Project Atlas would put three data center buildings of about 492,000 square feet each on roughly 410 acres at 2493 North Cedar Crest Boulevard, directly across from Parkland High School, for a tenant that hasn't been named. The plan started at six buildings and about 5 million square feet.

ContestedGrid HyperscaleGreenfieldLV
At a glance

The project by the numbers

StatusUnder Review
Capacity725 MW
Building area1,520,000 sq ft
Site410.65 acres
Capex$ 8.9 B
Permanent jobs, as claimed250
First announced2025-12-16
Target onlineTBD

Three hyperscale data center buildings across the street from a high school

The number that mattersParkland Superintendent Mark Madson described the proposed footprint as roughly equivalent to ten Parkland High Schools, and wrote that the district finds the proposal unacceptable as presented.
Developer
CDE Acquisitions, LLC of Atlanta, an affiliate of Edged Data Centers (Edged US), working with Scannell Properties; Jeras Corporation owns the land
Tenant
Undisclosed. No end user has been named.
Current stage
Preliminary plan (Major Plan 2025-109) under Planning Commission review with no decision. At a special meeting at Parkland High School on September 23, 2026 the applicant's attorney said it wasn't seeking approval and would return with a revised plan, and the deadline for the township to act was extended from October 31 to December 31. No new Planning Commission date has been set. On October 20, 2026 the Parkland School Board voted unanimously for a resolution opposing the project, with board members saying their concern is its location near Parkland High School. DEP has made a tentative decision to issue the construction stormwater permit and will hold a public meeting and hearing November 23 on that permit and the Chapter 105 water obstruction and encroachment permit.
Decision body
South Whitehall Township Planning Commission (recommendation) and Board of Commissioners (preliminary plan decision); Pennsylvania DEP Northeast Regional Office (Chapter 105 and construction stormwater permits)
Top issues
Siting directly across from Parkland High School; a dedicated substation and new PPL transmission lines; emergency diesel generators; noise and requests for continuous monitoring; karst geology with closed depressions and surface pits; clearing about 72 acres of woods; stormwater from 415.84 acres of earth disturbance; traffic on Cedar Crest Boulevard and Mauch Chunk Road; fiscal claims the township's economist called not credible; the demand for a hearing with cross-examination; an undisclosed end user
Key opponents
South Whitehall Civic Alliance, headed by Greg Sussman and represented by counsel; Parkland School District administration; Food & Water Watch; state Sen. Jarrett Coleman and his opponent, Lehigh County Controller Mark Pinsley, who both told the September 23 meeting the project was bad for the township
Key supporters
Edged US, which says the campus would bring more than $8.9 billion in investment, about $16.5 million a year in taxes and a $99.5 million annual economic impact for the township, and pledges to pay for all power and infrastructure upgrades. Earlier projections put about $11.5 million a year toward the Parkland School District.

How we got here

December 16, 2025: the Lehigh Valley Planning Commission says it has received a six-building, 5.1 million sq ft plan. January 22, 2026: the LVPC reviews it and unanimously approves a comment letter. January 28: DEP receives the Chapter 105 joint permit application. February 6: township staff and the township engineer don't recommend approval, and the February 12 Planning Commission review is pulled so the applicant can respond. February 17: PPL's plans for a nearby substation and new transmission lines become public. May 5: Parkland's superintendent writes that the district finds the proposal unacceptable; May 12 school board workshop. Late May: a revised three-building plan is posted, and the zoning officer's May 30 review recommends denial for noncompliance. June 11: review postponed while the township looks for a larger venue. June 25: the LVPC reviews the revised plan. July 9: first public presentation draws a standing-room-only crowd to Springhouse Middle School, where a township engineer says he does not recommend approval and the South Whitehall Civic Alliance asks for a formal hearing with cross-examination. August 4: DEP receives the stormwater permit application. September 9: three township advisory boards review the plan at Parkland High School. September 23: special Planning Commission meeting at Parkland High School; the applicant says it will revise the plan and the decision deadline moves to December 31. October 17: DEP announces a tentative decision to issue the stormwater permit and a November 23 public meeting and hearing.

Update, October 26, 2026. On October 20, 2026 the Parkland School Board voted unanimously to adopt a resolution opposing Project Atlas. The resolution puts the district on record against the project and authorizes district administrators and legal counsel to advocate for the district as the plan moves through the township's review. Board members said their concern is the site's location near Parkland High School.

What is at stake

Impacts raised and open questions

Traffic

High

LVPC traffic study projects about 4,000 weekday trips (371 new AM-peak) for the about 5M sq ft campus across from Parkland High School; recommended noise <55 dB.

WFMZ-TV

Public safety

High

The campus is proposed directly across from Parkland High School. The district superintendent wrote that the proposal is unacceptable as presented and described a footprint roughly equivalent to ten Parkland High Schools.

Lehigh Daily

Noise and vibration

High

Residents cite noise and around-the-clock operation among their central objections to a hyperscale campus sited across from a school and near homes.

The Morning Call

Air quality

High

Presentation materials include backup diesel generators alongside a dedicated electric substation on a site of more than 400 acres.

Lehigh Daily

Energy costs and the grid

High

A campus of this scale with its own substation adds major load in the PPL service territory, in a region where rising electricity prices have become a central political issue.

CNBC

Water

High

DEP's notices cover 415.84 acres of earth disturbance, with stormwater going to unnamed tributaries of Coplay Creek, Jordan Creek and wetlands. DEP has made a tentative decision to issue the construction stormwater permit, with comments due November 16.

Pennsylvania Bulletin / Pennsylvania DEP

Air quality

High

The zoning officer's May review said the plan identifies hundreds of emergency diesel-fueled generators and found it noncompliant because the applicant hadn't shown that smoke, fumes, noise, heat, glare or vibration would stay within the lot lines.

WFMZ-TV 69 News

Traffic

Medium

A new road is proposed connecting Cedar Crest Boulevard with Mauch Chunk Road. The applicant’s engineer told the commission the project is not generating traffic, a claim residents dispute; earlier materials referenced thousands of additional daily vehicle trips.

Lehigh Valley Public Media

Water

Medium

The applicant’s attorney told the commission the project does not use any additional water from the local supply. Residents have asked for that claim to be tested through a formal hearing with cross-examination.

Lehigh Valley Public Media

Property values

Medium

Residents have said publicly they worry the campus would make nearby homes difficult to sell.

CNBC

Water

Medium

The township's engineering consultant noted the site's karst geology, including numerous closed depressions and two surface pits, and wrote that it had directly observed more karst features on site, including a third surface pit near the center, that weren't shown on the plans.

WFMZ-TV 69 News

Visual and light

Medium

The applicant plans to clear about 72 acres of existing woodland and reforest about 12 acres elsewhere on the property. Two historic structures would be removed, with an existing barn restored.

WFMZ-TV 69 News

Energy costs and the grid

Medium

PPL bought more than 30 acres near Huckleberry Road and Herman Lane for a new substation, with three new transmission lines planned to run about 1.5 miles east to a new customer facility. The plans need approval from the Public Utility Commission.

WFMZ-TV 69 News

Traffic

Medium

The LVPC's June review of the revised plan projects 1,154 weekday trips, including 142 new morning-peak and 126 new evening-peak trips, and says signals may be needed where the new road meets existing roads near Parkland High School.

WFMZ-TV 69 News

Jobs and tax claims

Low

The developer projects roughly $9 billion in investment and more than $16 million in annual tax revenue, including about $11.5 million to the Parkland School District. Permanent staffing at hyperscale campuses is typically small relative to footprint.

Lehigh Valley Public Media

Jobs and tax claims

Low

When the plan shrank from six buildings to three, the anticipated permanent workforce fell from 440 to 250 employees and parking from 966 spaces to 399.

WFMZ-TV 69 News
Community response

Who is organizing against it

South Whitehall Civic Alliance

Township · Founded 2026

Leaders: Greg Sussman, head of the South Whitehall Civic Alliance; represented by attorneys Jason Aldrich and Jason Ulrich

Tactics: Community fundraising to retain land-use counsel for the whole township, a formal demand for a hearing process with cross-examination and resident expert testimony, packing planning commission meetings, and coordinating with Parkland School District concerns

The Alliance describes itself as representing the people of South Whitehall rather than showing up as an angry mob, and is raising money so residents can be represented by attorneys at the table. Parkland Superintendent Mark Madson has separately written that the district finds the proposal unacceptable as presented.

Timeline

How it has unfolded

  • 2025-12-16The LVPC says it has received a hyperscale data center application for 2493 N. Cedar Crest Blvd.: six buildings totaling 5.1 million sq ft. WFMZ-TV 69 News
  • 2026-01-22The LVPC reviews the six-building plan and unanimously approves a comment letter noting the site is designated for farmland preservation in its regional plan. Lehigh Valley Public Media
  • 2026-01-28DEP receives the Water Obstruction and Encroachment Joint Permit Application (E3902226-002) for Project Atlas through its SPEED program. Pennsylvania Bulletin / Pennsylvania DEP
  • 2026-02-06Staff review of Major Plan 2025-109 does not recommend approval because of outstanding comments, and the township engineer also does not recommend approval. South Whitehall Township
  • 2026-02-12The scheduled Planning Commission review is canceled after the project is pulled so the applicant can respond to the township's 101-page review. WFMZ-TV 69 News
  • 2026-02-17PPL's plans for a new substation north of Huckleberry Road and three new transmission lines running about 1.5 miles east to a new customer facility become public; they need PUC approval. WFMZ-TV 69 News
  • 2026-05-05Superintendent Mark Madson writes to the township manager, the Lehigh County Authority, PPL Electric Utilities and the developer: "Based on what is proposed, we find the proposal to be unacceptable" Lehigh Daily
  • 2026-05-12District workshop reviews the proposal; Madson describes a footprint roughly equivalent to ten Parkland High Schools and residents urge the board to take a stronger public stance Lehigh Daily
  • 2026-05-30The zoning officer's review of the revised three-building plan recommends denial for noncompliance, citing missing information, hundreds of emergency diesel generators and a proposed warehouse that isn't a permitted accessory use. WFMZ-TV 69 News
  • 2026-06-25The LVPC reviews the revised plan, says it addressed numerous comments but that outstanding issues remain, and projects 1,154 weekday trips. WFMZ-TV 69 News
  • 2026-07-09First public presentation of Project Atlas draws a standing-room-only crowd to Springhouse Middle School for a nearly three-hour session; a township engineer says he does not recommend approval, and residents cheer Lehigh Valley Public Media
  • 2026-07-09Alliance attorneys ask the township for a formal hearing process that would let residents’ experts question the developer’s witnesses and present testimony; no action is taken Lehigh Valley Press
  • 2026-07-14An executive is "no longer involved" with Project Atlas after residents publicize offensive text messages sent during the planning commission meeting, according to the developer Lehigh Valley Public Media
  • 2026-07-31Project Atlas is left off the August 13 Planning Commission agenda, and the township sets a special Planning Commission session for September 23 at Parkland High School. Lehigh Valley Public Media
  • 2026-08-04DEP receives the Individual NPDES construction stormwater permit application (PAD390390) for Project Atlas. Pennsylvania Bulletin / Pennsylvania DEP
  • 2026-09-04Township staff recommend against approving the preliminary plan because of outstanding review comments and ask the applicant for a revised submission. Lehigh Valley Press
  • 2026-09-09The Park and Recreation Board, Environmental Advisory Council and Landscape and Shade Tree Commission review the plan at Parkland High School after 90 minutes of public comment and send comments to the developer. WFMZ-TV 69 News
  • 2026-09-23At a special meeting at Parkland High School the applicant's attorney says it isn't seeking approval and will return with a revised plan; the commission takes the proposal under advisement and the decision deadline moves from October 31 to December 31. WFMZ-TV 69 News
  • 2026-10-17DEP schedules a public meeting and hearing November 23 at Cedar Crest College on the Chapter 105 permit; stormwater permit comments due November 16 PA Environment Digest
  • 2026-10-17DEP publishes a tentative decision to issue the construction stormwater permit for 415.84 acres of earth disturbance, with comments taken for 30 days. Pennsylvania Bulletin / Pennsylvania DEP
  • 2026-10-20The school board votes unanimously for a resolution opposing Project Atlas and authorizing district administrators and legal counsel to advocate for the district during the township's review. Lehigh Valley Press
Legal record

Filings and legal actions

  • 2026-05
    Land development plan South Whitehall Township Planning Commission · n/a

    Land development application for a hyperscale data center campus on roughly 406 to 410 acres at 2493 North Cedar Crest Boulevard. Township staff and consultants are continuing review, and numerous ordinance requirements remain to be addressed before the commission considers a recommendation.

    CDE Acquisitions, LLC, an affiliate of Edged Data Centers (Edged US) · Under review
  • 2026-07-09
    Request for formal hearing South Whitehall Township · n/a

    The Alliance, through counsel, asked the township to convene a formal hearing process allowing residents to question the developer’s witnesses under oath and present expert testimony of their own. No action was taken at the July 9 meeting.

    South Whitehall Civic Alliance · Pending
  • 2026-08-04
    DEP permit application (Individual NPDES construction stormwater permit) Pennsylvania DEP, Northeast Regional Office · PAD390390

    Stormwater permit for a data center campus with access roads, utilities, stormwater and security infrastructure, covering 415.84 acres of earth disturbance with discharges to an unnamed tributary of Coplay Creek.

    CDE Acquisitions, LLC (applicant) · Tentative decision to issue published October 17, 2026; comments due November 16; public meeting and hearing November 23
  • 2026-01-28
    DEP permit application (Chapter 105 water obstruction and encroachment joint permit) Pennsylvania DEP, Northeast Regional Office · E3902226-002

    Joint permit application received through DEP's SPEED program; receiving waters listed as unnamed tributaries to Coplay Creek, Jordan Creek and other wetlands.

    CDE Acquisitions, LLC (applicant) · Under review; public meeting and hearing November 23, 2026 at Cedar Crest College
News

Coverage of this project

Sources

Know your rights

In Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.

Know your rights →

Take action

Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.

How communities push back →