Water
HighAt least 750,000 gallons/day; planning commission pushing closed-loop cooling as a condition to force disclosure of cooling architecture.
PoweredByWhoLimerick Township, Montgomery County
Project Laurel would put eight 85-foot data buildings on 192 acres across from the Philadelphia Premium Outlets, drawing roughly 750 megawatts and at least 750,000 gallons of water a day, for an end user nobody has been allowed to name.
Supervisors voted 3-0 on March 5, 2026 to rewrite the data center ordinance. The Planning Commission held a hearing running more than three hours in April, moved to a high school auditorium for crowd size, and recommended denial unless 18 conditions are met. Residents were denied entry to a capacity hearing in May. The Game Commission approved the land swap in June. Conditional use hearings continue monthly through August 2026.
Update, October 13, 2026. Correction: the stricter ordinance (Amend. Ord. No. 438) was adopted July 7, 2026, hours after MCD 7 filed its Phase 1 and Phase 2 applications (CU 26-05 and CU 26-06); the original application is CU 25-04. Sessions followed on August 18, September 8 and October 1, covering landscaping, the fiscal analysis and traffic, and the hearing continues October 27. Limerick Town Center LLC's separate Publicker site application (CU 26-03) is tracked as its own project.
Update, October 22, 2026. At the close of the October 1 session the board added hearing dates of November 24, December 8 and December 22, according to the draft minutes. At the October 6 meeting the solicitor told residents that data centers are a lawful use in Pennsylvania, so the board can't simply say no.
Update, October 22, 2026. PJM planning records show PECO presented a transmission need (PE-2025-007) on November 4, 2025 for a new customer in the Limerick area asking for 100 megawatts in 2029 and 750 megawatts in 2032, and listed that need as withdrawn at PJM's August 4, 2026 planning committee meeting. The slides don't name the customer or give a reason.
Update, October 26, 2026. On September 22, 2026 the Board of Supervisors, which is hearing the MCD 7 application, voted 3-0 to appoint William DeGideo to the seat Linda Irwin left when she resigned on September 1. His term runs through December 31, 2027.
At least 750,000 gallons/day; planning commission pushing closed-loop cooling as a condition to force disclosure of cooling architecture.
PoweredByWhoPECO has reportedly committed roughly 750 megawatts to the campus, the power needed to run about half a million households, in the same PJM zone where capacity costs are already passing through to residential bills.
Data Center DynamicsThe campus would consume at least 750,000 gallons of water per day, more than fills an Olympic swimming pool, in a township where many households are on private wells.
PoweredByWhoIndustry reporting describes 30 to 45 rooftop chillers and a similar number of backup generators per data building across eight buildings. Limerick’s existing data center rules address noise but not vibration, which is why supervisors ordered the ordinance rewritten.
Hoodline / Pottstown MercuryBackup generation at this scale, roughly 30 to 45 units per building across eight buildings, drove supervisors to seek air pollution protections that the existing ordinance does not contain.
PoweredByWhoEight two-story buildings standing 85 feet tall on 192 acres directly across from the Philadelphia Premium Outlets would reshape the skyline of a suburban township.
Data Center DynamicsThe Pennsylvania Game Commission deeded 55 acres of State Game Lands 234 and a 200-foot right of way to a developer entity in a swap residents say nobody voted on, converting public hunting land adjacent to the project site.
PatchFor the Phase 2 application (CU 26-06), the township's summary lists the applicant's estimates of about 36 generators and 42 rooftop chillers for each building of roughly 300,000 sq ft, and about 42 generators and 64 chillers for each building of roughly 400,000 sq ft. Phase 2 covers four buildings of the first size and three of the second, and the separate Phase 1 building adds an on-grade field of about 36 generators.
Limerick TownshipResidents were denied entry to a conditional use hearing that had reached capacity, raising questions about meaningful public participation in a quasi-judicial proceeding.
WFMZResidents living within about two miles describe the pace as very fast and question well water, electric bills and long-term livability.
WFMZThe township's summary of MCD 7's original application (CU 25-04) says the project proposes to vacate and relocate portions of Sanatoga Road and Possum Hollow Road and to relocate a gas transmission line that crosses the site.
Limerick TownshipThe Phase 2 plans include an electrical substation with two power transformers, a control house and switchgear, plus a large utility switching station on the southern part of the site near the existing 500 kV transmission line, according to the township's summary.
Limerick TownshipRecords reviewed by planners reference a community-benefit protection intended to preserve roughly $40 million a year in tax revenue for the township, Montgomery County and the Spring-Ford Area School District; permanent staffing for hyperscale campuses is typically small relative to footprint.
Hoodline / Pottstown MercuryLeaders: Meagan Smolsky and resident organizers; supported by State Rep. Joe Ciresi and State Sen. Katie Muth
Tactics: Monthly turnout at conditional use hearings, coordinated protests in red outside the township administration building, public comment on water, noise and vibration, pressure for a rewritten data center ordinance
A bipartisan coalition of residents that has packed hearings to overflow, forcing meetings into a high school auditorium and, in May 2026, being denied entry when a hearing reached capacity. Works alongside State Rep. Joe Ciresi, who has pursued legislation targeting the nondisclosure agreements shielding projects like this one, and State Sen. Katie Muth.
Conditional use application for eight data buildings totaling roughly 1.4 million sq ft of footprint on 192 acres. The Planning Commission recommended denial unless 18 conditions are met; the elected Board of Supervisors holds the quasi-judicial hearing and makes the formal decision, with a separate land development review to follow any approval.
MCD 7 LLC (attorney Ed Campbell) · Hearings continuing; next session Oct 27, 2026Supervisors directed the solicitor to draft amendments to the data center overlay, whose existing standards address noise, woodland and water service but not water pollution, air pollution or vibration monitoring.
Township solicitor · Adopted July 7, 2026 (Amend. Ord. No. 438); further amendments in drafting55 acres of State Game Lands 234 plus a 200-foot right of way conveyed to Limerick Town Center LLC adjacent to the project area, in exchange for 176 acres in Edgemont Township and 377.2 acres in Bern Township.
Limerick Town Center LLC and the Commonwealth · ApprovedTwo additional conditional use applications on the same property, filed just before Limerick imposed stricter data center regulations, contemplating alternative phasing of the campus. The primary application covers eight two-story buildings totaling just under 2.8 million square feet, three substations of just under half a million square feet, and 80,000 sq ft of support buildings on 191 acres, and proposes to vacate and relocate portions of Sanatoga Road, Possum Hollow Road and a gas transmission line.
MCD 7 LLC / Limerick Town Center LLC (attorney Ed Campbell) · Filed; no hearing dates postedIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →