- Developer
- Capital Power Corporation of Edmonton, Alberta, through its subsidiary Hummel Station, LLC. Capital Power bought the plant from LS Power, closing June 9, 2025, in a US$2.2 billion deal that also included the Rolling Hills plant in Ohio.
- Tenant
- There's no tenant. Hummel sells energy, capacity and grid services into the PJM market on a merchant basis, according to Capital Power, which points to 663 data centers within 200 miles of the plant as a source of demand.
- Current stage
- Approved. PJM selected the 32.4 megawatt uprate in its Reliability Resource Initiative in May 2025 with a requested in-service date of 2027. DEP published its intent to approve the turbine upgrades on December 6, 2025, took public comments until January 5, 2026, and issued the plan approval on February 5, 2026. The plan approval expires August 4, 2027. Capital Power's second quarter 2026 report says the uprate is still planned.
- Decision body
- Pennsylvania Department of Environmental Protection, Northcentral Regional Office (air quality plan approval 55-00026C), and PJM Interconnection for the added grid capacity.
- Top issues
- Air emissions from running a large gas plant harder (DEP's approval caps the three turbines at 193.5 tons of nitrogen oxides and 42.69 tons of volatile organic compounds a year), regional capacity prices that cleared at PJM's cap in the plant's zone, and the growth in data center electricity demand that Capital Power cites as a reason to expand, including its stated hope to partner with data center companies.
- Key opponents
- No organized opposition to the uprate has been reported.
- Key supporters
- Capital Power; PJM Interconnection, which picked the uprate as one of 51 projects in its Reliability Resource Initiative to add capacity quickly; and U.S. Sen. Dave McCormick, who welcomed Capital Power's Pennsylvania investment in July 2025 as "transformative," according to PoliticsPA.
How we got here
Hummel Station began commercial operation in 2018, according to Capital Power. On April 14, 2025 Capital Power announced it would buy the 1,124 megawatt plant and Ohio's Rolling Hills plant from LS Power for US$2.2 billion combined, and said it planned a 30 megawatt uprate at Hummel in 2026 and 2027. Hummel Station, LLC applied to DEP for a plan approval for turbine hardware upgrades on May 2, 2025, the same day PJM selected the 32.4 megawatt uprate (project AH1-705, Sunbury 500 kV, Snyder County) in its Reliability Resource Initiative. FERC approved the acquisition June 2, and the deal closed June 9, 2025. In mid-July 2025, PoliticsPA, WKOK and The Daily Item reported that Capital Power valued the Hummel purchase at $1.3 billion, planned to invest more than $3 billion in the plant over 10 years and hoped to partner with data center companies. DEP published its intent to issue the plan approval on December 6, 2025, with comments due January 5, 2026, and issued plan approval 55-00026C on February 5, 2026. The approval notice ran in the Pennsylvania Bulletin on February 28.