Blue Creek Investments submitted preliminary land development plans for two data centers totaling about 1.22 million square feet in Mount Carmel Township on October 9, 2026, but the township found them incomplete and didn't accept them for filing.
The project by the numbers
Blue Creek Investments files plans for two data centers in Mount Carmel Township
- Developer
- Blue Creek Investments, with plans prepared by Kimley-Horn & Associates Inc. The public records we found don't say who owns or runs Blue Creek Investments or where it's based.
- Tenant
- No tenant or end user has been named.
- Current stage
- Blue Creek's two preliminary land development plans were submitted on October 9, 2026, and the township found them administratively incomplete and didn't accept them for filing. The township's new data center ordinance, adopted October 21, 2026, allows data centers as conditional uses in the I-1A industrial and S-2 special coal land reclamation districts, and no data center has received conditional use approval yet. The Northumberland County Planning Commission lists both plans for local review on its October 27, 2026 agenda. We didn't find any township hearing scheduled on Blue Creek's plans as of October 26.
- Decision body
- Mount Carmel Township Board of Supervisors (land development and conditional use), with a review by the Northumberland County Planning Commission
- Top issues
- In the township's data center debate, residents and CRANE have raised water use, noise including low-frequency sound, distance from homes, bonds for cleanup and decommissioning, compliance reporting and inspections, and who pays for new power lines.
- Key opponents
- CRANE, a local group that has pushed the supervisors for a stronger data center ordinance (contact email CRANEORG2026@gmail.com). We didn't find a public position from any group or official on Blue Creek's plans specifically.
- Key supporters
- None named in the public record.
How we got here
May 18, 2026: The News-Item reports that Blue Creek and FIT Energy, two of four companies that may propose data centers, sent comments on the township's draft ordinance, and the supervisors vote 3-0 for a 180-day moratorium. October 9, 2026: Blue Creek submits preliminary land development plans for the North Data Center (604,500 square feet) and the South Data Center (616,500 square feet), with Kimley-Horn & Associates Inc. as consultant. October 21, 2026: The News-Item reports the plans were found administratively incomplete and weren't accepted for filing, and the supervisors adopt the data center zoning ordinance. October 27, 2026: Both plans are on the Northumberland County Planning Commission agenda for local review.
Who is organizing against it
How it has unfolded
- 2026-05-18The News-Item reports that Blue Creek and FIT Energy are two of four companies that may propose data centers in the township. The News-Item
- 2026-05-18Supervisors Aaron Domanski, Gary Namet and Joseph Lapotsky vote 3-0 for a 180-day moratorium on data center proposals while they rework the zoning ordinance. The News-Item
- 2026-10-09Blue Creek submits a preliminary land development plan for the Mount Carmel Township North Data Center, 604,500 square feet, with Kimley-Horn & Associates Inc. as consultant. Northumberland County
- 2026-10-09Blue Creek submits a preliminary land development plan for the Mount Carmel Township South Data Center, 616,500 square feet, with Kimley-Horn & Associates Inc. as consultant. Northumberland County
- 2026-10-21The News-Item reports the township found both Blue Creek plans administratively incomplete and didn't accept them for filing. The News-Item
- 2026-10-21Supervisors unanimously adopt a data center zoning ordinance allowing data centers as conditional uses in the I-1A industrial and S-2 special coal land reclamation districts, ending the moratorium ahead of its November 13 expiration. The News-Item
Filings and legal actions
-
2026-10-09
Preliminary land development plan
Mount Carmel Township North Data Center, 604,500 square feet
Blue Creek Investments (applicant); Kimley-Horn & Associates Inc. (consultant) · Found administratively incomplete and not accepted for filing by the township; on the county planning commission's October 27, 2026 agenda for local review -
2026-10-09
Preliminary land development plan
Mount Carmel Township South Data Center, 616,500 square feet
Blue Creek Investments (applicant); Kimley-Horn & Associates Inc. (consultant) · Found administratively incomplete and not accepted for filing by the township; on the county planning commission's October 27, 2026 agenda for local review
Coverage of this project
- 2026-10-23 The News-ItemPPL proposes 16-mile transmission project to serve data center in Mount Carmel areaCovers PPL's plan for lines and a substation to serve an unnamed data center customer in the township, which PPL hasn't tied to any developer.
- 2026-10-21 The News-ItemMount Carmel Township approves data center ordinance as residents seek additional safeguardsReports the township adopted its data center ordinance and that Blue Creek's two plans, submitted by Kimley-Horn, were found administratively incomplete.
- 2026-05-18 The News-ItemMount Carmel Township enacts 180-day moratorium on data center proposals to upgrade zoningNames Blue Creek and FIT Energy as two of four companies that may propose data centers and says both commented on the draft ordinance.
Sources
Know your rights
In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Take action
Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →