- Developer
- Carlisle Development Partners, LLC, a joint venture of Pennsylvania Data Center Partners (CEO Igal Feibush) and PowerHouse Data Centers, part of American Real Estate Partners (CEO Doug Fleit). Harrisburg attorney Charles Courtney represents the developer before the township, and Livic Civil Engineering is the project engineer.
- Tenant
- No tenant has been named. The developers bought the land in 2025 and say the campus will serve demand for cloud and AI computing, according to PennLive reporting carried by WHP 580.
- Current stage
- Site work, blasting and PPL substation construction are underway. On September 2, 2026 the supervisors gave final approval to Phase 1-B, the first six data center buildings, and preliminary approval to Phase 3. Final plans for Phase 1-C (a construction laydown area) and Phase 2 are still under township review, and the residents' appeals are pending in county court and at the state Environmental Hearing Board.
- Decision body
- Middlesex Township Board of Supervisors, which approves the land development plans. Residents' appeals are before Judge Matthew Smith of the Cumberland County Court of Common Pleas and the Pennsylvania Environmental Hearing Board, and the state Department of Environmental Protection still has air quality and storage tank permits to issue.
- Top issues
- Noise from blasting, site work and future cooling equipment; more than 500 diesel backup generators; the 400,000 gallon a day water reservation; the view from the Appalachian Trail; buildings up to 75 feet tall; and how fast the overlay zoning moved from request to law before most residents knew about the project.
- Key opponents
- Stop PAX-1, a residents' group co-led by Kyle Gerber that has filed two county court appeals and an Environmental Hearing Board appeal through attorney Nathan Wolf, and Stewards of Cumberland County, a countywide group behind padatacenters.org. Hundreds of residents have packed township meetings since August 2026. The Appalachian Trail Conservancy has raised concerns about views from the trail.
- Key supporters
- The developers and the Middlesex Township supervisors, who adopted the overlay zoning in 2025 and approved the plans in 2026. Chairman Donald Geistwhite Jr. and Vice Chairman Phil Neiderer cast the two votes for final approval on September 2, 2026, and said they felt the law left them no choice. The township negotiated a $14 million community benefits agreement with the developer.
How we got here
The overlay amendment was submitted to Cumberland County in April 2025 and adopted 3-0 on May 30, 2025 as Ordinance 3-2025. Sen. Dave McCormick announced the $15 billion, three-campus project at his July 15, 2025 energy summit, and PennLive reported a $44 million land purchase later that month. The Planning Commission recommended the subdivision plan in December 2025 and supervisors approved it in early January 2026. In January 2026 the State Historic Preservation Office found the project would harm the Appalachian Trail viewshed. In February 2026 the developer signed a $14.1 million water and sewer deal reserving up to 400,000 gallons a day, and on March 4 supervisors approved the PPL substation plan. Blasting and site work began that spring. Residents filed a spot-zoning challenge in May 2026. An overflow crowd on August 5 and a medical emergency on August 19 forced the final vote to be postponed, and a supervisor resigned in late August. On September 2, 2026 the two remaining supervisors approved the community benefits agreement, the Phase 1-B final plan and the Phase 3 preliminary plan. Judge Matthew Smith let construction continue on September 22 and, on October 5, ruled the automatic stay doesn't apply but set a November 13 hearing.