Seven data center buildings proposed for the old Publicker distillery
The number that mattersThe July 2026 revised plan adds 13 Bloom power generation platforms labeled at 39 megawatts each, about 507 megawatts of on-site generation, and raises building height from 65 to 98.7 feet.
- Developer
- Limerick Town Center LLC (Madison, Connecticut)
- Tenant
- Not disclosed.
- Current stage
- Application filed (CU 26-03) and revised in July 2026. The applicant extended the township's review deadline to January 29, 2027. The township's hearing page now lists the Planning Commission review for December 10, 2026 at 6:30 p.m. and the supervisors' first conditional use hearing for January 12, 2027 at 6:30 p.m. at the Township Building.
- Decision body
- Limerick Township Board of Supervisors (conditional use)
- Top issues
- Scale on a riverfront brownfield; about 507 megawatts of on-site Bloom power generation added in the July revision; buildings growing from 65 to 98.7 feet; cooling water drawn from wells or the Schuylkill; the swap of 55 acres of State Game Lands 234 to the applicant; a second large data center in one township, near Project Laurel; rules that don't reach pending applications, since this one was filed under the township's 2024 data center zoning.
- Key opponents
- No organized opposition group specific to this site has been reported. Limerick's supervisors voted 3-1 on January 20, 2026 to send the Game Commission a letter opposing the related State Game Lands swap, after the township tallied 109 residents and 21 non-residents against it and 52 people spoke in opposition at the meeting. State Rep. Joe Ciresi and State Sen. Tracy Pennycuick asked the commission to postpone its vote, and Game Commission President Knick and Commissioners Schwalm and DiMarco voted against the swap.
- Key supporters
- No public supporters beyond the applicant are on record. Game Commission members who voted for the related land swap defended it: Commissioner Pride said the commission was swapping 55 acres to get 60, protecting land along the Schuylkill River, and gaining two other parcels, and Commissioner Koppenhafer said 'the winner side is pretty heavy.'
How we got here
June 18, 2024: Limerick amends its zoning with the conditional use overlay that allows data centers, the rules this application falls under. January 20, 2026: supervisors vote 3-1 to oppose a State Game Lands swap with the Publicker site's owner; the manager says no data center application has been filed. January 24: the Game Commission approves the swap 6-3. April 2026: CU 26-03 filed with an April 2 plan for eight two-story buildings, just under 1.8 million square feet, 65 feet tall. May 5: conflict solicitor appointed. July 7: Revision 1 plan with seven buildings up to 98.7 feet and 13 Bloom power platforms. August 31: time extension to January 29, 2027 granted; the September 10 Planning Commission and September 22 supervisors' sessions are postponed. Planning Commission review expected in December and supervisors' hearings in January.
Update, October 26, 2026. By October 26, 2026 the township had scheduled CU 26-03 for the Planning Commission on December 10, 2026 and set the supervisors' first conditional use hearing for January 12, 2027, both at 6:30 p.m.