Natalie Transmission Project (PPL Electric Utilities, Mount Carmel area)
Mount Carmel Township, Northumberland County
PPL Electric Utilities is planning a new Natalie 500/230 kV substation and about 16 miles of new lines in Northumberland and Columbia counties to serve an unnamed data center customer near Mount Carmel, and Mount Carmel Township's supervisors voted 3-0 on October 21, 2026 to oppose it.
The project by the numbers
PPL plans a Natalie substation and 16 miles of high-voltage lines for a data center customer
- Developer
- PPL Electric Utilities Corporation, the Allentown-based utility subsidiary of PPL Corporation
- Tenant
- PPL hasn't named the customer. PJM slides describe a customer that asked for a 230 kV source near Mt Carmel, with load growing from 290 MW in 2028 to about 2,000 MW by 2033.
- Current stage
- PPL presented the customer's request to PJM on April 7, 2026 and its Natalie substation solution on September 8, 2026, and it told Mount Carmel Township about the project by email on October 21, 2026, hours before the supervisors met. The project still needs Pennsylvania Public Utility Commission approval, and we didn't find a PUC application. Mount Carmel Township's supervisors voted 3-0 on October 21, 2026 to oppose it, and PPL has scheduled a public open house in Elysburg for early November.
- Decision body
- Pennsylvania Public Utility Commission (siting approval), with planning review at PJM Interconnection's Transmission Expansion Advisory Committee
- Top issues
- Easements and possible eminent domain on private land, monopoles up to about 210 feet tall, scenic views and natural resources, how costs would be split between the data center customer and other electric customers, and the township's complaint about a lack of disclosure from PPL.
- Key opponents
- Mount Carmel Township Board of Supervisors, which adopted a resolution opposing the project on October 21, 2026
- Key supporters
- None named in the public record.
How we got here
April 7, 2026: PPL presents need PPL-2026-0029 to PJM, a customer request for a 230 kV source near Mt Carmel growing to about 2,000 MW by 2033. September 8, 2026: PPL presents the Natalie 500-230 kV Substation solution to PJM, estimated at $408 million with a projected in-service date of December 30, 2029. October 21, 2026: PPL emails Mount Carmel Township about the project around 2 p.m., hours before the supervisors meet. October 21, 2026: Supervisors vote 3-0 for a resolution opposing it. October 23, 2026: The News-Item reports the details of PPL's fact sheet and the open house.
How it has unfolded
- 2026-04-07PPL tells PJM a customer has asked for a 230 kV source near Mt Carmel for a facility whose load would grow from 290 MW in 2028 to about 2,000 MW in 2033, with service requested by June 2028. PJM Interconnection
- 2026-09-08PPL presents its solution to PJM, a new Natalie 500-230 kV substation tied into existing 230 kV and 500 kV lines, estimated at $408 million with a projected in-service date of December 30, 2029. PJM Interconnection
- 2026-10-21PPL emails Mount Carmel Township about the Natalie Transmission Project around 2 p.m. on the day of the supervisors' meeting, according to Chairman Aaron Domanski. The News-Item
- 2026-10-21Supervisors vote 3-0 for a resolution opposing the project and asking PPL for details on easements and costs and for a public meeting in the township. The News-Item
- 2026-10-23The News-Item reports PPL's fact sheet on about 16 miles of new 230 kV and 500 kV lines and a substation, with construction planned from spring 2028 to early 2031. The News-Item
Filings and legal actions
-
2026-04-07
PJM supplemental project need and solution
Natalie 500-230 kV Substation to serve a customer's request for a 230 kV source near Mt Carmel, estimated at $408 million
PPL Electric Utilities; unnamed customer · Need presented April 7, 2026 and solution presented September 8, 2026; not in PPL's posted 2026 local plan as of September 17, 2026
Coverage of this project
- 2026-10-23 The News-ItemPPL proposes 16-mile transmission project to serve data center in Mount Carmel areaLays out the line lengths, tower heights, schedule and open house, and reports the township's 3-0 vote to oppose the project.
Sources
Know your rights
In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Take action
Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.