upper Merion Township
  • 2025-08-06The zoning officer issues the preliminary opinion the developer later cites to argue data centers are permitted as a specialized warehouse. Upper Merion Township
  • 2026-03-12The stricter data center ordinance increases required buffers to residences from 150 feet to 1,000 feet and excludes data centers from a zone previously eligible under the warehouse definition. Because the applications were filed days earlier, Township Manager Anthony Hamaday confirms the plans are vested under the older rules DeSmog
  • 2026-03-12Supervisors adopt the data center ordinance; the 600 River Road application is submitted the same day. Upper Merion Township
  • 2026-05-27First Planning Commission review of the five-site, 4.6M sq ft campus: packed and at times unruly meeting, no recommendation taken; O'Neill calls the project 'an opportunity to change the world for the better' Philadelphia Inquirer
  • 2026-05-27More than 1,000 residents pack the first hearing, with crowds spilling onto the lawn watching on phones; the group Upper Merion Data Centers estimates 1,000 to 1,200 people inside and outside Patch
  • 2026-05-28O'Neill about 4.6M sq ft King of Prussia / Upper Merion data center draws neighbor pushback (Inquirer) Philadelphia Inquirer
  • 2026-05-28Residents object that the campus would upend daily life and threaten long-term health; township manager Anthony Hamaday confirms officials declined O'Neill's offer to name tenants under a nondisclosure agreement because 'they didn't believe it was proper' Philadelphia Inquirer
  • 2026-07-15Township schedules in-depth review: three of the five applications for July 22 and the remaining two for August 12, with meetings moved to Upper Merion Area Middle School to accommodate crowds Philadelphia Inquirer
  • 2026-07-20The zoning officer writes to the developer's counsel asking about on-site energy generation, the letter the Zoning Hearing Board appeals later targeted. Upper Merion Township
  • 2026-07-22Second review: O'Neill returns with revisions to three of five applications; commissioners press on zoning, power generation, engineering and environmental impacts; nearly the entire auditorium stands when asked who opposes the project 6abc Philadelphia
  • 2026-07-22Commissioners vote unanimously to recommend that the three reviewed applications be disapproved, citing outstanding issues and a lack of detail across multiple areas, after a contentious four-hour meeting. Chairman Matt Popek to the developer: "I kind of have to ask what were you doing over the last few months." Told details would come "at the appropriate time," Popek replied, "This is the appropriate time. Right now." Chestnut Hill Local
  • 2026-07-22Vice Chair Bill Jenaway rebuts the developer’s claim that commissioners were playing to the audience: "There was no agenda here tonight other than getting answers from your team about submitted plans and the lack of significant detail that we believe existed, so that we can make an informed decision about whether or not these plans should move forward" Chestnut Hill Local
  • 2026-07-22Planning Commission votes against three of the five data center applications The Chestnut Hill Local
  • 2026-07-31Governor declares himself "a hell no" on the companion 900 Conshohocken Road project after its validity challenge, raising questions about state posture toward the developer's five King of Prussia applications Office of the Governor of Pennsylvania
  • 2026-08-12Remaining two of the five applications scheduled for Planning Commission review Montco.Today
  • 2026-08-12Recommendation due on the final two applications, 600 River Road and 411 Swedeland Road, at Upper Merion Area Middle School Patch
  • 2026-08-12Commission takes up the final two applications, 600 River Road and 411 Swedeland Road, at Upper Merion Area Middle School NBC10 Philadelphia
  • 2026-08-12O’Neill sues Upper Merion Township, its Board of Supervisors and its Planning Commission, saying they violated his right to an extension and treated him unfairly. He writes that it is clear the board intends to decline the offer of extension and instead proceed to deny the applications. A Montgomery County judge grants a temporary injunction freezing township action Philadelphia Inquirer
  • 2026-08-13Deadline for the Board of Supervisors to make a final decision on all five applications Patch
  • 2026-08-13Deadline for the Board of Supervisors to decide all five applications, meeting at 7 p.m. at Upper Merion Area Middle School NBC10 Philadelphia
  • 2026-08-13The judge vacates the injunction Thursday afternoon, clearing the Board of Supervisors to meet and decide 6abc Philadelphia
  • 2026-08-13The Board of Supervisors unanimously DENIES two extension requests and all five preliminary land development plans, finding the applications lacked requested architectural plans, traffic impacts and engineering clarification. Vice Chair William Jenaway: "I don’t want to see our professional staff bullied or coerced. Intimidation, coercion and bullying are not good qualities in a professional leader." Chair Tina Garzillo tells O’Neill he may appeal. The crowd applauds, dances and high-fives; more than 20,000 residents had signed the petition Philadelphia Inquirer
  • 2026-08-13O’Neill vows to appeal: "We are not resubmitting our plans. We never have. We have a plan filed, it’s approved by their zoning officer and we’re absolutely going to appeal to get that plan approved" 6abc Philadelphia
  • 2026-08-13Board denies extension letters and preliminary land development plans for all five sites, developer says he will appeal FOX 29 Philadelphia
  • 2026-08-13Commissioner Makhija tells supervisors more than 20,000 residents signed a petition against the data centers and backs the residents who organized against them. Upper Merion Township
  • 2026-09-10Board votes unanimously to authorize the township solicitor to oppose seven MLP Ventures zoning applications. Chair Tina Garzillo: "We want our solicitor to be actively involved in all these levels, just to protect our decision and our status with the case" The Times Herald
  • 2026-09-16Developer files land-use appeals in the Montgomery County Court of Common Pleas seeking reversal of the Aug 13 denials, preliminary approval, and a court-appointed referee. Attorney Marc Kaplin: "This is what happens when there is public pressure" Philadelphia Inquirer
  • 2026-10-07The applicants withdraw their appeals of the zoning officer's July 20 letter after the township moves to quash them for lack of jurisdiction. Upper Merion Township
  • 2026-10-08Supervisors discuss adding legal funding to the 2027 budget to defend the O'Neill/MLP lawsuits Patch
  • 2026-10-19The applicants withdraw their remaining variance by estoppel claims in all seven Zoning Hearing Board applications, and the township cancels the October 21 hearings. Upper Merion Township
  • 2026-10-20News reports say the developer's land-use appeals in the Montgomery County Court of Common Pleas remain pending after the zoning withdrawals. PhillyVoice
  • 2026-10-23The developer's attorney tells the Inquirer the zoning withdrawals don't drop the court appeals of the supervisors' denials, saying "The appeals of the rejection are ongoing." Philadelphia Inquirer
Legal record

Filings and legal actions

  • 2026-05
    Land development plan Upper Merion Township Planning Commission · 5 applications

    Five separate land development applications totaling more than 4.6 million square feet across Renaissance Boulevard, Horizon Drive, 2100 Renaissance Boulevard and the River/Swedeland Road area. Filed before the township’s stricter data center ordinance took effect, so reviewed under the older rules.

    900 Conshohocken Road LLC affiliates / MLP Ventures (J. Brian O'Neill) · Under review
  • 2026-05-27
    Zoning interpretation dispute Upper Merion Township · n/a

    O'Neill maintains the campus is permitted under current zoning with no variances required; township officials disagreed about whether data centers are allowed in all three zoning districts involved.

    Applicant vs. township officials · Open
  • 2026-08-12
    Court challenge Montgomery County Court of Common Pleas · n/a

    Suit alleging the township violated the applicant’s right to an extension and treated him unfairly during review. A temporary injunction freezing township action was granted August 12 and vacated August 13, after which the board denied all five applications. The developer has said he will appeal the denial.

    J. Brian O'Neill / MLP Ventures v. Upper Merion Township, Board of Supervisors and Planning Commission · Injunction vacated; denial issued
  • 2026-09-16
    Land-use appeals Montgomery County Court of Common Pleas · n/a

    Appeals of the August 13 denials asking the court to reverse them, grant preliminary approval and appoint an independent referee to hold an evidentiary hearing; the filing alleges bad faith and denial over minor technical items.

    MLP Ventures affiliates v. Upper Merion Township Board of Supervisors · Pending
  • 2026-09
    Zoning Hearing Board applications 2026-14 to 2026-20 Upper Merion Township Zoning Hearing Board · Zoning Hearing Board 2026-14 to 2026-20

    Seven applications appealing the zoning officer's July 20, 2026 letter or, in the alternative, seeking a variance by estoppel declaring the data centers, including energy generation infrastructure shown on the sketch plans, permitted by right.

    Breyemere Holding LLC, Innovation River Road LLC, Innovation 411 Fee Owner LLC, Innovation 2100 LLC and Renaissance Campus owners; Upper Merion Township (opposing) · Withdrawn October 19, 2026 (appeal claims withdrawn October 7, variance by estoppel claims withdrawn October 19); October 21 hearings cancelled
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →