Noise and vibration
MediumThe ordinance requires a sound study modeling worst-case conditions, including all backup generators running at once, and bans routine generator testing between 9 p.m. and 7 a.m.
Lowhill TownshipLowhill Township, Lehigh County
Lowhill Township adopted a 23-page data center ordinance on April 6, 2026 that allows the use only by conditional use in one overlay district, and it's now advancing a second ordinance that sorts data centers into tiers by power use.
The township manager presented a draft Digital Infrastructure Facility ordinance on Feb. 12, 2026, and supervisors voted unanimously to send it for review. The Lehigh Valley Planning Commission's committee reviewed it on March 24 alongside Bushkill, Washington and Plainfield townships' proposals. After a public hearing on April 6, supervisors adopted it unanimously as Ordinance 2026-02. At joint meetings on July 9 and Aug. 13 the supervisors and planning commission worked on Ordinance 2026-05, which adds tiers for small distributed computing systems. On Sept. 10 the planning commission recommended it and supervisors authorized advertising it.
The ordinance requires a sound study modeling worst-case conditions, including all backup generators running at once, and bans routine generator testing between 9 p.m. and 7 a.m.
Lowhill TownshipApplicants must file a water feasibility study with a one-mile hydrogeological study and a survey of wells and streams within 1,000 feet, show Delaware River Basin Commission approval for withdrawals of 100,000 gallons a day or more, and use closed-loop cooling to the maximum extent feasible.
Lowhill TownshipData centers and accessory structures must be set back at least 500 feet from any property line, and accessory structures, including rooftop equipment, are capped at 35 feet.
Lowhill TownshipFuel storage must be at least 500 feet from property lines, applicants must file an emergency services coordination plan, and owners must post a bond to remove generators, tanks and batteries if a facility sits idle for 18 months.
Lowhill TownshipApplicants must submit an electrical utility impact study, and any facility designed for 50 megawatts or more is classed as a 'Hyper Digital Infrastructure Facility' that must disclose maximum electrical demand at full build-out.
Lowhill TownshipIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →