All Pennsylvania projects
Ordinance response

West Pennsboro Township Zoning Rewrite

West Pennsboro Township, Cumberland County

A zoning response in West Pennsboro Township, Cumberland County, where a full rewrite of the zoning ordinance adopted in August 2025 allows data centers only as conditional uses in the Industrial district, with set standards for water, noise and setbacks.

Ordinance responseN/AS Central
At a glance

The project by the numbers

StatusOrdinance Response
First announced2025-08

West Pennsboro Township limited data centers to its industrial zone in a 2025 zoning rewrite

The number that mattersWest Pennsboro requires a data center applicant to show proof of Susquehanna River Basin Commission approval if it will withdraw 100,000 gallons a day or more, or consume 20,000 gallons a day or more.
Developer
No developer has applied. The rewrite was prepared by consultant Michael Baker International with a township task force, township staff, Township Manager and Codes Officer Larry Barrick Jr., engineer Paul Wilson and Solicitor Mark Allshouse.
Tenant
There is no project or tenant. The ordinance sets the rules any future data center would have to meet.
Current stage
Ordinance 2025-03 has been in effect since September 9, 2025. Any data center would need conditional use approval from the Board of Supervisors. No data center items appear on township agendas through October 2026.
Decision body
West Pennsboro Township Board of Supervisors (in 2025, Chairman Donald Agar, Vice Chairman Charles Finkenbinder and Supervisor Richard Mains), which adopted the ordinance and would hear any conditional use application.
Top issues
Where data centers can be built, protecting private wells and streams with a water feasibility study (the township manager called water a major concern for small townships, and The Sentinel noted a developer might have to drill a well or draw from the Conodoguinet Creek), noise at the property line, effects on electric rates, and truck and car access, since sites must front a minor arterial or major collector road and file a traffic study.
Key opponents
No organized opposition group has been reported. At the August 25, 2025 hearing one resident asked where data centers could go, and was told only in the Industrial zone.
Key supporters
The three supervisors adopted the rewrite unanimously. Consultant Troy Truax of Michael Baker International told the hearing the data center regulations were added to help protect the township, and Township Manager Larry Barrick told The Sentinel that a resident's concerns about data centers in Loudoun County, Virginia, prompted the rules.

How we got here

The township worked on a full zoning rewrite with a task force and Michael Baker International from at least January 2024, when it held a public open house. On July 28, 2025 the supervisors unanimously authorized advertising the new ordinance and map. On August 25, 2025 they held hearings and unanimously adopted Ordinance 2025-03 (zoning text) and Ordinance 2025-04 (zoning map), effective September 9, 2025. In early September 2025, Township Manager Larry Barrick told The Sentinel that a resident's concerns about data centers in Loudoun County, Virginia, had prompted the data center rules.

What is at stake

Impacts raised and open questions

Water

Medium

Data centers must use public water and sewer and file a water feasibility study covering wells and streams within 1,000 feet and long-term safe yield; none can be approved if it would harm nearby wells, and SRBC approval is required at 100,000 gallons a day of withdrawal or 20,000 gallons a day of consumptive use.

West Pennsboro Township

Noise and vibration

Medium

Data center noise can't exceed 70 dBA at the property line, measured by an independent expert paid by the applicant, except during power outages.

West Pennsboro Township

Water

Medium

Township Manager Larry Barrick told The Sentinel that water is a major concern for small townships, and the article said a data center developer here might have to drill a well or draw water from the Conodoguinet Creek.

The Sentinel (via GovTech)

Visual and light

Low

Data centers need a 25-acre lot with 150-foot front and rear and 100-foot side setbacks, and buildings can be up to 75 feet tall.

West Pennsboro Township

Energy costs and the grid

Low

Applicants should provide an interconnection letter from the electric provider and note any known effects on electric rates for other users.

West Pennsboro Township
Timeline

How it has unfolded

  • 2024-01-17The township holds a public open house on the zoning ordinance rewrite. West Pennsboro Township
  • 2025-07-28Supervisors unanimously authorize advertising the rewritten zoning ordinance and new zoning map for public hearings. West Pennsboro Township
  • 2025-08-25After hearings, supervisors unanimously adopt Ordinance 2025-03, which allows data processing centers only as conditional uses in the Industrial district, and Ordinance 2025-04, the new zoning map. West Pennsboro Township
  • 2025-09-03Township Manager Larry Barrick tells The Sentinel a resident's concerns about Loudoun County, Virginia, prompted the data center rules and calls water a major concern. The Sentinel (via GovTech)
  • 2025-09-09The new zoning ordinance, including its data center standards, takes effect. West Pennsboro Township
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →