- Developer
- FIT Energy USA LP, part of Fit Energy, whose CEO is Joel Leonoff. It works locally through the Mount Carmel Township Data Center Team, which includes engineers and environmental consultants. Supervisors say FIT and Blue Creek are two of four companies that may submit proposals. In 2025, Virtual Consonance, led by founder and president Subuhi Khan, said it was studying a data center west of Natalie.
- Tenant
- No tenant or end user has been named.
- Current stage
- On October 21, 2026 the supervisors unanimously adopted a data center zoning ordinance that allows data centers as conditional uses in the I-1A industrial and S-2 Special Coal-Land and Reclamation districts, with a 1,500-foot setback from homes, a 60-foot height limit, noise limits that cover low-frequency sound, required studies, and decommissioning security posted before a certificate of occupancy. No data center has received conditional use approval under the new ordinance. Blue Creek Investments submitted preliminary land development plans for two facilities on October 9, but the township found them administratively incomplete and didn't accept them for filing. Supervisors have asked the solicitor and engineer to draft supplemental amendments and a separate operational compliance ordinance, and they voted 3-0 to oppose PPL's proposed Natalie Transmission Project, about 16 miles of new 230 kV and 500 kV lines and a substation to serve a prospective data center customer. DEP's tracker lists the FIT Energy project as proposed with air, stormwater, encroachment and sewage planning permits not yet submitted.
- Decision body
- Mount Carmel Township Board of Supervisors (Aaron Domanski, Gary Namet and Joseph Lapotsky), after review by the township and Northumberland County planning commissions; Pennsylvania DEP Northcentral Regional Office for permits.
- Top issues
- noise and light pollution; water use for cooling; electricity demand; building on old mine land; how strict the ordinance can be without a legal challenge; decommissioning
- Key opponents
- Coal Region Advocates for a Neighborhood-First Environment (CRANE), a residents' group that drafted its own data center ordinance and met with supervisors; Supervisor Gary Namet, elected in November 2025 after saying he was 100 percent opposed to a data center in the township. A 2025 petition against a data center near Natalie drew nearly 500 signatures.
- Key supporters
- FIT Energy and its Mount Carmel Township Data Center Team, which point to a commissioned study projecting $4.7 million for the township and $13.5 million for the school district from one building. No township official has endorsed a project.
How we got here
In September 2025 Mount Carmel Township held hearings and gave final approval to a data center zoning overlay for a 450-acre tract of coal land west of Natalie. By October 2025 residents had collected nearly 500 signatures on a petition against a data center there. On November 4, 2025 Gary Namet won a supervisor seat after campaigning against a data center. In December 2025 FIT Energy USA LP bought about 561 acres along Route 54 and Woodland Drive from Susquehanna Coal Company. On May 13, 2026 about 400 people attended a hearing on an amended ordinance, and on May 18, 2026 supervisors voted 3-0 for a moratorium of up to 180 days. In June 2026 CRANE submitted its own ordinance. FIT's team held an open house at the Coal Region Sports Complex on July 21, 2026, and on July 28 supervisors said a first draft of new rules would come in August.
Update, October 26, 2026. On October 21, 2026 the Mount Carmel Township supervisors unanimously adopted a data center zoning ordinance that allows data centers as conditional uses in the I-1A and S-2 districts with a 1,500-foot residential setback, directed their solicitor and engineer to draft supplemental amendments, and voted 3-0 to oppose PPL's proposed Natalie Transmission Project. Earlier in the month, preliminary plans Blue Creek Investments submitted on October 9 for two data centers were found administratively incomplete and weren't accepted for filing.