- Developer
- No developer has applied. Township staff, led by Township Manager Ryan Strohecker and Zoning and Planning Director Nate Taggart, drafted the rules using Londonderry Township's ordinance as a template. According to township minutes, the effort grew out of the 2025 review of High Real Estate Group's Kready Farm rezoning, and High has said it has no current plans for a data center.
- Tenant
- There's no project or tenant. No data center application appears in the township's posted agendas or minutes through October 2026.
- Current stage
- Supervisors adopted the rules in Ordinance 2-2025 on November 6, 2025, and updated them with Ordinance 1-2026 on March 2, 2026. They're in effect.
- Decision body
- The Manor Township Board of Supervisors adopts and amends the ordinance. Any data center application would go to the Zoning Hearing Board.
- Top issues
- Noise at neighboring properties, including low-frequency sound, water use, setbacks and building height, fire safety, and what happens when a data center is decommissioned. The rules don't regulate electricity use.
- Key opponents
- No organized opposition to the ordinance has been reported. Nobody spoke at either public hearing. In 2025, residents raised concerns at supervisors' meetings about data center noise, vibration and water use.
- Key supporters
- Supervisors adopted both versions unanimously, and the township planning commission recommended both. Supervisor John Wenzel called it the first ordinance referring to data centers in the county and said other townships were looking to model it.
How we got here
During the June 2, 2025 hearing on High Real Estate Group's Kready Farm rezoning, residents raised data center concerns and Township Manager Ryan Strohecker said the township would refine its data center language within months. Staff presented a draft ordinance on August 4, 2025, built from Pennsylvania and Virginia ordinances with Londonderry Township's as the template. Supervisors sent it to the township and county planning commissions on September 2, 2025, and the township planning commission recommended approval on September 8, 2025. Supervisors adopted it unanimously as part of Ordinance 2-2025 on November 6, 2025, with 250-foot setbacks, a 40-foot height limit and noise and water standards. LNP reports the rules allow data centers on parcels of 30 acres or more in the industrial district with zoning hearing board approval, with noise limits of 65 dB(A) at night and 70 dB(A) by day. After Lancaster County Planning Commission comments arrived, an update was sent for review on January 5, 2026, recommended by the planning commission on January 12, 2026, and adopted unanimously as Ordinance 1-2026 on March 2, 2026. Ephrata and Penn townships have since adopted their own rules, and several other Lancaster County municipalities were drafting them as of June 2026.