MediumThe Governor's office says the $70 million expansion will create more than 100 new jobs overall, including at least 58 new full-time jobs at Mount Pleasant, and retain 299 jobs statewide.
Office of Gov. Josh ShapiroMount Pleasant, Hunker and Greensburg (Westmoreland County), Westmoreland County
Hitachi Energy is expanding its Mount Pleasant switchgear and circuit breaker plant, adding a component plant and lab in Hunker and consolidating service work in Greensburg, with more than 100 new jobs. It's on this tracker because Hitachi says its U.S. factory spending answers surging demand for grid equipment, including demand from AI data centers.
On September 23, 2024, Hitachi Energy announced a $60 million expansion of its Mount Pleasant high-voltage switchgear and breaker plant, meant to double production and create about 100 jobs, as part of $155 million in North American investments. On April 8, 2025, the company raised its Pennsylvania commitment to more than $70 million, adding a new high-voltage component plant with a research lab and customer center in Hunker and consolidating its high-voltage service work in Greensburg, and Gov. Josh Shapiro announced more than $329,000 in state grants tied to at least 58 new jobs at Mount Pleasant. DEP issued industrial stormwater coverage for a Hitachi Energy USA site in Hempfield Township in August 2025. In May 2026 the company said the investment, with more than 100 new jobs in Westmoreland County, was still underway.
The Governor's office says the $70 million expansion will create more than 100 new jobs overall, including at least 58 new full-time jobs at Mount Pleasant, and retain 299 jobs statewide.
Office of Gov. Josh ShapiroThe expansion centers on EconiQ switchgear and breakers that don't use sulfur hexafluoride (SF6), which Hitachi calls the most potent greenhouse gas, and includes a new gas management system for switchgear production.
Hitachi EnergyDEP granted new industrial stormwater permit coverage in 2025 for a Hitachi Energy USA site in Hempfield Township, which sets rules for stormwater runoff from industrial activity.
Pennsylvania Bulletin, Vol. 55, No. 32New industrial stormwater coverage for Hitachi Energy USA's site at 100 Distribution Circle, Mount Pleasant mailing address, in Hempfield Township. The filed date is the Pennsylvania Bulletin publication date of the application.
Hitachi Energy USA Inc. · Issued (reported August 9, 2025)In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →