Gilpin Township in Armstrong County adopted a zoning amendment in April 2026 that allows data centers only as a conditional use in its industrial district, with setbacks, buffers, noise limits and protection against higher electric bills, and it tightened the noise rules in August 2026. No data center has applied.

Ordinance responseN/ASW
At a glance

The project by the numbers

StatusOrdinance Response
First announced2026-04-09

Gilpin Township wrote data center rules before anyone applied, then tightened its noise limits

The number that mattersSince August 2026, Gilpin caps data center sound at 45 decibels at night and on weekends and 55 on weekday days, or 3 decibels over the existing background level if that's lower, and bans any plainly audible hum or droning at neighboring homes.
Developer
No developer has applied, and township records don't tie the rules to any specific proposal. The Gilpin Township Board of Supervisors adopted both ordinances; in February 2026 it authorized its solicitor, Tim Miller, to prepare amendments to the zoning ordinance's tables.
Tenant
There's no project or tenant. This entry tracks the township's zoning rules.
Current stage
Both ordinances are adopted and in effect. Ordinance No. 3 of 2026 took effect on adoption on April 21, 2026, and Ordinance No. 4 of 2026, adopted Aug. 18, 2026, replaced its noise section with stricter limits. Township minutes through September 2026 and the October 2026 agenda don't show any data center application.
Decision body
Gilpin Township Board of Supervisors, which adopts zoning amendments and would decide any data center conditional use application after a hearing.
Top issues
How far data centers must sit from homes, schools and parks (200 feet, plus a 100-foot planted buffer); noise, including low-frequency hum; who pays if a data center raises electric rates; showing enough water without affecting nearby wells or streams, along with wastewater handling and grid capacity; vibration and emergency planning; a possible community benefit agreement; and keeping data centers in the industrial district only.
Key opponents
No organized opposition to the ordinances has been reported, and TribLive reported that no residents commented at the July 21, 2026 hearing on the noise amendment.
Key supporters
The Board of Supervisors adopted Ordinance No. 3 on a motion by Supervisor Charles Stull, seconded by Supervisor Kevin Miller. Stull promoted the rules on Facebook, saying the township's zoning didn't clearly define or address data centers. No outside groups or companies have publicly taken a position on them.

How we got here

Gilpin adopted its current zoning ordinance on Nov. 1, 2023. On Feb. 17, 2026 the supervisors authorized the township solicitor to prepare an ordinance amending tables in the zoning ordinance. By April 9, 2026 the supervisors were advertising a data center ordinance, and Supervisor Charles Stull said on Facebook that the township may also require a community benefit agreement as part of any approval. On April 21, 2026 the board held a public hearing and adopted Ordinance No. 3 of 2026 the same night. It sets a 60-foot height cap, 200-foot setbacks, a 100-foot planted buffer, noise limits of 67 decibels by day and 57 at night, vibration limits, an emergency response plan reviewed by the local fire department, and a requirement that any electric costs to township residents be paid by the project owner. Pittsburgh Magazine noted the new ordinance later that month. On July 21 the supervisors held a hearing on another zoning amendment, where no residents commented, and voted to advertise it. On Aug. 18, 2026 they adopted it as Ordinance No. 4 of 2026, which lowered the noise limits, added low-frequency limits, banned audible hum and required baseline sound testing before approval.

What is at stake

Impacts raised and open questions

Noise and vibration

Medium

Ordinance No. 4 of 2026 limits data center sound, measured at the property line or the boundary nearest a sensitive receptor, to 55 dB(A) and 60 dB(C) on weekdays from 7 a.m. to 8 p.m. and 45 dB(A) and 50 dB(C) at night and on weekends, or 3 decibels over measured background, whichever is lowest, and bans plainly audible low-frequency hum.

Gilpin Township Board of Supervisors

Energy costs and the grid

Medium

Ordinance No. 3 of 2026 requires an interconnection agreement from the electric provider listing known rate impacts, and any costs to residential customers in the township must be paid for by the project owner.

Gilpin Township Board of Supervisors

Visual and light

Low

Ordinance No. 3 of 2026 caps data center buildings at 60 feet including rooftop equipment and requires 200-foot setbacks and a 100-foot planted buffer, 40 to 70 percent evergreens at least 8 feet tall, next to homes, parks, farms and other sensitive uses.

Gilpin Township Board of Supervisors

Public safety

Low

Ordinance No. 3 of 2026 requires an emergency response plan reviewed by the local fire department, covering fire suppression, evacuation and access for emergency equipment, and training for first responders.

Gilpin Township Board of Supervisors

Water

Low

TribLive reports that under the ordinance an applicant must show an adequate water supply that won't affect nearby wells or streams, proper wastewater handling and enough electric grid capacity before a data center can be approved.

TribLive (Valley News Dispatch)
Timeline

How it has unfolded

  • 2026-02-17The supervisors authorized the township solicitor to prepare an ordinance amending tables in the zoning ordinance. Gilpin Township
  • 2026-04-09TribLive reports the supervisors are advertising a proposed data center ordinance, with a public hearing set for April 21, though no data center has been proposed. TribLive (Valley News Dispatch)
  • 2026-04-21The board held a public hearing on a zoning amendment and modified use table setting rules for data centers. Gilpin Township
  • 2026-04-21The board adopted Ordinance No. 3 of 2026, allowing data centers only as a conditional use in the Industrial District with setbacks, buffers, noise and grid cost rules. Gilpin Township Board of Supervisors
  • 2026-07-21The supervisors voted to advertise a new zoning amendment ordinance. Gilpin Township
  • 2026-07-21The supervisors hold a public hearing on a zoning amendment that tightens data center sound standards; no residents comment, and the vote moves to August. TribLive (Valley News Dispatch)
  • 2026-08-18The board adopted Ordinance No. 4 of 2026, replacing the data center noise rules with lower limits, a ban on audible hum and baseline sound testing. Gilpin Township Board of Supervisors
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →