Energy costs and the grid
MediumMudiita Infra's website described a campus with 750 megawatts of capacity, built in phases and powered with battery storage and solar and no gas, according to Data Center Dynamics.
Data Center DynamicsRansom Township, Lackawanna County
Mudiita Land Venture LLC bought about 530 acres along Ransom Road above the Alliance Landfill in July 2026 while an affiliate's website advertised a 930-acre, 750 megawatt data center campus. Its organizer later said there are no current plans, and nothing has been filed.
Renewable Energy Aggregators Inc. filed plans with federal regulators on July 7, 2026 for the Old Forge Pumped Storage project, which appears to include part of the land. Mudiita Land Venture LLC bought the five parcels from KF Real Estate LLC for $2.4 million on July 14, and the deed was recorded July 20. Data Center Dynamics reported on July 24 that Mudiita Infra's website advertised a 930-acre, 750 megawatt campus. By July 27 the websites were down and the company's organizer told WVIA there were no current plans. Ransom supervisors started writing data center rules on August 3, held a hearing on September 8 and enacted Ordinance No. 3 of 2026 on October 5. At the September 14 meeting, the solicitor reported that the buyer of what the minutes call the Keisling property is considering ways to develop it, including a data center.
Mudiita Infra's website described a campus with 750 megawatts of capacity, built in phases and powered with battery storage and solar and no gas, according to Data Center Dynamics.
Data Center DynamicsAny data center here would face Ransom's new limits: buildings no taller than 40 feet including rooftop equipment, 400-foot setbacks from property lines and roads, 800 feet from homes, schools, parks and similar uses, and 45 decibels at night at homes.
Ransom TownshipIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →