DEP is reviewing permits for what it calls the Triboro Industrial Park Data Center on about 548 acres owned by Ercor Triboro LLC at the Jessup and Olyphant border. Olyphant says the land is approved only for warehouses after data center plans were pulled in May 2026, but PPL's transmission plans point to a large new power customer there.

ContestedTBD/UndisclosedGreenfieldNEPA
At a glance

The project by the numbers

StatusUnder Review
Site548 acres
First announced2026-04

State permits move ahead on Triboro land where a nine-building data center plan was filed, then pulled

The number that mattersPPL's plan calls for two parallel double-circuit 230-kilovolt lines running about three miles from a new Winton Switchyard to 'a new customer facility near Moosic Lake Road,' which WVIA reported appears to be a data center on the Ercor Triboro land.
Developer
Ercor Triboro LLC, the landowner and permittee on DEP's stormwater permit (DEP's notice lists an address at 207 High Point Drive, Victor, N.Y.), which WVIA traces to Sansone Group, a St. Louis commercial real estate firm. Olyphant's records also refer to the developer as the Tri-Boro Commerce Park.
Tenant
No end user has been named. PPL officials said nondisclosure agreements are in place and wouldn't say which developer or company the new lines would serve, according to WVIA.
Current stage
Under DEP review as of October 22, 2026: the construction stormwater permit has been issued and a water obstruction and encroachment permit is pending. Locally, the data center plans were pulled before Olyphant's May 18, 2026 planning commission meeting, the borough says the land is approved only for warehouses, and any data center would need conditional use approval from Olyphant council. A lawsuit by Ercor against the borough is pending.
Decision body
Pennsylvania DEP (stormwater permit PAC350120 and water obstruction permit E3502221-006); Olyphant Borough Council, which must grant conditional use for any data center in its CM-2 district; the Pennsylvania Public Utility Commission, which must approve PPL's transmission project. DEP's permits also list Jessup and Throop boroughs.
Top issues
Turning an approved warehouse park into data centers; new 230-kilovolt PPL transmission lines and who pays for them; Eddy Creek and abandoned mine drainage; tree clearing north of the Eales Preserve; noise limits; cancer and pollution worries tied to the area's industrial past; lawsuits over Olyphant's zoning vote and noise rules
Key opponents
Stop Olyphant Data Centers (co-organizer Eva Rappenglueck), which rallied at Fern Hill Park on Aug. 2, 2026; the Lackawanna Citizens Overwatch Project (founder and president Aline Browning), which urged Olyphant council on Oct. 13, 2026 to adopt its four-page list of recommended changes to the data center ordinance; Lackawanna County Commissioner Bill Gaughan, who urged Olyphant council in June 2026 to weigh cumulative health effects.
Key supporters
No public supporters of a data center here have been identified. Olyphant Council President Baldan said council made data centers a conditional use on the solicitor's advice so it could restrict them, and that the borough would benefit from providing the electricity if one were allowed.

How we got here

WVIA reports Ercor Triboro LLC bought the roughly 548-acre property for $17.5 million in June 2025, and Olyphant had approved warehouse lots there. In March 2026, PPL published plans for transmission lines to a new customer near Moosic Lake Road and scheduled an open house in Throop for March 31. In April 2026, DEP issued a blasting permit for the 'Triboro Warehouse,' Olyphant council's April 14 vote on its data center ordinance drew a Tri-Boro lawsuit, and the borough received a nine-building data center zoning application. On April 21, PPL told an open house its new lines would serve data centers, and WVIA reported its map shows a customer on the Ercor land. By May 9, DEP had issued the construction stormwater permit to Ercor Triboro LLC, and on May 8 it issued a second blasting permit for 'Triboro Revision 2 Commercial Development.' The Triboro Commerce Park land development plan was pulled before the May 18 planning commission meeting. On June 9, Olyphant settled the Tri-Boro lawsuit, and the solicitor said the ordinance stands. Stop Olyphant Data Centers rallied on Aug. 2. A water obstruction and encroachment application was submitted to DEP on Aug. 25, and by Sept. 8 the borough had filed preliminary objections in a separate Ercor lawsuit. On Oct. 13, the borough said the development is approved only for warehouses.

What is at stake

Impacts raised and open questions

Energy costs and the grid

High

PPL plans two parallel double-circuit 230 kV lines running about three miles from a new Winton Switchyard to a new customer near Moosic Lake Road. PPL says the customer pays for lines into its facility, while regional improvements go into the rate base that all customers pay.

WVIA News

Water

Medium

Eddy Creek runs through the property and dips into abandoned coal mines, carrying acid mine drainage into the Lackawanna River, WVIA reported; a DEP water obstruction and encroachment permit for the project is pending.

WVIA News

Visual and light

Medium

Land clearing on the property was under way by April 2026, and the borough said timbering is allowed; residents cited the tree clearing at the Aug. 2 rally.

Olyphant Borough

Environmental justice and site legacy

Medium

The state Health Department has been assessing cancer rates around the closed Cinram plant in Olyphant, and residents at borough meetings have cited it, the Marjol site and the Keystone Sanitary Landfill as burdens the area already carries.

WVIA News
Community response

Who is organizing against it

Stop Olyphant Data Centers

Olyphant and the Mid Valley, Lackawanna County

Leaders: Eva Rappenglueck, co-organizer

Tactics: Rally at Fern Hill Park on Aug. 2, 2026; sharing information with residents; speaking at Olyphant council and planning meetings.

Organized against the proposed TriBoro data centers. We didn't find a website, Facebook page, petition or donation link.

Lackawanna Citizens Overwatch Project (LCOP)

Mid Valley, Lackawanna County

Leaders: Aline Browning, founder and president

Tactics: Gave Olyphant council a four-page list of recommended changes to its data center ordinance and urged adoption on Oct. 13, 2026; holds town halls on cancer concerns around the former Cinram plant in Olyphant.

The group's main focus has been chemical exposure concerns around the former Olyphant plant; it has also pressed council on data center rules. No website or social media link was found.

Timeline

How it has unfolded

  • 2025-06The Sansone Group affiliate buys the roughly 548-acre Triboro property for $17.5 million, according to WVIA. WVIA News
  • 2026-03-25PPL's Archbald Mountain plan includes two double-circuit 230 kV lines to a new customer facility near Moosic Lake Road; an open house is set for March 31 in Throop. WVIA News
  • 2026-04Olyphant receives a zoning application for a nine-building data center. Olyphant Borough
  • 2026-04-09DEP issues a construction blasting permit in Olyphant for the revision of the Triboro Warehouse. Pennsylvania Bulletin, Vol. 56, No. 17 (DEP notices)
  • 2026-04-14Council's disputed vote on its CM-2 data center ordinance, which covers the Triboro land, leads to a Tri-Boro lawsuit. Olyphant Borough
  • 2026-04-21At an open house, PPL confirms its new lines are for data centers; WVIA reports PPL's map shows a customer on the Ercor Triboro land. WVIA News
  • 2026-05-08DEP issues a second blasting permit, for Triboro Revision 2 Commercial Development. Pennsylvania Bulletin
  • 2026-05-09The Pennsylvania Bulletin reports DEP issued construction stormwater general permit PAC350120 to Ercor Triboro LLC for land in Jessup, Olyphant and Throop. Pennsylvania Bulletin
  • 2026-05-18The Triboro Commerce Park land development plan, listed on the planning commission agenda, is pulled before the meeting. Olyphant Borough
  • 2026-06-09Council approves a stipulation settling the Tri-Boro Commerce Park lawsuit, and the solicitor says the data center ordinance stands. Olyphant Borough
  • 2026-08-02Residents rally at Fern Hill Park against the proposed TriBoro data centers. 28/22 News (WBRE/WYOU)
  • 2026-08-25A water obstruction and encroachment permit application, E3502221-006, is submitted to DEP. Pennsylvania Department of Environmental Protection
  • 2026-09-08The solicitor reports preliminary objections filed in the Ercor lawsuit and says the ordinance can't be changed while it's pending. Olyphant Borough
  • 2026-10-13The borough says the development is approved only for warehouses, and the Lackawanna Citizens Overwatch Project urges ordinance changes. Olyphant Borough
Legal record

Filings and legal actions

  • 2026
    Land use lawsuit over zoning vote Not stated in borough records · n/a

    Dispute over whether council's April 14, 2026 vote adopted the CM-2 data center zoning amendment. After the settlement, the solicitor said the amendment was adopted and the curative amendment no longer applies.

    Tri-Boro Commerce Park v. Olyphant Borough · Settled; council approved a stipulation of settlement June 9, 2026
  • 2026
    Lawsuit Not stated in borough records · n/a

    Planning commission minutes from June 29, 2026 describe a new Tri-Boro lawsuit over the borough's noise ordinance. Council minutes in August and September call it the Ercor lawsuit and say Ercor isn't contesting the data center zoning amendment, though the solicitor said the ordinance can't be amended while the suit is pending.

    Ercor (Tri-Boro) v. Olyphant Borough · Pending; the borough filed preliminary objections (reported Sept. 8, 2026)
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.