- Developer
- 614 Prospect Road LLC, managed by Allen J. Sherwood III, with GridSwitch Asset Management Services LLC of Coraopolis. Sherwood is president of Pittsburgh-based AJ Sherwood Capital, according to the Butler Eagle. Engineers are KubiTech LLC of South Park Township and KDH Consulting Engineers of Greensburg; Bracewell LLP speaks for the developer.
- Tenant
- No end user announced. Sherwood says the developers are in preliminary talks with potential tenants.
- Current stage
- Preliminary land development plan under review. The planning commission tabled it Oct. 1, 2026. Revised plans dated Oct. 12 arrived Oct. 15 with responses to the township engineer's 16 comments and a request to cut required parking from 1,145 spaces to 125, and the Oct. 22 planning meeting was canceled so the engineer can review them. The 90-day review clock that began Sept. 23 runs out Dec. 22, 2026.
- Decision body
- Forward Township Board of Supervisors, which must approve or deny the land development plan by Dec. 22, 2026 unless the developer grants a written extension. The planning commission is advisory.
- Top issues
- Noise and low-frequency vibration in a valley; Connoquenessing Creek and flooding; well water; gas plant emissions near two compressor stations and a rail yard; heron rookery and bald eagle nest; no dedicated fire department; no township zoning; neighbors from other townships barred from public comment; power plant details put off until final plans; a request to waive most of the required parking; relocating access to an existing gas well pad on the site
- Key opponents
- Misty Hollow Data Center Coalition (informal resident group); Connoquenessing Township Board of Supervisors (chair Angela Fleeger), which voted Oct. 7, 2026 to formally comment on the project's effects on its residents, creek and volunteer fire company.
- Key supporters
- No public supporters identified beyond the developer team. Sherwood says some people support the project.
How we got here
Sherwood says his team surveyed the land for three years before 614 Prospect Road LLC filed preliminary land development plans on Aug. 24, 2026. The Butler County Planning Commission issued review comments on Sept. 17, and the township posted the plans and its engineer's review letter on Sept. 22. The 90-day review period began Sept. 23. The Sept. 24 planning commission meeting was postponed when the crowd exceeded the 100-person capacity of the township building. On Oct. 1, about 400 people came to the meeting in the township maintenance garage, and the commission voted unanimously to table the plan. On Oct. 7, Connoquenessing supervisors voted to participate under the state planning code and to draft their own data center ordinance, and on Oct. 9 they notified Forward by letter. On Oct. 8 Forward's supervisors heard residents but didn't discuss the plan, and their agenda listed a motion to advertise an update to the subdivision and land development ordinance for non-residential development. On Oct. 15 the developer delivered revised plans dated Oct. 12, including a request to allow 125 parking spaces in place of the 1,145 the ordinance requires, and the township canceled the Oct. 22 planning meeting.