- Developer
- Fezzik Energy, whose partners include land developer Chuck Betters, attorney Jonathan Kamin and Joanna Doven, who is also executive director of the Pittsburgh-based AI Strike Team. Fezzik says it is advancing three sites in Southwestern Pennsylvania and that one is fully entitled and shovel-ready near existing nuclear generation.
- Tenant
- No end user has been named. Fezzik markets its sites to hyperscale data center companies but hasn't announced a buyer or tenant.
- Current stage
- Site marketing and recruitment. No municipal application has been reported in Midland or Aliquippa, and Aliquippa City Council agendas posted from July 2025 through October 2026 show no data center items. The state's data center permit tracker reportedly lists a Fezzik project in Midland, while Beaver County Commissioner Jack Manning said in April 2026 that he had no information on any proposed data centers going through permitting other than the Bruce Mansfield site in Shippingport.
- Decision body
- Midland Borough Council for the Midland site and the City of Aliquippa for the Aliquippa site, with state permits from the Pennsylvania Department of Environmental Protection. Beaver County has no approval role, according to the county solicitor.
- Top issues
- What remains in the ground at the former steel mills, the gas power plants Fezzik says its sites are set up for, use of Ohio River water, how little has been disclosed, and Midland's location directly across the Ohio River from the Beaver Valley nuclear plant.
- Key opponents
- No organized opposition group has been reported.
- Key supporters
- Aliquippa Mayor Dwan Walker, who is also Midland's borough manager, has said he wants old industrial sites redeveloped, possibly as data centers. Fezzik partner Joanna Doven says she has been in frequent contact with Midland's borough council and mayor, who have had many questions.
How we got here
The Wall Street Journal reported on July 12, 2025, on a $2 billion plan to turn a long-closed mill site in Aliquippa into a power plant and data centers, and Fezzik Energy reposted the story on Aug. 4, 2025, under its own name. Fezzik's website says it is advancing three Southwestern Pennsylvania sites, one fully entitled and shovel-ready near existing nuclear generation and a future small modular reactor zone. In February 2026 the Post-Gazette reported that Fezzik was working to attract data centers to former J&L Steel sites in Midland and Aliquippa, and partner Joanna Doven said a Midland project was similar in scale to Aligned's Shippingport plan. In April 2026 Beaver County Commissioner Jack Manning said he had no information on any data centers going through permitting besides the one in Shippingport. No municipal application has been reported.