Chirisa Technology Parks Northpointe Data Center (former BNY Mellon data center, South Buffalo Township)
South Buffalo Township, Armstrong County
Chirisa Technology Parks bought the former BNY Mellon data center at 182 Northpointe Boulevard in 2024 and said it would turn it into a campus of up to 100 MW, but there's no public sign of construction or local filings.
The project by the numbers
Chirisa bought BNY's vacant Freeport-area data center in 2024 with a 100 MW plan, but no work has shown up since
- Developer
- Chirisa Technology Parks (part of Chirisa Investments); CoStar reported the buyer as Chirisa Capital
- Tenant
- No tenant named
- Current stage
- The property changed hands in late 2024 and Chirisa announced a redevelopment plan with a groundbreaking expected in early 2025. We found no township or county filings, permits or construction reports. Chirisa's own website doesn't list the site as of November 2, 2026.
- Decision body
- South Buffalo Township (zoning and permits) and Armstrong County (planning review); no filings found
- Top issues
- Whether the project is still active, how much power it will draw and from where, and whether expansion beyond the existing buildings is planned
How we got here
2006: BNY Mellon builds the data center. 2012: the facility earns Energy Star certification. Late 2024: BNY sells the vacant property to Chirisa for $5.5 million (October 1, 2024 per a public-record page cited in a research submission we received). November 27, 2024: Chirisa confirms the purchase and a plan for up to 100 MW, with groundbreaking expected in early 2025. April 17, 2025: Crestline lists Pittsburgh, PA among Chirisa Technology Parks sites. November 2, 2026: Chirisa's website lists no Pittsburgh or Freeport site.
How it has unfolded
- 2024-11-27Chirisa confirmed it bought the former BNY data center and expects up to 100 MW there; CoStar put the price at $5.5 million. Data Center Dynamics
- 2025-04-17Crestline's financing announcement listed Pittsburgh, PA among Chirisa Technology Parks' sites. Crestline Investors
- 2026-11-02Chirisa's website listed Lancaster as its only Pennsylvania campus, with no Pittsburgh or Freeport site. Chirisa Technology Parks
Coverage of this project
- 2024-11-27 Data Center DynamicsUS bank BNY sells site in Pennsylvania to Chirisa for 100MW data center developmentChirisa confirms the purchase and its plan for an AI-focused campus of up to 100 MW.
Sources
Know your rights
In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Take action
Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →