- Developer
- National Land Developers (NLD), which calls itself a partner for data center site selection and development, working with Greener by Design. Joe Marley and Adam Zellner presented the first sketch plan for the applicants in October 2025.
- Tenant
- Not disclosed. No end user has been named publicly.
- Current stage
- Application filed. NLD filed Zoning Hearing Board application 2026-02 for a special exception, with a one-page sketch plan, on July 10, 2026. The township's October 2026 plan status report says the hearing schedule was postponed by the applicant, and no land development plan has been filed. Supervisors adopted Ordinance 257 on July 15 and introduced a third version, Ordinance 260, on Aug. 19. The Bucks County Planning Commission recommended adopting it, while the township Planning Commission recommended an outside legal review first, and supervisors took no action on Sept. 16.
- Decision body
- West Rockhill Township Zoning Hearing Board (special exception); Board of Supervisors (data center ordinances and any land development plan)
- Top issues
- Well water and groundwater in an area that already has PFAS-affected wells, constant noise and low-frequency hum, electricity demand and rates, fire suppression chemicals, an eagle's nest residents say is on the site, and which version of the township's rules applies to an application filed five days before Ordinance 257 passed.
- Key opponents
- Residents who started 'The Petition Against Data Center on Cathill Road in Sellersville' on Change.org, which had 3,690 verified signatures by July 20, 2026; a residents' data center advisory group that drafted tougher rules based on PennFuture's model ordinance; and the nearly 200 residents who turned out in April 2026.
- Key supporters
- No public supporters beyond the applicants have been reported. In 2025 they pitched the project as low-traffic and tax-generating, with high-paying jobs.
How we got here
NLD and Greener by Design showed the Planning Commission an informal sketch plan for 215 Cathill Road on Oct. 14, 2025. Supervisors adopted a first data center ordinance (Ordinance 256) on April 15, 2026 before nearly 200 residents, promising changes. On May 20 they advanced Ordinance 257 and formed a citizens advisory committee. The Planning Commission recommended against Ordinance 257 as drafted on June 9. NLD filed its Zoning Hearing Board application on July 10, and supervisors adopted Ordinance 257 on July 15. They introduced Ordinance 260 on Aug. 19, the Bucks County Planning Commission endorsed it Sept. 2, and the township Planning Commission recommended an outside legal review before adoption.