- Developer
- No developer has applied. The rewrite was prepared by consultant Michael Baker International with a township task force, township staff, Township Manager and Codes Officer Larry Barrick Jr., engineer Paul Wilson and Solicitor Mark Allshouse.
- Tenant
- There is no project or tenant. The ordinance sets the rules any future data center would have to meet.
- Current stage
- Ordinance 2025-03 has been in effect since September 9, 2025. Any data center would need conditional use approval from the Board of Supervisors. No data center items appear on township agendas through October 2026.
- Decision body
- West Pennsboro Township Board of Supervisors (in 2025, Chairman Donald Agar, Vice Chairman Charles Finkenbinder and Supervisor Richard Mains), which adopted the ordinance and would hear any conditional use application.
- Top issues
- Where data centers can be built, protecting private wells and streams with a water feasibility study (the township manager called water a major concern for small townships, and The Sentinel noted a developer might have to drill a well or draw from the Conodoguinet Creek), noise at the property line, effects on electric rates, and truck and car access, since sites must front a minor arterial or major collector road and file a traffic study.
- Key opponents
- No organized opposition group has been reported. At the August 25, 2025 hearing one resident asked where data centers could go, and was told only in the Industrial zone.
- Key supporters
- The three supervisors adopted the rewrite unanimously. Consultant Troy Truax of Michael Baker International told the hearing the data center regulations were added to help protect the township, and Township Manager Larry Barrick told The Sentinel that a resident's concerns about data centers in Loudoun County, Virginia, prompted the rules.
How we got here
The township worked on a full zoning rewrite with a task force and Michael Baker International from at least January 2024, when it held a public open house. On July 28, 2025 the supervisors unanimously authorized advertising the new ordinance and map. On August 25, 2025 they held hearings and unanimously adopted Ordinance 2025-03 (zoning text) and Ordinance 2025-04 (zoning map), effective September 9, 2025. In early September 2025, Township Manager Larry Barrick told The Sentinel that a resident's concerns about data centers in Loudoun County, Virginia, had prompted the data center rules.