- Developer
- Aligned Data Centers, a Plano, Texas-based developer and operator that BlackRock acquired in an October 2025 deal valued at $40 billion, according to the Post-Gazette. Aligned.AI PA Owner, LLC bought the land from Shippingport Industrial Park, LLC, the Frontier Group of Companies entity that owns the former Bruce Mansfield plant. Kimley-Horn is the site engineer, and Holder Construction and Kokosing are building the campus. Frontier is separately converting the coal plant to natural gas. The conversion was announced at the July 2025 Pennsylvania Energy and Innovation Summit as a $3.2 billion investment, according to Sen. McCormick's summit fact sheet, and Frontier now puts its direct investment in the generating project at about $1.6 billion, according to Data Center Frontier.
- Tenant
- No customer has been named. The Post-Gazette reported in February 2026 that Aligned was still working to secure one, and the company's September 2026 groundbreaking announcement didn't name a tenant.
- Current stage
- Under construction. Borough council approved the conditional use on Jan. 28 and March 31, 2026, the Phase 1 grading permit on Jan. 28, and the Phase 2 land development plan on Sept. 21, 2026, contingent on outstanding outside permits. Aligned closed on the land on July 27, 2026, and held a groundbreaking on Sept. 10, 2026. At the Sept. 21 work session, the borough engineer and Aligned's engineer said state stream and wetland permits, Phase 2 erosion control approval, sewage planning approval and a PennDOT permit were still being finished.
- Decision body
- Shippingport Borough Council handles the conditional use, grading and land development approvals, and the Shippingport Zoning Hearing Board hears zoning appeals. The Pennsylvania Department of Environmental Protection issues state permits, the Beaver County Conservation District reviews erosion controls, the U.S. Army Corps of Engineers reviews stream and wetland impacts, and PennDOT handles highway access. Beaver County's solicitor has said the county has no vote on data center approvals.
- Top issues
- Round-the-clock construction noise including rock crushing, operating noise limits near homes, clearing most of the site's woods and regrading steep slopes, construction traffic on Ferry Hill Road and near a school bus stop at Gate 17, water supply and fire protection, emissions from on-site gas generation, and how late residents learned about the project.
- Key opponents
- No organized opposition group has been reported. Residents asked about property values, landslides and ground stability above old mines, and borough solicitor Rich Urick said in December 2025 that the project should slow down to allow proper review and criticized Frontier's lack of transparency.
- Key supporters
- Beaver County Commissioners chairman Dan Camp said in May 2026 that the commissioners support the Shippingport data center. Shippingport Mayor John Erickson praised the project at the groundbreaking, and Aligned says it supports Gov. Josh Shapiro's GRID standards and has signed the Ratepayer Protection Pledge.
How we got here
Bruce Mansfield stopped burning coal in 2019, and Frontier Group of Companies bought the plant in 2022 and renamed the area the Shippingport Industrial Park. Shippingport held a hearing on March 4, 2025, on Ordinance 240, which made data centers a conditional use with standards on noise, water and power planning, and the ordinance passed that March. On July 15, 2025, Frontier announced a $3.2 billion plan to convert the coal plant to natural gas, which it said would create more than 300 permanent jobs and 15,000 construction jobs. Council rezoned parts of the industrial park from residential to general industrial in July 2025 and again on Nov. 4, 2025. Aligned and Kimley-Horn presented early plans on Dec. 9, 2025, when company representatives apologized for seismic testing letters sent to residents without notice. On Jan. 28, 2026, council unanimously approved the Phase 1 grading permit and the conditional use with modifications for a 65-foot height, 24-hour construction, clearing of 75 percent of the woodlands and a 65 decibel noise cap at the nearest home. On March 31, 2026, council approved round-the-clock rock crushing 3 to 2 and approved the conditional use subject to a written decision. A Zoning Hearing Board hearing on an application from Shippingport Industrial Park, LLC set for July 13, 2026, was cancelled when the applicant withdrew. Aligned closed on 650.89 acres for $223,150,865.38 on July 27, 2026, DEP scheduled a public information session in Shippingport for Aug. 18, and Aligned broke ground on Sept. 10, 2026. Council approved the Phase 2 land development plan on Sept. 21, 2026.