All Pennsylvania projects
Withdrawn / Denied

Blakely Borough Data Center (early stage)

Blakely Borough, Lackawanna County

A 209-acre data center campus proposed in 2025 for mostly residential-zoned land behind West Mountain Road in Blakely Borough, Lackawanna County, which the developers withdrew in September 2025 after residents organized against it.

Withdrawn / DeniedMega scaleGrid HyperscaleGreenfieldNEPA
At a glance

The project by the numbers

StatusWithdrawn
Capacity1500 MW
Building area586,000 sq ft
Site209 acres
First announced2025-08-04
Target onlineTBD

Blakely data center withdrawn in 2025; borough has since written strict data center rules

The number that mattersThe developers said PPL had committed 1.5 gigawatts of power to the Blakely site shortly before the August 2025 information session.
Developer
Jim Marzolino, president of Kriger Construction, and the landowner, who filed as the applicant, presenting themselves as co-developers. Michael Mey of Mey & Sulla in Dunmore represented them.
Tenant
No end user was named before the project was withdrawn.
Current stage
Withdrawn in September 2025. Since then Blakely adopted a data center overlay in November 2025, re-adopted its zoning ordinance in September 2026, and in October 2026 took up rules for connecting large power users to the borough's own electric system. Officials said in November 2025 that no developer had contacted them about a new proposal.
Decision body
Blakely Borough Council, with review by the Blakely Borough Planning Commission.
Top issues
Putting a data center on land zoned for homes, air pollution and health worries, round-the-clock noise, water and electricity use, tree clearing on the hillside, and the borough's role as the local electric provider.
Key opponents
Blakely residents, especially the roughly 30 households nearest the site, who ran a door-to-door petition and delivered it to council on Sept. 15, 2025.
Key supporters
The developers, who said the project would bring more than $121 million a year in local utility fees and taxes, about 500 construction jobs and well-paid permanent jobs.

How we got here

Aug. 4, 2025: rezoning request goes to the planning commission. Aug. 13, 2025: public information session with the developers. Sept. 7, 2025: residents collect petition signatures. Sept. 12, 2025: developers withdraw. Sept. 15, 2025: petition presented to council; the Sept. 16 hearing is canceled. Nov. 17, 2025: council unanimously adopts a data center overlay. Sept. 21, 2026: council re-adopts the zoning ordinance with amendments. Oct. 19, 2026: council takes up large-load electric interconnection rules.

What is at stake

Impacts raised and open questions

Energy costs and the grid

High

At the August 2025 information session the developers said PPL had committed 1.5 gigawatts of power to the Blakely project.

Blakely Borough

Visual and light

Medium

The plan called for a 586,000-square-foot building footprint with buildings up to 70 feet tall on a wooded hillside, with fence lines 470 to 620 feet from homes, according to the developers.

Blakely Borough

Air quality

Medium

Residents circulating the petition said the campus would sit 400 to 500 feet from their homes and raised concerns about air particles, noise and pollution.

FOX56 (WOLF)

Jobs and tax claims

Medium

The developers projected about 500 construction jobs over two to four years and more than $121 million a year in local utility fees and property taxes for the borough, Valley View School District and county.

FOX56 (WOLF)
Community response

Who is organizing against it

Blakely Borough residents

Borough · Founded 2025 · 1,800 signatures

Tactics: Door-to-door petition (more than 300 signatures by Sept. 7, 2025), organizing in local forums, meetings and visible protests, pressure on borough leaders not to grant an additional developer forum

One of Pennsylvania's clearest early wins. Borough leaders declined the developers' request for another informational meeting, the developers withdrew on Sept. 12, 2025, and the Sept. 16 zoning hearing was canceled.

Blakely residents' petition drive

Blakely Borough, especially homes near West Mountain Road · Founded 2025-09 · 300 signatures

Tactics: Petition signing at the Blakely Recreation Complex and door to door; delivered to council Sept. 15, 2025

FOX56 reported more than 300 signatures by Sept. 7, 2025, and later said all but one of about 30 nearest homes signed.

Timeline

How it has unfolded

  • 2025-08-04Rezoning request for an AI data center on land behind the Assembly of God Church goes before Blakely's planning commission. Blakely Borough
  • 2025-08-13Developers present a 209-acre plan with a 586,000-square-foot footprint and 70-foot buildings at a public information session. Blakely Borough
  • 2025-09-07Volunteers collect more than 300 petition signatures against rezoning the residential site. FOX56 (WOLF)
  • 2025-09-12Developers withdraw the zoning request, saying the borough declined to schedule a second informational meeting. FOX56 (WOLF)
  • 2025-09-15Petition and letters on the data center are presented to council; the Sept. 16 zoning hearing is canceled. Blakely Borough
  • 2025-11-17Council unanimously approves a zoning overlay that sets rules for any future data center. FOX56 (WOLF)
  • 2026-09-21Council is scheduled to pass the updated zoning ordinance with amendments, adopted as Ordinance 8 of 2026. Blakely Borough
  • 2026-10-19Council agenda includes Ordinance 9 of 2026 on rules for connecting large-load customers to the borough electric system. Blakely Borough
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →