Muncy Data Center (Liberty Group / Danko Holdings II)

Muncy Township, Lycoming County

The Liberty Group's DANKO Holdings II wants to build three data center buildings on about 100 acres off John Brady Drive, says the plan was approved by default, and now faces appeals from neighbors, the township and an environmental group.

ContestedLargeTBD/UndisclosedGreenfieldN Central
At a glance

The project by the numbers

StatusOn Appeal
Building area699,574 sq ft
Site100 acres
First announced2026-06-08

A 100-acre data center plan in Muncy Township, now tied up in court

The number that mattersThe conditional-use plan was formally acknowledged at 2:40 p.m. on April 28, 2026, and the township adopted its data center moratorium at a special meeting later that same day.
Developer
DANKO Holdings II, LP and Fishlips, LLC, both at 101 W. Third St. in Williamsport and both owned by The Liberty Group, led by Daniel Klingerman. Livic Civil of Bloomsburg is listed on the site plan, and attorney Samuel E. Wiser Jr. of Salzmann Hughes, P.C. represents the developer.
Tenant
No end user has been named, and the developer hasn't said how much power the buildings would use.
Current stage
The developer says its conditional use application was deemed approved because the township didn't hold a hearing within 60 days, and it published a notice saying so in July 2026. Neighbors filed a land use appeal in Lycoming County court on August 14, 2026, and the township's answer admits it didn't act in time and asks the court to send the matter back to supervisors for a hearing. The developer has moved to quash that appeal, and Judge William P. Carlucci will hear argument November 6. Green Amendments for the Generations, neighbors and the township are also challenging the deemed approval law itself in a Commonwealth Court case filed September 25, 2026. Meanwhile the township is finishing a data center ordinance, with a public hearing November 4 and adoption planned for December.
Decision body
Muncy Township Board of Supervisors (conditional use and the new zoning ordinance), with the Muncy Township Planning Commission reviewing the draft ordinance. The deemed approval dispute is before Lycoming County court (Judge William P. Carlucci) and the Commonwealth Court.
Top issues
Whether a data center can be approved by default under the deemed approval rule; water for nearby wells and possible withdrawals from the West Branch Susquehanna River; noise, which the solicitor says the developer is trying to avoid conditions on; property values; loss of cropland next to the historic Muncy Farms; and transparency from the developer and the township.
Key opponents
Green Amendments for the Generations, led by founder Maya K. van Rossum, filed the Commonwealth Court challenge with neighboring property owners, including the owners of the historic Muncy Farms, and the township supervisors. Neighboring residents filed the county land use appeal. Township solicitor Joseph F. Orso III opposes the deemed approval and has told residents the fight could last years. Sam Burleigh of Concerned Citizens of Montour County spoke at the township's first planning meeting.
Key supporters
No organized supporters have been reported. The developer hasn't commented publicly, and coverage has described supporters only in general terms, as people who say such projects bring investment and jobs.

How we got here

A zoning permit application dated April 15, 2026 named DANKO Holdings II and Fishlips. On April 22 the township secretary told the developer that plans had to go through the township's formal intake process. The township formally acknowledged a conditional use plan at 2:40 p.m. on April 28 and adopted a moratorium of up to nine months on data center applications at a special meeting later that day; the then-solicitor said it would not be applied retroactively. The proposal became public in June 2026 reporting, and residents spoke at the planning commission's first public meeting on June 24. The supervisors declared the zoning ordinance substantially invalid for data centers on July 8, starting a curative amendment. The developer published a deemed approval notice in the Sun-Gazette on July 15. The solicitor called the filings inconsistent and said roughly half the site lies in neighboring Muncy Creek Township, which says it has received no applications, permits or plan submittals. Neighbors appealed in county court, and in early October Green Amendments for the Generations, neighbors and the township challenged the deemed approval law in Commonwealth Court. The township posted its proposed data center ordinance on October 13, and Judge William P. Carlucci set a November 6 hearing on the developer's motion to quash.

Update, October 26, 2026. On August 14, 2026 neighbors whose home borders the site filed a land use appeal of the deemed approval in Lycoming County court. In its answer the township admitted it didn't act on the application within 60 days or advertise the deemed approval within 10 days, and asked the court to send the matter back to supervisors for a hearing. On September 25, 2026 Green Amendments for the Generations, the township and several residents filed a Commonwealth Court challenge to the deemed approval provisions of the Municipalities Planning Code.

What is at stake

Impacts raised and open questions

Water

High

The site plan shows six water tanks plus water and sewage treatment facilities. At the June 24 planning meeting, the township engineer said any withdrawals from the nearby Susquehanna River would need feasibility studies, including whether pumping is possible during drought, and a neighbor who relies on two wells said he worried his supply could be drained.

Williamsport Sun-Gazette

Noise and vibration

Medium

The township's proposed ordinance would cap equivalent continuous sound at 50 dBA in the daytime and 45 dBA in the evening at suburban receiving properties, limit tonal noise, and allow backup generator testing only from 9 a.m. to 5 p.m. on weekdays with 24 hours' public notice.

Muncy Township

Property values

Medium

A neighboring property owner told the planning commission that a data center could make his property nearly worthless.

Williamsport Sun-Gazette

Visual and light

Medium

The roughly 100-acre site is cornfields downriver from Muncy Farms, home to a 1769 farmhouse described as the oldest in Lycoming County. Land across the highway holds the largely vacant Lycoming Mall.

Pennsylvania Capital-Star (via News From The States)
Community response

Who is organizing against it

Green Amendments for the Generations

Pennsylvania-based environmental rights organization working statewide and nationally

Leaders: Maya K. van Rossum (founder)

Tactics: Commonwealth Court lawsuit under the Environmental Rights Amendment, filed with neighbors and the township supervisors

Van Rossum also leads the Delaware Riverkeeper Network. The Sun-Gazette describes the group as a Bucks County organization.

Website

Timeline

How it has unfolded

  • 2026-04-15Zoning permit application dated for Muncy Data Center off John Brady Drive Williamsport Sun-Gazette
  • 2026-04-22The township secretary writes to the developer that plans and applications must go through the township's formal intake process. Williamsport Sun-Gazette
  • 2026-04-28Conditional-use plan formally acknowledged; township adopts a moratorium of up to nine months on data center applications the same day Williamsport Sun-Gazette
  • 2026-06-08The Muncy Data Center proposal becomes public, showing three data center buildings, water tanks and a water treatment facility off John Brady Drive. Williamsport Sun-Gazette
  • 2026-06-24The planning commission holds its first public meeting on a data center ordinance, hearing concerns about wells, noise and property values. Williamsport Sun-Gazette
  • 2026-07-08Supervisors adopt Resolution 2026-09 declaring the zoning ordinance substantially invalid for data centers and starting a 180-day curative amendment. Muncy Township Board of Supervisors
  • 2026-07-15The developer publishes a notice in the Sun-Gazette claiming deemed approval of its conditional use application. Williamsport Sun-Gazette
  • 2026-07-24Muncy Creek Township says it has received no applications, permits or zoning requests for the data center. Williamsport Sun-Gazette
  • 2026-08-14Neighbors whose home borders the site file a land use appeal of the deemed approval in Lycoming County court. NorthcentralPA.com
  • 2026-09-25Green Amendments for the Generations, the township and several residents file a Commonwealth Court challenge to the Municipalities Planning Code's deemed approval provisions. NorthcentralPA.com
  • 2026-10-05The Capital-Star reports a Commonwealth Court challenge to the Municipalities Planning Code's deemed approval provisions under the Environmental Rights Amendment. Pennsylvania Capital-Star (via News From The States)
  • 2026-10-10Judge William Carlucci sets a November 6 hearing on the developer's motion to quash Williamsport Sun-Gazette
  • 2026-10-13The township posts proposed Data Center Ordinance 2026-01 for public review ahead of a November 4 hearing. Muncy Township
  • 2026-10-14Solicitor Joe Orso tells residents he doesn't expect a data center in the township in the next 10 years, citing the Commonwealth Court challenge and state permitting rules. NorthcentralPA.com
  • 2026-11-04Scheduled public hearing on proposed Data Center Ordinance 2026-01 at 7 p.m. Muncy Township
  • 2026-11-06Scheduled hearing before Judge William P. Carlucci on the developer's motion to quash the neighbors' land use appeal. Williamsport Sun-Gazette
Legal record

Filings and legal actions

  • 2026
    Land use appeal of deemed approval Lycoming County court (Judge William P. Carlucci) · n/a

    Neighbors appealed the developer's notice of deemed approval. The township served an answer. The developer moved to quash, arguing the appeal has defects that can't be cured by amendment. It says it is seeking deemed approval of its conditional use application, not a curative amendment, and that the planning code allows no deemed approval for curative amendments.

    Neighboring residents (appellants); Muncy Township; DANKO Holdings II, LP / Fishlips, LLC (developer, represented by Samuel E. Wiser Jr. of Salzmann Hughes, P.C.) · Pending. Hearing on the developer's motion to quash set for November 6, 2026, 9:30 a.m.
  • 2026
    Constitutional challenge to deemed approval provisions Commonwealth Court of Pennsylvania · n/a

    Claims that the deemed approval provisions of the Municipalities Planning Code conflict with the Environmental Rights Amendment (Article I, Section 27) and violate free expression, property and due process rights.

    Green Amendments for the Generations and its members, neighboring property owners including the Muncy Farms owners, and the Muncy Township supervisors; served on the Pennsylvania Attorney General's office · Pending
  • 2026-08-14
    Land use appeal Lycoming County Court of Common Pleas (Judge William P. Carlucci) · n/a

    The neighbors' land use appeal challenges the deemed approval of the conditional use application. The township's answer admits it didn't act within 60 days or advertise within 10 days and asks the court to send the matter back to supervisors for a hearing. The developer, represented by Samuel E. Wiser Jr. and Tyler R. Beaston of Salzmann Hughes, P.C., moved to quash, arguing the appeal targets the curative amendment instead of the conditional use approval and that the window to raise new grounds has closed.

    Two neighboring residents (appellants); Muncy Township Board of Supervisors; DANKO Holdings II, LP and Fishlips, LLC · Pending. Argument on the developer's motion to quash is scheduled for November 6, 2026 at 9:30 a.m.
  • 2026-09-25
    Constitutional challenge Commonwealth Court of Pennsylvania · n/a

    The petitioners challenge the constitutionality of the Municipalities Planning Code's deemed approval provisions, which the developer relies on. Solicitor Joe Orso said the case provides for an automatic appeal to the state Supreme Court and could take about five years.

    Green Amendments for the Generations, Muncy Township, the Muncy Township Board of Supervisors and several residents · Pending
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.