- Developer
- Allegheny DC Property Co. LLC, which now goes by Dynamo DC and has been reported as an affiliate of the investment firm Davidson Kempner Capital Management. Brian Regli is the company's consultant and main spokesman, Anna Skipper Jewart of Babst Calland is its land use counsel, and Civil & Environmental Consultants is its engineering firm. The company bought the 47.2-acre site for $14.3 million on Nov. 19, 2025, from Cheswick Plant Environmental Redevelopment, an entity owned by Charah Environmental.
- Tenant
- No tenant has been named. The developer describes the campus as built for high-density computing and AI workloads and hasn't said who would use it.
- Current stage
- Springdale Borough Council granted conditional use approval on December 16, 2025, and the borough also granted six variances. Springdale has no subdivision and land development ordinance of its own, so Allegheny County Economic Development's Planning Division is reviewing the developer's 182-page preliminary land development plan, on which county staff made 97 comments. The county held a virtual public meeting on October 14, 2026, and its review found missing and inconsistent information, including no evidence of completed cleanup of arsenic and other contamination. The project website now lists a power draw of up to 240 megawatts, up from the 180 megawatts first proposed, according to WESA. The developer still needs an air quality permit from the Allegheny County Health Department, and the state's permit tracker shows it has water obstruction and encroachment permits but hasn't yet filed for erosion control or brownfield cleanup permits.
- Decision body
- Allegheny County Economic Development's Planning Division decides the preliminary and final land development plans. The Allegheny County Health Department issues the air quality permit, and the Pennsylvania Department of Environmental Protection handles erosion and stormwater permits and the Act 2 cleanup. Springdale Borough Council granted the conditional use, and a borough zoning officer issues zoning and building permits after the county's final approval.
- Top issues
- Noise from more than 100 backup diesel generators and cooling equipment, air pollution from those generators, contaminated soil left from the coal plant including arsenic and methylnaphthalene, well water and groundwater, a church cemetery that borders the site, electricity demand and power bills, property values, and how little say a small borough has over a project this size.
- Key opponents
- Save Allegheny Valley Environment (SAVE), a residents group that meets weekly in Springdale, and Indivisible Allegheny Valley are the main local opposition groups. SAVE treasurer Marty Garrigan says the group wants the county to deny the plan. Regional groups including Protect PT, the Breathe Project, the Environmental Health Project and the Pittsburgh and Southwestern Pennsylvania chapter of the Climate Reality Project have organized protests, a sign-on letter to county leaders and public education. Most residents who spoke at the borough hearings and at the county's Oct. 14, 2026 meeting opposed the project.
- Key supporters
- The Pittsburgh Regional Building Trades backs the project; business manager Jason Markovich told the county it would bring more than 1 million union work hours. Five of seven borough council members voted yes in December 2025, though several, including Councilor Dolly Stephens, said they did so mainly because they expected to lose a lawsuit if they said no. Then-borough manager Terry Carcella said council lacked legal grounds to reject the plan without evidence of harm.
How we got here
The 565 megawatt Cheswick Generating Station retired in 2022, the same year Charah Environmental's redevelopment arm bought the site. Allegheny DC Property Co. submitted its conditional use plans in August 2025. The borough planning commission put off its recommendation three times that fall while the borough hired Thornton Acoustics and Vibrations for an independent noise study, and the Zoning Hearing Board heard the developer's variance requests on Oct. 22, 2025, including a request to raise the height limit to 75 feet. The planning commission recommended approval with conditions on Nov. 17, 2025, and the land sale closed for $14.3 million on Nov. 19. On Nov. 24, council heard about five hours of developer testimony after the only formal objector withdrew, and a real estate appraiser testifying at the hearing estimated roughly $2.55 million a year in property taxes for the borough, school district and county combined. Council approved the conditional use 5 to 2 on Dec. 16, 2025. Borough manager Terry Carcella was hired as Ebensburg's borough manager in March 2026, and Patrick Bono now manages Springdale. Residents planned a protest for May 30, 2026, and on June 10 the developer held an open house showing generators moved from the roof to ground level inside double enclosures, a smaller building, solar panels in the parking lot and closed-loop cooling, while advocates delivered a sign-on letter asking the county to require an air permit first. Allegheny County's virtual public meeting on the preliminary land development plan drew about 80 people on Oct. 14, 2026.