- Developer
- No developer has applied. Councilman Jonah Milliken introduced the June resolution, which the assistant city solicitor helped write, and the city brought in engineering firm Barry Isett & Associates for zoning reviews while the draft ordinance was prepared.
- Tenant
- There's no project or tenant. City officials say no data center application exists in Williamsport.
- Current stage
- Council adopted Resolution 10088 on June 25 and Resolution 10091 on July 9, 2026, starting a 180-day curative amendment period. A public hearing draft of the data center amendment was posted September 29 and went to the city Planning Commission on October 5. Council still has to hold its hearing and vote, and its October 22 meeting was canceled.
- Decision body
- Williamsport City Council adopts the ordinance, after review by the Williamsport Planning Commission.
- Top issues
- Where data centers could go in the city, noise near homes, schools and other sensitive places, water use and the capacity of the city's water and sewer authorities, backup generator emissions, whether other electric customers could see higher costs, and who pays to tear a facility down.
- Key opponents
- No organized opposition group has been reported, and no one has publicly opposed the ordinance.
- Key supporters
- Council voted 6-0 on both resolutions. Councilman Jonah Milliken introduced the June resolution, Council President Eric Beiter signed it and Mayor Derek Slaughter approved it. Council member Yoder urged the city to use the state Department of Community and Economic Development's toolkit and other municipalities' ordinances as models.
How we got here
City Council voted 6-0 on June 25, 2026 to adopt Resolution 10088, declaring the city's 1998 zoning ordinance substantively invalid because it doesn't account for data centers or accessory uses including power generating facilities. The municipal curative amendment route starts a 180-day clock to write data center rules and blocks developer validity challenges while the work is underway. On July 9 council voted 6-0 for Resolution 10091, the required second resolution listing the specific defects. Lycoming County commissioners took the same step in June for the 19 municipalities in the county planning partnership, and Woodward and Pine Creek townships made similar moves. In July the county planning commission's chairman said Woodward and Washington townships and the City of Williamsport had ratified curative amendments setting data center conditions. In September the city brought in Barry Isett & Associates for zoning reviews, and a public hearing draft of the ordinance was posted September 29. The city Planning Commission took it up October 5.