- Developer
- Amazon Data Services, Inc., part of Amazon Web Services, which bought the land in 2025. The site had earlier been planned and permitted for warehouses by Brewster Land Co. of Massachusetts.
- Tenant
- Amazon would own and run the campus for its own use. PPL representatives said Amazon agreed to buy power for ten years and can be curtailed to keep service to the surrounding area.
- Current stage
- Kline Township supervisors unanimously approved the land development plans with conditions on September 30, 2026, adopting the planning commission's nine-page list covering noise, emergency response, infrastructure, water and environmental protections. State, county, zoning and pre-construction conditions still have to be met.
- Decision body
- Kline Township Board of Supervisors, which decides the preliminary and final land development plan after review by the Kline Township Planning Commission. DEP and the Schuylkill County Conservation District handle stormwater and other state permits.
- Top issues
- Residents worry most about round-the-clock noise and Amazon's request to exempt its diesel backup generators from the township noise ordinance, with the nearest home about 600 feet from the buildings. They also raise water, since Amazon may use up to 100,000 gallons a day for cooling but gave no annual estimate, along with the McAdoo Superfund site down the road, limits on who may speak at hearings, and nondisclosure agreements signed by county officials.
- Key opponents
- Kline Township residents calling for a moratorium, joined by people from nearby communities, including Sugarloaf Township in Luzerne County, who rallied outside the July 1, 2026 hearing. Former state House Majority Leader Todd Eachus was removed by police from the June 30 hearing after trying to speak as a nonresident.
- Key supporters
- Amazon; Schuylkill County Commissioners Chairman Larry Padora, who has encouraged data centers on old coal lands and industrial sites to ease property taxes; and PPL, whose representative testified that customers shouldn't see rate increases from data center growth.
How we got here
Brewster Land Co. first proposed warehouses on the Devil's Mountain site around 2021. The state accepted Amazon's data center project into Fast Track on May 22, 2025, and deeds reported in July 2025 showed Amazon Data Services had bought the land for about $178.6 million. An overflow crowd led the township to cancel Amazon's December 2025 introduction, which was held instead on January 17, 2026 at the McAdoo-Kelayres school. Amazon briefed county commissioners on June 17, 2026, and the planning commission opened hearings on June 30, 2026 under heavy security, with public comment limited to residents and property owners. Supervisors extended the plan deadline to September 30, 2026, the state removed data centers from Fast Track on August 18, and the planning commission recommended conditions on September 28, 2026.
Update, October 26, 2026. On September 30, 2026 the Kline Township supervisors voted unanimously to approve Amazon's data center campus plans with the planning commission's nine-page list of conditions covering noise, emergency response, electrical infrastructure, water and wastewater, environmental protections, construction, long-term operations, financial security and outside agency approvals. Supervisor Gary Perna Jr. said the conditions reflect the work of the planning commission, zoning and the engineers. FOX56 reported Amazon still has to complete the township's zoning and pre-construction processes and the state's pre-construction process before construction can begin.