Glassworks Data Campus (former Owens-Illinois glass plant, Clarion Borough)

Clarion Borough, Clarion County

Colliers is marketing the old Owens-Illinois glass plant in Clarion Borough as a 100-acre, expandable data center campus, but no developer, tenant or filing has come forward.

SpeculativeTBD/Undisclosed (marketing describes FirstEnergy West Penn grid power with an optional on-site natural gas generation layer)BrownfieldSW
At a glance

The project by the numbers

StatusSpeculative / Exploratory
First announced2026-01-30

Former Clarion glass plant marketed as a data center campus with up to 700 MW

The number that mattersThe marketing brochure says the campus could reach 700 MW with on-site gas generation, on the grounds of a glass plant that once employed more than 1,500 people.
Developer
Site developed and marketed by the Miles family of companies (Miles Brothers, Terraworks, American Precast), with Colliers as exclusive broker; no data center developer or end user named
Tenant
No tenant or buyer named; brochure offers delivery 18 months after a signed letter of intent
Current stage
The site is being marketed with conceptual designs, and the listing was updated September 22, 2026, according to a research submission we received. Clarion Borough made data centers a permitted use in the CI district in January 2026. We found no building permit, land development application or county planning review for a data center here.
Decision body
Clarion Borough (zoning and building permits) and the Clarion County Planning Commission (land development review)
Top issues
Power demand and on-site gas generation, water draw from the Clarion River, noise and screening, and whether the campus extends beyond the borough's CI district
Key supporters
Colliers and the Miles family companies as site marketers

How we got here

1941 to 2010: Owens-Illinois runs the Clarion glass plant. 2012: plant demolished. May 2017: state approves $5.29 million in grant and loan funds for redevelopment. June 2018: groundbreaking on the $39 million Glassworks Business Park. January 20, 2026: Clarion Borough adopts Ordinance 2025-851 allowing data centers in the CI district. January 30, 2026: exploreClarion reports on the conceptual Glassworks Data Campus. September 22, 2026: listing updated (from a research submission).

Timeline

How it has unfolded

  • 2017-05-25The state approved a $1.03 million grant and a $4.26 million loan to the Clarion County Industrial Development Authority to redevelop the glass plant site. Office of Senator Scott Hutchinson
  • 2018-06-19Work began on the $39 million, 28.5-acre Glassworks Business Park. Penn Business Report
  • 2026-01-20The borough held a public hearing on Ordinance 2025-851 to allow data centers in the CI district, where the former glass plant sits. Clarion Borough
  • 2026-01-20Council voted 6 to 0 to adopt Ordinance 2025-851, making data centers a permitted use in the CI district. Clarion Borough
  • 2026-01-30Local news reported on the conceptual plans for the 100-acre Glassworks Data Campus. exploreClarion
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →