Property values
LowThe withdrawn plan placed a 150,000-square-foot building less than 300 feet behind several homes along Gravel Pike, and the owners of a farm next to the site worried health effects could force them to move.
Town & CountryUpper Hanover Township, Montgomery County
Hanover Development L.P. withdrew both applications for a 150,000-square-foot data center on about 37 acres off Gravel Pike on October 14, 2026; the owner is weighing the site's existing light industrial zoning or a residential plan, which would need rezoning.
June 9, 2026: conditional use application and validity challenge delivered at noon, about seven hours before supervisors unanimously adopt Ordinance 2026-04. June 19: the developer waives the 60-day hearing deadline and asks to go first with the conditional use hearing. July 6: a joint supervisors and Planning Commission meeting on the new ordinance draws a large crowd opposed to the data center. July 14: supervisors hire special solicitor Joseph C. Kuhls for the hearings. August 11: solicitor reports a 163-townhouse offer tied to a January postponement, or else a sale to an unnamed third party for the data center. September 8: 138-townhome alternative presented and called too dense. October 13: Robert Downs announces the withdrawal and shows a 60-home sketch; supervisors suggest about 30 homes. October 14: withdrawal letters received.
The withdrawn plan placed a 150,000-square-foot building less than 300 feet behind several homes along Gravel Pike, and the owners of a farm next to the site worried health effects could force them to move.
Town & CountryThe plan showed a gas line that runs through the property being relocated to make room for the building.
Town & CountryResidents raised concerns about strain on groundwater and asked for strict stormwater standards at the July 6 ordinance meeting.
Town & CountryIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →