- Developer
- Prime Data Centers, led by CEO Nicholas Laag, is the developer. UGI Energy Services, a subsidiary of UGI Corporation led by president Joseph Hartz, is selling the property and plans to build the gas pipeline and supply facilities, an investment UGI says could exceed $100 million. UGI keeps about 15 billion cubic feet of underground gas storage capacity and the oil and gas rights tied to the property.
- Tenant
- No end user has been named. The companies describe the site as supporting future hyperscale data center operations for AI and high-performance computing.
- Current stage
- Announced on May 6, 2026 as a purchase and sale agreement. As of October 22, 2026, no location, municipal application or state permit filing tied to the project has been made public, and UGI gave no update in its August 6 quarterly results.
- Decision body
- Not yet known. The site hasn't been disclosed, so the township or county that would handle zoning and land development review can't be identified yet.
- Top issues
- Secrecy about the location and the end user, emissions from a large on-site gas-fired power plant, construction of a new gas pipeline, and whether rural northern tier townships have zoning rules ready for a project of this size.
- Key opponents
- No organized opposition group has been reported. Former state Department of Environmental Protection Secretary David Hess told WPSU that little is known about the project and urged UGI and the developer to be "very transparent and upfront with the communities" about their plans.
- Key supporters
- U.S. Senator Dave McCormick endorsed the project in the announcement, saying this kind of infrastructure is necessary for energy security and will create good jobs. UGI Energy Services president Joseph Hartz and Prime CEO Nicholas Laag spoke for the project in the announcement.
How we got here
UGI Energy Services and Prime Data Centers announced a purchase and sale agreement on May 6, 2026, under which UGI sells Prime property for an on-site, gas-fueled electric generation facility and Prime builds a data center campus. UGI keeps about 15 billion cubic feet of underground storage capacity and the associated oil and gas rights, and plans more than $100 million in pipeline and supply infrastructure. U.S. Senator Dave McCormick endorsed the deal. UGI described the partnership in its May 7 SEC filing and earnings call, where CEO Bob Flexon said more than 75 nondisclosure agreements tied to possible projects had been signed. On May 20 a UGI spokesman told WPSU he couldn't provide the location or timeline. UGI's August 6 third quarter results and call didn't add details.