Energy costs and the grid
HighNRDC estimated PECO ratepayers may absorb $9.1B in costs by 2033; about $70/mo PJM household bill projection.
FERCFalls Township, Bucks County
Amazon Web Services is building a campus of about 10 buildings and roughly 2 million square feet on about 250 acres at the Keystone Trade Center, the former U.S. Steel Fairless Works, with the first sections expected to start running in late 2026.
LevittownNow first reported a data center plan for the Keystone Trade Center in August 2024. Supervisors approved the digital infrastructure campus in March 2025 after sparsely attended meetings, and Amazon confirmed its role on June 9, 2025 as part of a $20 billion Pennsylvania commitment. PECO filed its transmission service agreement with Amazon at FERC on Sept. 23, 2025. As construction moved ahead, opposition grew through 2026: a petition launched in May, about 50 residents protested before the June 22 supervisors meeting, and a nearly four-hour town hall followed on July 14. Supervisors started a 180-day zoning review on July 27. The comment period on the generator permit closed Aug. 17 with 1,236 comments, and on Aug. 18 Gov. Shapiro removed data centers from fast-track permitting.
Update, October 26, 2026. On April 16, 2026 the Public Utility Commission approved two short PECO 230 kV taps (docket A-2025-3058203) from the Emilie to Ford Mill lines to a customer-owned "Clinker Substation" and data center next to the Ford Mill Generation Station, the Fairless Energy Center on Energy Drive, for 240 MW at first and 600 MW anticipated, with service planned for the first quarter of 2027. The order doesn't name the customer. The plant sits beside the Keystone Trade Center, where NorthPoint subdivided a tract at Sorrells Boulevard and Energy Drive in September 2025 for a realignment of utilities, and PECO said on July 14, 2026 that the Amazon campus's next phase connects directly to its high-voltage transmission system.
NRDC estimated PECO ratepayers may absorb $9.1B in costs by 2033; about $70/mo PJM household bill projection.
FERCAmazon has applied to DEP for 280 natural gas-fired backup generators of 4,287 horsepower each plus three diesel units, after DEP approved 72 diesel-fired emergency engines in 2025. Amazon says the generators are for backup power only and will have pollution controls.
Philadelphia InquirerConstruction traffic on existing Keystone Trade Center / Tyburn Rd corridor.
FERCDEP's regional air quality manager said Amazon committed to operate as a synthetic minor source, keeping nitrogen oxides and volatile organic compounds below 25 tons a year. At the town hall a resident pointed out that Bucks County has a failing ozone grade from the American Lung Association.
LevittownNow.comThe Morrisville Municipal Authority says evaporative cooling will draw from the old U.S. Steel raw water system at up to 4.4 million gallons a day at peak, averaging about 135,000 gallons a day, with about 40 percent returned to the Delaware River through an industrial wastewater plant. Drinking water use is about 19,000 gallons a day.
LevittownNow.comA resident acoustical engineer estimated that if all generators ran at once during a long outage, noise within about half a mile could reach 65 decibels. Amazon says its modeling shows no impact because the nearest home is more than 5,000 feet away.
LevittownNow.comAWS expects 400 to 500 permanent workers within two years and projects 1,550 full-time jobs eventually, plus thousands of construction workers, according to LevittownNow's town hall coverage.
LevittownNow.comResidents asked whether local fire and police have the training and plans for a major incident at the campus. Amazon says its buildings have fire suppression systems, it trains local responders as construction proceeds, and the site will have an emergency response plan.
LevittownNow.comTactics: Petition, protests, public comment at township and county meetings, push for a local freeze and a curative amendment
The petition asks for a pause on data center approvals, protection from higher electric rates, air quality monitoring and noise limits. The Philadelphia Inquirer put signatures at nearly 5,000 in August 2026.
Leaders: Alex Beauchamp, Northern Regional Director
Tactics: Organized 407 public comments asking DEP to reject the generator permit; pushes for a statewide moratorium
Its release says Amazon has already installed 76 diesel generators at the site.
Transmission service agreement for AWS Falls Township facility.
PECO, AWS, Bowring (IMM) · IMM protest filed Nov 1 2025; pendingApplication to add 280 natural gas-fired backup generator engines of 4,287 horsepower each and three diesel generators. Amazon told DEP it would operate as a synthetic minor source, keeping nitrogen oxides and volatile organic compounds under 25 tons a year.
Amazon Data Services Inc. (applicant); DEP · Comment period closed Aug. 17, 2026 with 1,236 comments; the latest reporting we found (Aug. 20) said DEP hadn't set a decision dateSupervisors declared parts of the zoning ordinance substantively invalid to start a 180-day rewrite of data center rules. The township says it doesn't affect the approved Amazon campus.
Falls Township · 180-day review under way; amendments due back to supervisors by about late January 2027Two 230 kV taps of about 0.15 and 0.16 miles from the 220-90 and 220-91 Emilie to Ford Mill lines to a customer-owned Clinker Substation and data center; about $8.13 million; PJM supplemental project s3807.
PECO Energy Company (applicant) · Approved April 16, 2026; docket remains open until PECO files the final project costIn Pennsylvania, the local zoning ordinance sets the route. A conditional use is decided by the elected governing body (supervisors, commissioners or council). A special exception or variance, and an appeal of a zoning officer’s decision, go to the Zoning Hearing Board. Each is a public hearing on a record: affected neighbors can ask for party status, cross-examine witnesses, and appeal. Municipalities can also adopt data center ordinances with enforceable standards.
Know your rights →Organized community opposition is the single most effective check on these projects in Pennsylvania. Show up to hearings, submit comment when it is taken, support legal and expert-witness costs, and press your municipality for a real ordinance. Pennsylvania municipalities cannot simply freeze applications, but a curative amendment under the Planning Code gives them a defined window to fix a defective ordinance.
How communities push back →