Air quality
HighAn air quality expert testified that the plant's four turbines, running around the clock, would emit an estimated 28 billion pounds of carbon dioxide, methane and nitrous oxide a year, 28/22 News reported.
28/22 News (WBRE/WYOU)Archbald Borough, Lackawanna County
Essential Energy, LLC wants to replace a former junkyard on Eynon Jermyn Road with a gas-fired power plant of about 400 megawatts next to Staback Park. Archbald Borough Council has held at least five conditional use hearings, and residents and the school district are fighting it.
Essential Energy filed a zoning permit application on March 12, 2026, and Stop Archbald Data Centers says the company was registered with the state the next day. On March 18 Borough Council voted to draft an amendment removing electric generating plants as a permitted use in the I-2 district, and on March 26 the borough received the conditional use application. Attorney Frank Tunis presented a sketch plan to the Planning Commission on April 1, and an updated site plan arrived April 23. Council held the first hearing on April 27, and on May 7 the Planning Commission voted not to comment because the applicant hadn't provided enough information. At the May 21 hearing, Stop Archbald says, the emissions witness acknowledged no air dispersion modeling had been done. Council hired J. Michael Spencer Acoustics on June 17 to advise it, and on June 22 the noise expert testified (Stop Archbald says he predicted 43 decibels at the nearest home against a 45-decibel nighttime limit) and residents' attorney argued the application was a legal nullity. A 92-page safety report presented July 21 repeatedly referred to a data center, and the hearings continued August 18, with a sixth session scheduled for September 29, 2026.
Update, October 26, 2026. As of October 26, 2026, Archbald's conditional use page shows the sixth Essential Energy hearing on September 29, 2026 was continued to a seventh hearing on October 27, 2026 at 5 p.m. in the Valley View High School auditorium.
An air quality expert testified that the plant's four turbines, running around the clock, would emit an estimated 28 billion pounds of carbon dioxide, methane and nitrous oxide a year, 28/22 News reported.
28/22 News (WBRE/WYOU)The applicant's seven-page noise study predicted the plant would meet borough limits day and night, but its author acknowledged equipment hadn't been chosen, placement was unknown and no baseline measurements were taken in nearby neighborhoods.
FOX56 (WOLF)The site is former mining land, and KCI's engineer said past mining would need investigating but called the site suitable despite having no final engineering plans; his safety report repeatedly described a data center instead of a gas plant.
FOX56 (WOLF)The traffic study had no construction traffic analysis for a 6 to 18 month build on Eynon Jermyn Road, which is the only access to the Highlands neighborhood, according to Stop Archbald.
Stop Archbald Data CentersDevelopers told council they can't guarantee lower local electricity costs because the plant's power would be sold on the open market in PJM.
FOX56 (WOLF)The application says the plant would employ about as many people as the salvage yard, which it puts at fewer than 30.
Archbald BoroughLeaders: Tamara Misewicz-Healey (co-founder)
Tactics: Tracks every Essential Energy hearing on its project page, cross-examines the applicant's witnesses and raised money for its legal fund with the Stand Strong 5k at Staback Park in October 2026.
28/22 News describes the group as opposing large-scale data center and power plant development in the borough.
Objectors argue the application is a legal nullity because Essential Energy, LLC was registered with the state on March 13, 2026, one day after the zoning permit application was filed in its name. Stop Archbald says the objection was raised May 21, and FOX56 reported Richards argued it on the record June 22.
Residents represented by attorney Justin Richards; Essential Energy, LLC · Pending; council hasn't ruled publiclyIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →