CoreWeave's AI data center is going up in Lancaster city, and neighbors are fighting the second building
The number that mattersDEP's draft air permit covers 176 diesel emergency generators of 3,250 kilowatts each, with estimated emissions of 83 tons a year of nitrogen oxides and 45,000 tons a year of carbon dioxide.
- Developer
- Chirisa Technology Parks, co-developing with Machine Investment Group. The city says the properties are owned by Greenfield Road Owner, LLC (216 Greenfield Road) and Harrisburg Place Owner, LLC (1375 Harrisburg Pike), both Chirisa subsidiaries. Funds managed by Blue Owl Capital formed a $4 billion joint venture with the developers, and a Turner and Wohlsen joint venture is building the first phase.
- Tenant
- CoreWeave (NASDAQ: CRWV) is the named tenant. CoreWeave says it will commit up to $6 billion to equip the Lancaster data center, starting at 100 megawatts with potential to expand to 300 megawatts.
- Current stage
- The first building at 216 Greenfield Road has been under construction since June 2025 inside the old plant's footprint, and LNP reported on September 30, 2026 that it's set for completion late next year. The planning commission gave the second Greenfield Road building conditional preliminary approval on July 1, 2026, but it still needs final approval and faces a residents' appeal that a judge put on hold on September 21, 2026. The state Department of Environmental Protection is reviewing an air quality application for that building's 84 diesel backup generators, which would bring the campus to 156. Plans for a building at 1375 Harrisburg Pike have been submitted.
- Decision body
- Lancaster City Planning Commission (land development plans for the second Greenfield Road building and Harrisburg Pike), Lancaster City Zoning Hearing Board (appeals), Lancaster City Council (benefits agreement and zoning rules), Lancaster County Court of Common Pleas (the developers' lawsuits), and the Pennsylvania DEP (air permits for the backup generators).
- Top issues
- Emissions and testing of 176 diesel backup generators, noise at nearby homes and parks, how much electricity the campus draws and who pays for PPL grid upgrades, water use, whether the city should have required a zoning hearing, and whether the community benefits agreement can be enforced.
- Key opponents
- Lancaster Residents Against Glut and Exhaust (Lancaster RAGE), a residents' group that listed 25 members, many within half a mile of the site, filed the 2026 appeal of the second building's approval. Council member Janet Diaz cast the only vote against the benefits agreement in November 2025. More than 40 people spoke when council adopted data center rules in July 2026.
- Key supporters
- CoreWeave, Chirisa Technology Parks, Machine Investment Group and Blue Owl. Council President Amanda Bakay backed the benefits agreement for its quality-of-life protections, and Lancaster City Alliance and EDC Lancaster County spoke in support. Then-Mayor Danene Sorace's administration negotiated the agreement and said its terms couldn't have been won through zoning.
How we got here
The developers bought the two former Donnelley-LSC printing plants, which closed in 2023, and announced data center plans in February 2025. DEP received the air permit application for 216 Greenfield Road on May 14, 2025, and the city approved the first building's permit in June 2025. CoreWeave announced on July 15, 2025, at the Pennsylvania Energy and Innovation Summit in Pittsburgh, that it would commit up to $6 billion to equip the site, with about 600 construction jobs and about 70 full-time roles at launch growing to about 175. A Turner and Wohlsen joint venture won the construction contract, and Blue Owl formed a $4 billion joint venture with the developers in August 2025. City Council asked the solicitor to draft data center rules on August 15, 2025. DEP published the draft air permit on November 15, 2025. Council approved a community benefits agreement 6-1 on November 20, 2025, with $20 million for economic development and sustainability, a 100 percent clean energy requirement for the first 10 years, a noise standard at existing ambient levels, and a 20,000 gallon per day water cap per campus. A judge ruled for the developers on December 22, 2025 in their suit against a resident's zoning appeal. Council adopted data center zoning rules 7-0 on July 14, 2026, which don't apply to these two sites. The planning commission conditionally approved the second Greenfield Road building on July 1, 2026, Lancaster RAGE appealed, and a judge stayed the zoning hearing on September 21, 2026.
Update, October 26, 2026. On September 30, 2026 LNP reported that DEP is reviewing an air quality application for 84 diesel backup generators for the second Greenfield Road building, with public comments accepted through October 26, 2026. Combined with the first building's 72 generators, the campus would have 156, with annual nitrogen oxide emissions of 99.03 tons, just under the 100-ton level that would require a federal major source permit.