Energy costs and the grid
HighCo-located behind-the-meter arrangement triggers cost-shift to ratepayers; flagship FERC ER24-2172 case.
FERCSalem Township, Luzerne County
Amazon Web Services bought Talen Energy's data center campus beside the Susquehanna nuclear plant in 2024 and is building it out on about 1,200 acres toward as many as 20 data centers, powered under a deal with Talen for up to 1,920 megawatts.
Talen started the campus in 2021 and sold it to AWS for $650 million in March 2024. Salem Township's planning commission recommended Amazon's overlay district in April 2024, and supervisors, who had already approved a 10-year tax break for Amazon, approved the district after a May 28, 2024 hearing. PJM's request to raise the co-located load from 300 to 480 megawatts was rejected by FERC 2-1 on November 1, 2024, and Talen's subsidiary took the case to the Fifth Circuit on January 16, 2025. Gov. Shapiro announced Amazon's $20 billion statewide plan on June 9, 2025, and on June 11, 2025 Talen and Amazon replaced the co-location deal with a 1,920 megawatt agreement through 2042. Amazon lists October 2025 as its construction start, and that month it asked for a traffic light at its Route 11 entrance. The river basin commission raised Amazon's water approval to 0.129 million gallons a day on March 12, 2026, and the state took the project off its Fast Track list in August 2026.
Co-located behind-the-meter arrangement triggers cost-shift to ratepayers; flagship FERC ER24-2172 case.
FERCThe Susquehanna River Basin Commission approved up to 129,000 gallons a day of consumptive use, after Amazon asked for 277,000 and had started construction in 2024 with a 60,000 gallon limit for three buildings. Amazon says 129,000 gallons is peak use on the hottest days. Three Mile Island Alert's Eric Epstein said Amazon low-balled its water requests and kept its full build-out needs confidential.
Altoona MirrorFERC rejected the plan to raise the co-located Amazon load from 300 to 480 megawatts, citing possible increases in power bills for the public and risks to grid reliability. Talen and Amazon then moved to a grid-connected deal for up to 1,920 megawatts.
Data Center DynamicsAmazon is seeking a DEP permit to discharge used cooling water into a stretch of the Susquehanna classified as a warm water fishery. Critics worry about water temperature and lower dissolved oxygen during low flows, and the Fish and Boat Commission said it had not reviewed any discharge permit for the site.
Outdoor NewsAWS asked for a traffic light where its campus entrance meets Route 11, and the Salem Township police chief supported it, citing triaxle truck traffic from construction.
Press EnterpriseAt the 2024 rezoning hearing, residents worried that changing about 1,600 acres from agricultural to industrial zoning would devalue their land, and some said Amazon had approached them with offers to buy.
PhillyVoiceAmazon says that when the campus is fully built, it expects 20 data centers supporting about 1,000 permanent jobs.
Amazon Innovation Campuses in PennsylvaniaLeaders: Eric Epstein (quoted for the group)
Tactics: Public criticism and comments on Susquehanna River Basin Commission water approvals
Criticized Amazon's Salem Township water requests in March 2026.
AWS-Talen ISA amendment 300 to 480 MW; rejected 2-1 Nov 1 2024; rehearing denied Apr 16 2025.
PJM, Talen, AWS · Rehearing denied; appealedTalen appeal of FERC ISA rejection.
Susquehanna Nuclear, L.L.C. (Talen Energy subsidiary) v. FERC · Dismissed by Talen, January 2026. Talen voluntarily dismissed the appeal in January 2026 after FERC approved restoring 148 megawatts of capacity interconnection rights at Susquehanna, according to its 2025 annual report.Talen's subsidiary challenges FERC's 2024 orders rejecting the amended interconnection service agreement that would have raised the co-located Amazon load at Susquehanna from 300 to 480 megawatts.
Susquehanna Nuclear, L.L.C. v. Federal Energy Regulatory Commission; intervenors Vistra, American Electric Power, Exelon and PPL Electric Utilities · Dismissed by Talen, January 2026. Talen voluntarily dismissed the appeal in January 2026 after FERC approved restoring 148 megawatts of capacity interconnection rights at Susquehanna, according to its 2025 annual report.Modification raising consumptive water use at the PHL100 Data Center Campus in Salem Township to up to 0.129 million gallons a day (30-day average). Amazon had asked for 0.277.
Amazon Data Services, Inc. · ApprovedIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →