- Developer
- Carbon Node East Development, LLC, owned by Keel Infrastructure Corp. (formerly Bitfarms Ltd.), on land owned by Kovatch Enterprises
- Tenant
- No tenant named. Keel said in June 2026 it aimed to sign a major tenant lease at Panther Creek by the end of 2026.
- Current stage
- Nesquehoning Borough Council granted conditional preliminary land development approval in late May 2026, after the borough adopted a data center ordinance in April. DEP held a public meeting and hearing on August 20, 2026 on the NPDES stormwater permit (PAD130057) and the Chapter 105 stream and wetland permit (E1302226-001), and no decision on either has been reported. Carbon Node East said at an August information session that construction would start in 2027 if DEP approves and take up to 20 months. DEP took written comments on both permits through September 4, 2026.
- Decision body
- Pennsylvania Department of Environmental Protection, Northeast Regional Office (NPDES and Chapter 105 permits); Nesquehoning Borough Council and Planning Commission (land development); Carbon County Planning Commission (advisory review)
- Top issues
- Runoff into Dennison Run, Broad Run, Nesquehoning Creek and Exceptional Value wetlands; tree removal; noise; diesel generators and fuel storage; water from the borough's wells; property values near Stock Street and Lake Hauto; emissions from the neighboring waste coal and tire burning plant; tax revenue for the Panther Valley School District
- Key opponents
- Save Carbon County, an environmental nonprofit that has opposed the project and testified at the DEP hearing; a representative of the Lehigh River Stocking Association raised concerns about Exceptional Value streams and brook trout.
- Key supporters
- State Sen. Dave Argall said there appeared to be local support, according to a March 2026 Times News opinion column. A member of the Panther Valley Blueprint Community spoke in favor at the borough's April 22 ordinance hearing.
How we got here
Stronghold Digital Mining's Panther Creek waste coal plant in Nesquehoning was acquired by Bitfarms with the Scrubgrass plant in a $175 million deal completed in March 2025, and Bitfarms later signed a 350 megawatt power agreement with PPL for Panther Creek. November 2025: plans first go to the Carbon County Planning Commission and Bitfarms holds four informational meetings. December 2025: the applicant withdraws its phase 1 preliminary plan to resubmit the full development. February 23, 2026: borough planning commission approves a special exception. March 24, 2026: DEP accepts the Chapter 105 application for technical review. April 21, 2026: county planning commission recommends conditional plan rejection. April 22, 2026: borough council adopts data center Ordinance 2026-03. May 18, 2026: borough planning commission grants unanimous conditional preliminary approval. Late May 2026: borough council grants conditional preliminary land development approval. August 20, 2026: DEP public meeting and hearing in Lansford. Early September 2026: written comment period closes. Along the way DEP received the stormwater permit application on February 25, 2026 and the stream crossing application on March 13; the county planning commission tabled the plan on March 17 and recommended approval of the sewage planning module on June 16; PPL's stormwater permit for a 69 kV tap line to a new substation was listed as issued May 23; Keel stopped Bitcoin mining at the plant on June 29 but keeps selling its power; and DEP published a draft stormwater permit on July 18, 2026 with five years of wetland monitoring.
Update, October 26, 2026. On August 20, 2026 about 75 people attended DEP's information session at Panther Valley Junior-Senior High School, and about a dozen spoke against the project at the hearing that followed. DEP took written comments until September 4, 2026, and Carbon Node East said at an information session that construction could begin in 2027 if DEP approves the permits.