- Developer
- TECfusions Inc. of Clearwater, Fla., through TECfusions Keystone LLC. Simon Tusha is the founder and Denis Minihane is chief executive. In July 2026 TECfusions agreed to go public through a merger with Apex Treasury Corp., which it expects to close in the fourth quarter of 2026.
- Tenant
- TECfusions says Building J is live and fully leased, with 2 MW running and 10 MW more contracted, but it hasn't named the tenant. AI cloud company TensorWave has a capacity commitment with TECfusions, and a May 2026 company release says TensorWave is splitting 20 MW between Arizona and Pennsylvania.
- Current stage
- Building J is operating, according to TECfusions. The planning commission recommended the data center zoning ordinance 5-0 on October 20, 2026, and the supervisors adopted it unanimously on October 22. WESA reported that it requires new or expanded data center buildings to be at least 1,000 feet from homes, caps noise at 75 decibels during the day and 65 overnight, requires closed-loop water cooling, limits each diesel backup generator to 120 hours a year, and requires data centers to provide their own power and sign a community benefit agreement with the township. The moratorium ends November 2, and Protect PT's land use appeal is before the Westmoreland County Court of Common Pleas.
- Decision body
- Upper Burrell Township Board of Supervisors (Chairman Ross Walker III, Vice Chairman Kenneth Slahtovsky and Supervisor Scott Brown), advised by the township planning commission, for zoning and land development. DEP's Southwest Regional Office decides the air operating permit, and the Westmoreland County Court of Common Pleas will decide the land use appeal.
- Top issues
- Whether TECfusions should have had to go through a zoning hearing before expanding (the subject of the appeal), on-site gas turbines, boilers and generators and their emissions, a possible on-site power plant the township doesn't yet regulate, noise and vibration, water use and well testing, electric rates, and how much the public knows about work inside Building J.
- Key opponents
- Protect PT, a Harrison City environmental group led by executive director Gillian Graber, filed a land use appeal with two residents on August 25, 2026 and holds monthly Upper Burrell community meetings at Penn State New Kensington. A member of Save Allegheny Valley Environment, a volunteer group formed to fight a Springdale data center, has also spoken at township meetings. More than 50 residents came to the September 2 supervisors' meeting, and most of them opposed the project, according to PublicSource.
- Key supporters
- State Rep. Jill Cooper and Sen. Joe Pittman praised the project when it was announced. At the September 2, 2026 meeting, Chairman Ross Walker said he's for it and believes it's a good thing overall, but that the township will govern it, according to the minutes.
How we got here
TECfusions closed on vacant buildings at the former Arconic Technology Center in December 2024 and announced the 1,395-acre Keystone Connect campus on January 14, 2025, with plans for 3 gigawatts of natural gas-fired capacity over six years and 12 MW available right away. State Rep. Jill Cooper and Sen. Joe Pittman welcomed it, and the company was awarded a $2 million Redevelopment Assistance Capital Program grant. In 2025 DEP transferred the site's existing wastewater permits to TECfusions Keystone LLC, and in September 2025 it received the company's application for a state air operating permit. TECfusions has leased space to the AI cloud company TensorWave. After residents pressed for a pause, supervisors voted 3-0 on May 6, 2026 to start a 180-day moratorium on new data center applications, which didn't cover work already underway in Building J. July 2026 reporting found officials still seeking answers: the company says cooling will be closed-loop and filled mostly with glycol, with power from on-site gas wells, and it told TribLIVE that township officials describing water use 'must have been mistaken.' The planning commission approved a draft ordinance on July 21, and on July 22 TECfusions announced it would go public through a merger with Apex Treasury Corp. Supervisors approved a land development plan for Building J upgrades on August 5. Protect PT and two residents appealed that approval in county court on August 25, and two days later TECfusions announced the site was live and running on turbines. The township posted a revised draft ordinance on September 18 that adds a 5 to 10 year master plan requirement, and DEP published its intent to issue the air permit on October 3, 2026. Without a data center ordinance, current operations have been treated as a research and technology park, an allowed use in the industrial zone. Full build-out could take decades.
Update, October 26, 2026. On October 20, 2026 the Upper Burrell planning commission voted 5-0 to recommend the data center ordinance, and on October 22, 2026 the supervisors adopted it unanimously. WESA reported that the ordinance requires new or expanded data center buildings to be at least 1,000 feet from homes, caps noise at 75 decibels by day and 65 overnight, requires closed-loop cooling, limits each diesel backup generator to 120 hours a year, requires data centers to provide their own power and requires a community benefit agreement with the township, with $500 a day fines for violations. Supervisors said they'll work next on an ordinance for power plant construction.