CoreWeave Lancaster Data Center

Lancaster City, Lancaster County

Chirisa Technology Parks and Machine Investment Group are turning two former R.R. Donnelley printing plants into the Lancaster AI Hub for tenant CoreWeave, with an initial 100 megawatts that CoreWeave says could grow to 300 megawatts.

Active / ApprovedLargeGrid HyperscaleBrownfieldS Central
At a glance

The project by the numbers

StatusUnder Construction
Capacity300 MW
Water (max)0.04 MGD
Capex$ 6 B
Permanent jobs, as claimed150
First announced2025-07-15
Target online2027

CoreWeave's AI data center is going up in Lancaster city, and neighbors are fighting the second building

The number that mattersDEP's draft air permit covers 176 diesel emergency generators of 3,250 kilowatts each, with estimated emissions of 83 tons a year of nitrogen oxides and 45,000 tons a year of carbon dioxide.
Developer
Chirisa Technology Parks, co-developing with Machine Investment Group. The city says the properties are owned by Greenfield Road Owner, LLC (216 Greenfield Road) and Harrisburg Place Owner, LLC (1375 Harrisburg Pike), both Chirisa subsidiaries. Funds managed by Blue Owl Capital formed a $4 billion joint venture with the developers, and a Turner and Wohlsen joint venture is building the first phase.
Tenant
CoreWeave (NASDAQ: CRWV) is the named tenant. CoreWeave says it will commit up to $6 billion to equip the Lancaster data center, starting at 100 megawatts with potential to expand to 300 megawatts.
Current stage
The first building at 216 Greenfield Road has been under construction since June 2025 inside the old plant's footprint, and LNP reported on September 30, 2026 that it's set for completion late next year. The planning commission gave the second Greenfield Road building conditional preliminary approval on July 1, 2026, but it still needs final approval and faces a residents' appeal that a judge put on hold on September 21, 2026. The state Department of Environmental Protection is reviewing an air quality application for that building's 84 diesel backup generators, which would bring the campus to 156. Plans for a building at 1375 Harrisburg Pike have been submitted.
Decision body
Lancaster City Planning Commission (land development plans for the second Greenfield Road building and Harrisburg Pike), Lancaster City Zoning Hearing Board (appeals), Lancaster City Council (benefits agreement and zoning rules), Lancaster County Court of Common Pleas (the developers' lawsuits), and the Pennsylvania DEP (air permits for the backup generators).
Top issues
Emissions and testing of 176 diesel backup generators, noise at nearby homes and parks, how much electricity the campus draws and who pays for PPL grid upgrades, water use, whether the city should have required a zoning hearing, and whether the community benefits agreement can be enforced.
Key opponents
Lancaster Residents Against Glut and Exhaust (Lancaster RAGE), a residents' group that listed 25 members, many within half a mile of the site, filed the 2026 appeal of the second building's approval. Council member Janet Diaz cast the only vote against the benefits agreement in November 2025. More than 40 people spoke when council adopted data center rules in July 2026.
Key supporters
CoreWeave, Chirisa Technology Parks, Machine Investment Group and Blue Owl. Council President Amanda Bakay backed the benefits agreement for its quality-of-life protections, and Lancaster City Alliance and EDC Lancaster County spoke in support. Then-Mayor Danene Sorace's administration negotiated the agreement and said its terms couldn't have been won through zoning.

How we got here

The developers bought the two former Donnelley-LSC printing plants, which closed in 2023, and announced data center plans in February 2025. DEP received the air permit application for 216 Greenfield Road on May 14, 2025, and the city approved the first building's permit in June 2025. CoreWeave announced on July 15, 2025, at the Pennsylvania Energy and Innovation Summit in Pittsburgh, that it would commit up to $6 billion to equip the site, with about 600 construction jobs and about 70 full-time roles at launch growing to about 175. A Turner and Wohlsen joint venture won the construction contract, and Blue Owl formed a $4 billion joint venture with the developers in August 2025. City Council asked the solicitor to draft data center rules on August 15, 2025. DEP published the draft air permit on November 15, 2025. Council approved a community benefits agreement 6-1 on November 20, 2025, with $20 million for economic development and sustainability, a 100 percent clean energy requirement for the first 10 years, a noise standard at existing ambient levels, and a 20,000 gallon per day water cap per campus. A judge ruled for the developers on December 22, 2025 in their suit against a resident's zoning appeal. Council adopted data center zoning rules 7-0 on July 14, 2026, which don't apply to these two sites. The planning commission conditionally approved the second Greenfield Road building on July 1, 2026, Lancaster RAGE appealed, and a judge stayed the zoning hearing on September 21, 2026.

Update, October 26, 2026. On September 30, 2026 LNP reported that DEP is reviewing an air quality application for 84 diesel backup generators for the second Greenfield Road building, with public comments accepted through October 26, 2026. Combined with the first building's 72 generators, the campus would have 156, with annual nitrogen oxide emissions of 99.03 tons, just under the 100-ton level that would require a federal major source permit.

What is at stake

Impacts raised and open questions

Air quality

High

DEP's proposed plan approval covers 176 diesel emergency generators of 3,250 kilowatts each (72 in phase one), each with selective catalytic reduction and a diesel particulate filter. DEP estimated potential emissions of 83 tons per year of nitrogen oxides, 31 tons of carbon monoxide, 13 tons of volatile organic compounds, 4 tons of particulates and 45,000 tons of carbon dioxide.

Pennsylvania Bulletin

Air quality

Medium

DEP draft air permit Nov 15 2025; backup generators.

PA Bulletin

Noise and vibration

Medium

Under the benefits agreement, operations can't exceed existing ambient noise at nearby homes and parks, with testing before and after the sites open. Generators sit in sound-attenuated enclosures and can be tested only in daytime, never on Sundays or federal holidays, according to the city's summary.

City of Lancaster

Energy costs and the grid

Medium

The developer says it's spending about $200 million on electric grid upgrades, including a new PPL substation and switchyard near Pitney Road. PPL told the city that large-load customers pay directly for upgrades only they need, while upgrades with broader reliability benefits are spread among all customers.

WITF (LNP | LancasterOnline)

Jobs and tax claims

Medium

The city's FAQ says Chirisa expects 600 to 1,000 construction jobs at the Greenfield site and up to 350 permanent jobs as the projects scale up. CoreWeave's own figure is about 70 full-time roles at launch, growing to about 175.

City of Lancaster

Water

Low

The agreement caps water use at 20,000 gallons per day per campus, compared with the 100,000 to 125,000 gallons per day the printing plant used on average, and requires closed-loop cooling with no added chemicals, according to the city.

City of Lancaster
Community response

Who is organizing against it

Lancaster Residents Against Glut and Exhaust (Lancaster RAGE)

Lancaster city neighborhoods near 216 Greenfield Road

Tactics: Appealed the planning commission's July 1, 2026 conditional approval of the second Greenfield Road building to the zoning hearing board without a lawyer.

Listed 25 members on its appeal application, many living within half a mile of the site, according to LNP. A judge stayed the hearing on September 21, 2026.

Timeline

How it has unfolded

  • 2025-05-14DEP received the air plan approval application for 176 diesel emergency generators at 216 Greenfield Road. Pennsylvania Bulletin
  • 2025-07-15CoreWeave announced it would commit up to $6 billion to equip a 100 megawatt Lancaster data center with potential to grow to 300 megawatts. CoreWeave investor relations
  • 2025-08-15City Council directed the city solicitor to draft a zoning amendment to regulate data centers. City of Lancaster
  • 2025-09-17The developers asked a judge to block a resident's appeal of the city's zoning determination. Fox Rothschild LLP
  • 2025-10-14Council held the first reading of the draft data center zoning amendment. City of Lancaster
  • 2025-11-15PA Bulletin: DEP CoreWeave draft air permit PA Bulletin
  • 2025-11-20Council approved the community benefits agreement with Chirisa Technology Parks by a 6-1 vote. LNP | LancasterOnline
  • 2025-12-22Judge Thomas B. Sponaugle ruled the zoning officer's letters were advisory and couldn't be appealed, siding with the developers. LNP | LancasterOnline
  • 2026-02-04The planning commission was scheduled to hear an informational presentation on the 735,128 square foot second building at 216 Greenfield Road. LNP | LancasterOnline
  • 2026-06-24Council held its public hearing on the data center zoning amendment. City of Lancaster
  • 2026-07-01The planning commission granted conditional preliminary land development approval for the second data center building at 216 Greenfield Road. LNP | LancasterOnline
  • 2026-07-14Council adopted Administrative Ordinance No. 07-2026, limiting future data centers to the suburban manufacturing district by special exception. City of Lancaster (eCode360)
  • 2026-08-21LNP reported the residents' group had appealed the second building's approval to the zoning hearing board. LNP | LancasterOnline
  • 2026-09-21Judge Thomas B. Sponaugle granted the developers' emergency motion to stay the zoning hearing on the residents' appeal. LNP | LancasterOnline
  • 2026-09-30LNP reports DEP is reviewing an air quality application for 84 diesel backup generators for the second Greenfield Road building, with public comments accepted through October 26, 2026. LNP | LancasterOnline
  • 2026-10-06PPL holds an open house on its Lancaster-area transmission upgrades, which include a 2.1-mile underground line to a new switchyard beside the Greenfield Road campus; construction is expected in 2028 and 2029 and needs state approval. LNP | LancasterOnline
Legal record

Filings and legal actions

  • 2025-09-17
    Zoning appeal and developers' suit to block it Lancaster County Court of Common Pleas; Lancaster City Zoning Hearing Board · n/a

    A resident appealed the zoning officer's February 2025 finding that the data centers are a permitted 'wholesale trade and storage' use. The developers sued to stop the zoning hearing board from hearing it, and Judge Thomas B. Sponaugle ruled the officer's letters were advisory opinions that couldn't be appealed.

    Data center developers (Chirisa Technology Parks and partners) v. a city resident who appealed the zoning determination · Decided for the developers on December 22, 2025; the resident did not appeal to a higher court
  • 2026-08-21
    Zoning appeal and developers' declaratory judgment suit Lancaster County Court of Common Pleas; Lancaster City Zoning Hearing Board · n/a

    Lancaster RAGE appealed the planning commission's July 1, 2026 conditional preliminary approval of the second building at 216 Greenfield Road, arguing it amounted to a zoning determination. The developers sued for a declaratory judgment, saying they have spent about $1.3 billion and that the new ordinance permits data centers with complete applications filed before June 25, 2026.

    Lancaster Residents Against Glut and Exhaust; data center developers (Chirisa Technology Parks and partners) · Zoning hearing stayed by the court on September 21, 2026; suit pending
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.