Project Green Mountain (Stavola Quarry, Archbald)

Archbald Borough, Lackawanna County

Green Mountain 6 LLC wants to build seven two-story data centers with 196 diesel backup generators on about 271 acres of the old Stavola quarry east of the Casey Highway. Borough council's conditional use hearings are still going, and the Planning Commission has already given the plans preliminary approval.

ContestedTBD/UndisclosedBrownfieldNEPA
At a glance

The project by the numbers

StatusUnder Review
Building area1,930,000 sq ft
Site271 acres
Water (max)0.014 MGD
Permanent jobs, as claimed350
First announced2026-01

Seven-building data center campus proposed at Archbald's old Stavola quarry

The number that mattersA developer's engineer testified that each of the seven buildings would have 28 diesel generators holding about 10,000 gallons of fuel apiece, which 28/22 News totaled at 1,960,000 gallons of diesel on a site zoned for coal mining.
Developer
Green Mountain 6 LLC is the applicant, and Stop Archbald Data Centers identifies the developer as Western Hospitality Partners, which WVIA says also owned the Project Gravity land through Archbald 25 Developer LLC. Attorneys Jeffrey Wilhelm of Reed Smith in Pittsburgh and Raymond Rinaldi of Rinaldi & Poveromo represent the project, Kimley-Horn is the engineer, Acentech prepared the sound study, and a consultant from FTI Consulting testified about economic benefits.
Tenant
No tenant or end user has been named.
Current stage
Borough council has held conditional use hearings on March 19, May 11 and June 18, 2026, and the borough's hearing page lists a fourth on September 30, 2026, continued to a fifth hearing on November 12, 2026. The Planning Commission unanimously granted preliminary land development approval on May 6, 2026, and the plan has been listed with no update at commission meetings since, including in September. Final land development approval, council's conditional use decision and state permits are all still needed, and DEP's tracker showed no permit applications as of our last check.
Decision body
Archbald Borough Council decides the conditional use application under the borough's November 2025 data center overlay ordinance. The Planning Commission reviews the land development plans, and council moved in April 2026 to make that commission advisory. DEP would review stormwater, stream crossing and air permits.
Top issues
196 diesel backup generators and close to 2 million gallons of fuel stored on old mine land; noise from 280 rooftop chillers and a sound study that predicts levels right at the legal limit; air quality and cumulative emissions; traffic, with no traffic impact study finished as of May 2026; a new PPL substation and switchyard next to the quarry; loss of wooded hills near Aylesworth Park; part of the site zoned resource conservation
Key opponents
Stop Archbald Data Centers, whose co-founder Tamara Misewicz-Healey has cross-examined the developer's witnesses at the hearings; the Valley View School District, which council granted party status in June 2026 over the applicant's objection.
Key supporters
No organized support has been reported. The developer's economic consultant from FTI Consulting testified about jobs and tax benefits, and the company has offered the borough a one-time $1.25 million payment.

How we got here

Archbald Borough Council created the data center overlay district on November 24, 2025, making data centers a conditional use. Green Mountain 6 LLC filed its conditional use application on January 23, 2026, which the borough logged as received January 26, and attorney Jeffrey Wilhelm presented it to the Planning Commission on February 4. The developer submitted land development plans on February 25, and on March 4 the Planning Commission sent its advisory comments on the conditional use to council. The first conditional use hearing on March 19, 2026 drew a packed auditorium, where the developer's engineer described seven two-story buildings with 28 diesel generators each. PPL announced on March 25 a new substation and switchyard on either side of Salem Road near the quarry. The Planning Commission granted preliminary land development approval on May 6, the second hearing on May 11 covered air permits and traffic, and the third on June 18 focused on the sound study and gave the Valley View School District party status. A fourth hearing set for August 6 was later listed by the borough for September 30, 2026.

Update, October 26, 2026. As of October 26, 2026, Archbald's conditional use page lists the fifth Project Green Mountain hearing for November 12, 2026 at 5 p.m. in the Valley View High School auditorium, continued from the September 30, 2026 hearing.

What is at stake

Impacts raised and open questions

Air quality

High

The campus would have 196 diesel backup generators, and at the May 11 hearing the applicant's air permitting expert couldn't answer council's questions about cumulative air quality impacts or a facility-wide emissions inventory, according to Stop Archbald Data Centers' hearing summary.

Stop Archbald Data Centers

Public safety

High

Each generator would hold about 10,000 gallons of fuel, close to 2 million gallons on a roughly 270-acre site zoned for coal mining, where residents worry about abandoned mine workings, 28/22 News reported.

WBRE/WYOU 28/22 News

Noise and vibration

Medium

The applicant's acoustic consultant acknowledged that predicted sound at two homes equals the 45-decibel nighttime limit with no margin, and that one monitoring microphone was mounted against a tree and its reading lowered by 2 decibels; objectors say the study measured at the wrong property lines.

Stop Archbald Data Centers

Traffic

Medium

At the May 11, 2026 hearing the traffic engineer confirmed no traffic impact assessment had been completed and counts were taken on a single day, according to Stop Archbald Data Centers' hearing summary.

Stop Archbald Data Centers

Energy costs and the grid

Medium

PPL plans a new 500/230 kV Archbald Mountain Substation and Winton Switchyard on either side of Salem Road near the Stavola quarry, with a 250-foot-wide right-of-way for new 230 kV lines; Green Mountain's application mentions a PPL-owned switchyard.

WVIA News

Jobs and tax claims

Medium

The developer says the campus would create about 350 permanent jobs and about 1,500 temporary construction jobs and would make a one-time $1.25 million payment to the borough.

WBRE/WYOU 28/22 News

Water

Low

Pennsylvania American Water's serviceability letter acknowledges a requested average demand of up to 14,000 gallons a day.

Stop Archbald Data Centers
Community response

Who is organizing against it

Stop Archbald Data Centers

Archbald Borough and neighboring Mid Valley communities

Leaders: Tamara Misewicz-Healey (co-founder)

Tactics: Members in yellow shirts pack the conditional use hearings, hand out signs and circulate petitions, and the co-founder cross-examines the developer's witnesses; the group also posts hearing summaries, sells yard signs and shirts to fund legal costs and helped lead an October 2026 bus tour past the proposed sites.

The group's Green Mountain page tracks hearing dates, key documents and its summaries of each hearing. It also brought the court appeal of the overlay ordinance under which Green Mountain applied.

Website · Facebook · Donate

Timeline

How it has unfolded

  • 2025-11-24Council enacts Ordinance No. 04-2025, creating the data center overlay district that makes data centers a conditional use. Stop Archbald Data Centers
  • 2026-01-23Green Mountain 6 LLC files its conditional use application for a data center campus at the Stavola quarry. Stop Archbald Data Centers
  • 2026-02-04Attorney Jeffrey Wilhelm presents the conditional use application to the Planning Commission and corrects the site's zoning listing. Archbald Borough
  • 2026-02-25The developer submits a land development plan package to the borough. Stop Archbald Data Centers
  • 2026-03-04The Planning Commission votes to send its advisory comments on the conditional use application to council. Archbald Borough
  • 2026-03-19First conditional use hearing draws a packed Valley View High School auditorium. FOX56 (WOLF)
  • 2026-03-25PPL announces a new substation and switchyard on either side of Salem Road near the quarry. WVIA News
  • 2026-05-06The Planning Commission unanimously grants preliminary land development approval. Archbald Borough
  • 2026-05-11Second hearing covers air permits, fuel storage and traffic, and no decision is made. WBRE/WYOU 28/22 News
  • 2026-06-18Third hearing questions the sound study and grants the Valley View School District party status. Stop Archbald Data Centers
  • 2026-09-30The borough's schedule lists the fourth conditional use hearing for this date. Archbald Borough
Legal record

Filings and legal actions

  • 2025
    Land use appeal of the data center overlay ordinance Lackawanna County Court of Common Pleas · 2025-CV-10325

    Residents argue Ordinance No. 04-2025, the overlay ordinance under which Green Mountain applied, was improperly developed and enacted. The case doesn't name Green Mountain 6 LLC, but its outcome could affect the zoning the project relies on.

    Archbald residents backed by Stop Archbald Data Centers (appellants); Archbald Borough; Archbald I LLC, which moved to dismiss · Active; Archbald I LLC's motion to dismiss for lack of standing was denied on July 15, 2026
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →