All Pennsylvania projects
Contested

Nescopeck / Valley View Wood Data Center

Nescopeck Township, Luzerne County

A 'Nescopeck / Valley View Wood' data center appears on DEP's tracker with no permit applications, months after township supervisors limited where data centers can go and an attorney for a data center warned of a legal fight.

ContestedTBD/UndisclosedUnknownNEPA
At a glance

The project by the numbers

StatusProposed
First announced2025-12

DEP lists an early-stage data center in Nescopeck Township with no developer named

The number that mattersThe Press Enterprise, Dec. 12, 2025: 'Supervisors here passed an ordinance Thursday to limit where data centers can be built in the township,' under the subhead 'Nescopeck Township supervisors warned of legal fight.'
Developer
Not publicly identified. DEP's project title names 'Valley View Wood,' but we found no company or property by that name in news coverage or public records. The Press Enterprise reported that an attorney for a data center warned Nescopeck Township supervisors of a legal fight in December 2025 without naming the client in the portion we could read.
Tenant
No tenant named.
Current stage
DEP lists the project as 'Proposed (No Applications Received)' as of October 22, 2026, with stormwater, waterway encroachment, clean water, air quality and storage tank permits all marked not yet submitted. Township supervisors passed an ordinance limiting where data centers can be built on Dec. 11, 2025, according to the Press Enterprise.
Decision body
Nescopeck Township Board of Supervisors (zoning); Pennsylvania DEP (permits)
Top issues
Unknown developer and site; the township's limits on data center locations and a threatened legal challenge; PPL's planned Nescopeck Switchyard and 500-kilovolt-capable Sugarloaf line; Susquehanna River withdrawals and Pennsylvania American Water supply; spillover from three data center campuses across the river in Salem Township
Key opponents
No organized opposition focused on this project has been reported. The Alliance to Stop the Line, which opposes PPL's 500-kilovolt Sugarloaf line, lists Nescopeck among the communities in its petition. State Rep. Jamie Walsh, R-Ross Township, has named Nescopeck among the townships he says are being targeted for data centers.
Key supporters
None publicly identified.

How we got here

On Dec. 11, 2025, Nescopeck Township supervisors passed an ordinance limiting where data centers can be built, and the Press Enterprise reported that an attorney for a data center warned of a legal fight. In February 2026, WVIA reported PPL's plan for a new Nescopeck Switchyard in the township as the starting point of its Sugarloaf transmission line to Hazle Township, and on Feb. 12 State Rep. Jamie Walsh told the Luzerne County Planning Commission he had confirmed data center applications or land purchase offers in Nescopeck and six other townships. In neighboring Nescopeck Borough, more than 50 residents objected to a draft data center overlay on May 18, 2026, and on June 15 the borough council voted to acknowledge that its zoning doesn't address data centers, starting a 180-day window to write rules. DEP's permit tracker lists the township project as proposed with no applications as of October 22, 2026.

What is at stake

Impacts raised and open questions

Energy costs and the grid

Medium

PPL plans a new Nescopeck Switchyard in the township, near its existing Sunbury-Susquehanna lines, as one end of a 12-mile line through Nescopeck, Black Creek, Sugarloaf and Hazle townships that's built for 500 kilovolts and would start at 230 kilovolts. No public record ties the switchyard to this data center.

WVIA News

Water

Medium

At a May 2026 meeting in neighboring Nescopeck Borough, residents warned about Susquehanna River withdrawals during drought and whether Pennsylvania American Water's system can serve more data centers on top of Amazon's in Salem Township. The project's own water use is unknown.

FOX56 (WOLF)
Community response

Who is organizing against it

Alliance to Stop the Line

Sugarloaf Valley residents (Nescopeck, Sugarloaf and Prospect Park) opposing PPL's 500-kilovolt Sugarloaf line · 327 signatures

Leaders: John Zola, founder

Tactics: Petition, testimony at township meetings and Public Utility Commission hearings

The petition form shows 327 offline signatures; it targets the PPL line, which would start at a planned switchyard in Nescopeck Township.

Petition

Timeline

How it has unfolded

  • 2025-12-11Supervisors pass an ordinance limiting where data centers can be built, and an attorney for a data center warns of a legal fight. Press Enterprise
  • 2026-02-05WVIA reports PPL's plan for a new Nescopeck Switchyard in Nescopeck Township at the end of its 12-mile Sugarloaf transmission line. WVIA News
  • 2026-02-12Walsh tells the Luzerne County Planning Commission he has confirmed data center applications or land purchase offers in seven townships, including Nescopeck. Times Leader
  • 2026-05-18In the neighboring borough, more than 50 residents push back on a draft data center overlay district. FOX56 (WOLF)
  • 2026-06-15The borough council votes to acknowledge its zoning doesn't address data centers, opening a 180-day window to write rules. 28/22 News (WBRE/WYOU)
  • 2026-10-22DEP's tracker lists the Nescopeck Township project as proposed with all permits not yet submitted. Pennsylvania Department of Environmental Protection
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →