All Pennsylvania projects
Contested

West Rockhill Township Data Center (Cathill Road)

West Rockhill Township, Bucks County

National Land Developers wants to build a data center at 215 Cathill Road near Sellersville, now listed by the township as a 350,000 square foot plan, and has asked the Zoning Hearing Board for a special exception while West Rockhill works on a third round of data center rules.

ContestedMid-sizeTBD/UndisclosedBrownfieldSE
At a glance

The project by the numbers

StatusApplication Filed
Building area350,000 sq ft
Permanent jobs, as claimed18
First announced2025-10-14
Target onlineTBD

A zoning application for Cathill Road while the township rewrites its rules

The number that mattersWest Rockhill has written three versions of its data center ordinance in six months, and the developer filed its zoning application five days before the second version was adopted.
Developer
National Land Developers (NLD), which calls itself a partner for data center site selection and development, working with Greener by Design. Joe Marley and Adam Zellner presented the first sketch plan for the applicants in October 2025.
Tenant
Not disclosed. No end user has been named publicly.
Current stage
Application filed. NLD filed Zoning Hearing Board application 2026-02 for a special exception, with a one-page sketch plan, on July 10, 2026. The township's October 2026 plan status report says the hearing schedule was postponed by the applicant, and no land development plan has been filed. Supervisors adopted Ordinance 257 on July 15 and introduced a third version, Ordinance 260, on Aug. 19. The Bucks County Planning Commission recommended adopting it, while the township Planning Commission recommended an outside legal review first, and supervisors took no action on Sept. 16.
Decision body
West Rockhill Township Zoning Hearing Board (special exception); Board of Supervisors (data center ordinances and any land development plan)
Top issues
Well water and groundwater in an area that already has PFAS-affected wells, constant noise and low-frequency hum, electricity demand and rates, fire suppression chemicals, an eagle's nest residents say is on the site, and which version of the township's rules applies to an application filed five days before Ordinance 257 passed.
Key opponents
Residents who started 'The Petition Against Data Center on Cathill Road in Sellersville' on Change.org, which had 3,690 verified signatures by July 20, 2026; a residents' data center advisory group that drafted tougher rules based on PennFuture's model ordinance; and the nearly 200 residents who turned out in April 2026.
Key supporters
No public supporters beyond the applicants have been reported. In 2025 they pitched the project as low-traffic and tax-generating, with high-paying jobs.

How we got here

NLD and Greener by Design showed the Planning Commission an informal sketch plan for 215 Cathill Road on Oct. 14, 2025. Supervisors adopted a first data center ordinance (Ordinance 256) on April 15, 2026 before nearly 200 residents, promising changes. On May 20 they advanced Ordinance 257 and formed a citizens advisory committee. The Planning Commission recommended against Ordinance 257 as drafted on June 9. NLD filed its Zoning Hearing Board application on July 10, and supervisors adopted Ordinance 257 on July 15. They introduced Ordinance 260 on Aug. 19, the Bucks County Planning Commission endorsed it Sept. 2, and the township Planning Commission recommended an outside legal review before adoption.

What is at stake

Impacts raised and open questions

Water

Medium

At the 2025 sketch review a resident estimated 5,000 gallons a day per building plus fire suppression would exceed the 10,000 gallon a day threshold for a water resource impact study, and neighbors worried about their wells. The applicant said it prefers public water and could switch to a closed-loop system.

West Rockhill Township

Noise and vibration

Medium

Neighbors raised noise bouncing off the Route 309 corridor, and the applicant said noise studies would come during land development. Ordinance 260 would add sound limits by zoning district, limits on tonal noise and a required sound and vibration study by an acoustical expert.

West Rockhill Township

Public safety

Medium

A resident asked about fire suppression chemicals given existing PFAS contamination of area wells; the applicant said the chemical hadn't been chosen and would depend on the fire department or state code.

West Rockhill Township

Jobs and tax claims

Low

The applicants told the Planning Commission in 2025 the facility would employ about 18 people across three shifts.

West Rockhill Township
Community response

Who is organizing against it

West Rockhill Data Center Citizens Advisory Group

West Rockhill Township · Founded 2026

Tactics: Drafting ordinance amendments based on PennFuture's model ordinance, public comment, urging support for state moratorium bills

Supervisors approved a citizens advisory committee on May 20, 2026. The group drafted a second set of amendments, and the Aug. 19 supervisors' minutes say Ordinance 260 incorporates the vast majority of its recommendations.

The Petition Against Data Center on Cathill Road in Sellersville

West Rockhill Township · Founded 2026 · 3,690 signatures

Tactics: Online petition

Started by two neighbors who live across from the site; 3,690 verified signatures as of July 20, 2026.

Timeline

How it has unfolded

  • 2025-10-14The applicants present an informal sketch plan for a data center of 150,000 to 200,000 square feet at 215 Cathill Road to the Planning Commission. West Rockhill Township
  • 2026-04-15West Rockhill Township preemptive ordinance approved
  • 2026-05-20Supervisors authorize advertising Ordinance 257 and create a Data Center Citizens Advisory Committee. West Rockhill Township
  • 2026-06-09The Planning Commission votes 4-1 to recommend against Ordinance 257 as drafted, citing legal risks. West Rockhill Township
  • 2026-07-10Zoning Hearing Board application and sketch plan filed for 215 Cathill Road Bucks County Herald
  • 2026-07-15Supervisors adopt Ordinance 257 by a 3-0 vote and direct the solicitor to draft a third version with the advisory group's changes. West Rockhill Township
  • 2026-08-19Ordinance 260, the third version, is introduced and sent to the township and county planning commissions for review. West Rockhill Township
  • 2026-08-25Township moves to draft a third version with changes from its Data Center Citizens Advisory Committee Bucks County Herald
  • 2026-09-02The county planning commission recommends that supervisors adopt Ordinance 260 as submitted. West Rockhill Township
  • 2026-09-16Supervisors review the Planning Commission's advice to get an outside legal review of Ordinance 260 and the township planner's recommendations, and take no action. West Rockhill Township
Legal record

Filings and legal actions

  • 2026-07-10
    Zoning Hearing Board application for special exception West Rockhill Township Zoning Hearing Board · Application 2026-02

    Request for a special exception to build a data center at 215 Cathill Road, filed with a one-page sketch plan. No land development plan has been filed.

    National Land Developers (applicant); West Rockhill Township · Hearing schedule postponed by the applicant, per the township's October 2026 plan status report
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →