Energy costs and the grid
HighThe ordinance bars on-site primary power generation and requires the developer to pay for supply lines and substations and buy power from Olyphant Borough Electric.
Olyphant BoroughOlyphant Borough, Lackawanna County
A zoning ordinance in Olyphant Borough, Lackawanna County, that allows data centers only by conditional use in the CM-2 industrial and commercial district, which includes the 548-acre Triboro Industrial Park land at the Jessup border.
Dec. 30, 2025: planning commission recommends the conditional-use amendment. March 31, 2026: public hearing. April 14, 2026: council votes 4-3 to adopt, a re-vote fails 3-4, and council declares a 180-day curative amendment. April 2026: a nine-building data center zoning application is filed and later pulled. June 9, 2026: council approves a settlement with the Tri-Boro Commerce Park and the solicitor says the amendment stands. Sept. 2026: the borough's preliminary objections are filed in a separate Ercor lawsuit.
The ordinance bars on-site primary power generation and requires the developer to pay for supply lines and substations and buy power from Olyphant Borough Electric.
Olyphant BoroughPPL's map for its data center transmission project appears to show a data center customer on the Ercor Triboro land at the Jessup and Olyphant border; PPL said that customer will pay for the lines into its facility.
WVIA NewsThe ordinance requires a licensed acoustical engineer's sound study before conditional use approval and an as-built study within six months of opening, with a remediation plan due within 30 days if the facility exceeds the limits.
Olyphant BoroughBorough officials said at a June 29, 2026 planning commission meeting that the noise limits that apply are 60 decibels in the daytime and 50 at night.
Olyphant BoroughData center buildings may rise to 80 feet in the CM-2 district, with 200-foot setbacks where a site adjoins homes or a residential zone and a 50-foot woodland buffer along all property lines.
Olyphant BoroughProjects must file a water feasibility study, show no harm to nearby wells, and get Susquehanna River Basin Commission review for withdrawals of 100,000 gallons a day or consumptive use of 20,000 gallons a day.
Olyphant BoroughTactics: Gave council a four-page list of recommended changes to the data center ordinance; public comment
Dispute over whether council's April 14, 2026 vote adopted the data center zoning amendment. After the settlement, the borough treats Ordinance No. 3 of 2026 as adopted.
Tri-Boro Commerce Park v. Olyphant Borough · Settled; council approved a stipulation of settlement June 9, 2026Separate suit by Ercor, the Triboro landowner. The solicitor said it does not contest the zoning amendment but that the ordinance can't be changed while it is pending.
Ercor v. Olyphant Borough · Pending; borough filed preliminary objections (reported Sept. 8, 2026)In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.